Technical Assistance to Nrc,Region Iv,For Preservice Insp, Monthly Ltr Rept for Nov 1986
ML20207N246
Person / Time
Site: South Texas, Comanche Peak, 05000000
Issue date: 12/16/1986
From: Poucher F
ROCKWELL INTERNATIONAL CORP.
To: Westerman T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
CON-FIN-A-0700, CON-FIN-A-700 86DRF-2488, NUDOCS 8701140075
Download: ML20207N246 (4)


Text

. - g,-

Energy Technology Engineering Center Rocketdyne Division Rockwell international Corporation Rockwell Canoga Park, Ca o a International Qgh$0gg (818)700-8200 L OperatedforUS Department of Energy .

k ,l December 16, 1986 In Reply Refer to: 86DRF-2488 Mr. T.F. Westerman, Chief Reactor Safety Branch U. S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76011

Subject:

Monthly Letter Report on ETEC Technical Assistance to V. S.

NRC, Region IV, for Preservice Inspection, FIN A0700

Dear Mr. Westerman:

Enclosed is a monthly business letter report which summarizes the work performed by ETEC on the subject program during the month of November 1986.

Sincerely yours, 87 dh&wl~

F. W. Poucher j0p 224co73 ADOCKhhjjf6 -

Programs Manager PDj6 Energy Technology Engineering Center

Enclosure:

as noted cc w/ encl: R. Ireland, NRC Region IV D. M. Meyer, NRC Region IV M. E. Long, ETEC P0 D. Tomlinson, NRC, Region IV V

} -

\

qvi4 % 5 '

J w -

Enclosure to: 86ETEC-DRF-2488 Page 1

?

MONTHLY REPORT Technical Assistance for Casework Reviews FIN: A0700 NRC Dockets: 50-498-50-446 Contract No.: DE-AC03-76-SF00700 Principal Investigator: R. Fuhrer

Period of Performance: 05-30-86 to 09-30-87 Reporting Period: November 1986

l. PROJECT STATUS Task Order A - Review of Preservice Inspection Activities A. Task

Description:

This task establishes a team of qualified individuals to perform and report the review results of Preservice Inspection Activities at the South Texas Project, Unit 1, and at Comanche Peak, Unit 2. These reviews are to be accomplished in accordance with four NRC supplied inspection modules.

B. Efforts Completed During This Period: None C. Problems or Delays Encountered: None D. Plans for the Next Reporting Period: None. The South Texas Unit 1, portion of the task is complete and the Comanche Peak portion is yet to be defined.

Task Order 8 - Review of IE Bulletin, IE Circulars and Notices and License 10 CFR 50.55(e) Reports ,

A. Task

Description:

This task establishes a two person team consisting of one Mechanical Engineer and one Electrical Engineer to assist the NRC Region IV Office in reviewing IE Bulletins, IE Circulars and notices and License 10 CFR 50.55(e) reports to determine which of these may be closed out. The review will be done in accordance with NRC direction.

B. Efforts Completed During This Period: None scheduled.

C. Problems or Delays Encountered: None.

D. Plans for the Next Reporting Period: Complete the task.

Enclosure to: 86ETEC-DRF-2488 Page 2

.II. FINANCIAL STATUS

1. Total Cost of the Project Total ~ cost of the project is as follows:

Total Funds Balance of Funds Projected Obligated by Fiscal Year Project Cost To Date FY 86 FY 37

$ 90,700 $ 90,700 0 0 B. The total amount of funds expended during the month of November, 1986 and the cumulative through November is as follows:

Period YTD FY Cumulative

a. Direct Labor Staff Effort 0.2 0.2 2.2 (Staff Months)
b. Funds ($000)

Direct Salaries 0.7 0.8 7.4 Materials and Services - -

(Excluding ADP)

. ADP Support - -

Subcontracts - 0.04 9.4(a)

Travel Expenses - - 2.4 Indirect Labor Costs 0.6 0.8 8.5 Other (Specify) - - -

General & Administrative 0.07 0.08 1.6 Fee 0.04 0.04 3.0 TOTAL 1.4 1.8 32.3(36%)

III. FEE REC 0VERY COST STATUS Pursuant to the provisions of NRC Regulations, 10 CFR 170, the total amount of funds expended during the period and the cumulative amount for the program are as in the attachment to this report.

i l

l l

Enclosure to: 86ETEC-DRF-2488 Page 3 FIN: A0700 TITLE: Technical Assistance for Preservice Inspection PERIOD: November, 1986 ,

i COSTS TASK NUMBER PERIOD CUMULATIVE Task Order A:

South Texas, Unit 1 $42.00- $30,941.00 Comanche Peak Task Order B: $1336.00 $ 1336.00 51378.00 532,277.00