ML20207N244

From kanterella
Jump to navigation Jump to search
Ack Receipt of 860829 Response to Re Violations Noted in Insp Repts 50-313/86-18 & 50-368/86-19.Errors in Structure of Response Noted.Addl Info Re Violation B Needed, Per 861222 Discussion W/D Lomax
ML20207N244
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 01/09/1987
From: Gagliardo J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Campbell G
ARKANSAS POWER & LIGHT CO.
References
NUDOCS 8701140073
Download: ML20207N244 (2)


See also: IR 05000313/1986018

Text

_

JAN

9 1987

In Reply Refer To:

Dockets: 50-313/86-18

50-368/86-19

Arkansas Power & Light Company

ATTN: Mr. Gene Campbell

Vice President, Nuclear

Operations

P. O. Box 551

Little Rock, Arkansas

72203

Gentlemen:

Thank you for your letter of August 29, 1986, in response to our letter and

Notice of Violation dated July 25, 1986. We have reviewed your reply and have

identified some major concerns that need to be addressed.

Our first concern is in regard to the structure or make up of the response.

The opening paragraph under the section entitled, " Notice of Violation " is in

actuality the opening paragraph from the Notice of Violation (NOV) in NRC

Inspection Report 50-313:368/86-15 issued on July 23, 1986, and not from our

July 25, 1986, report. The violation that you have categorized as Violation A

is, in fact, Violation B in the NOV of our July 25, 1986, report, and the

,

violation that you have categorized as Violation B is our Violation A.

As a result of our review of your response to Violation B (categorized as

Violation A in your response), we find that additional information, as discussed

with your Mr. D. Lomax (during a meeting with the NRC resident inspector on

December 22,1986) is needed.

The area of concern addressed by this violation

was the number of deficiencies found in the procedures reviewed which place the

adequacy of your procedure review program and the overall quality of your

procedures in question.

Your response focused on the specifics of the examples

of deficiencies and not on the cause of the deficiencies. Your response should

address the root cause of the procedural deficiencies and your actions to

correct the cause and prevent recurrence.

We find that the response to Violation A (categorized as Violation B in your

response) is responsive to the concerns raised in our Notice of Violation. We

will review the implementation of your corrective actions during a future

inspection to determine that full compliance has been achieved and will be

maintained,

000IIjjj{K0500o333

3 07o:09

o

PDR

PI:RPD

C:R

C:RPGs

HEMur

cs

DRifunter

JEGagit rdo

M[@

1T/4 /0%

11/ 6 /8 %

1/7 /f)

/


----


-

-

.

I

Arkansas Power & Light Company

-2-

We would, again, retnind you of the context of the four questions to be answered

in the response to a violation that are contained in the last paragraph of each

Notice of Violation.

Please provide the supplescental information for Violation B

within 30 days of the date of this letter.

Sincerely,

Od bd r 5 9 ny

t

J.E.Cc,y.vda

J. E. Gagliardo, Chief

Reactor Projects Branch

CC:

J. H. Levine, Director

Site Nuclear Operations

Arkansas Nuclear One

P. O. Box 608

Russellville, Arkansas

72801

Arkansas Radiation Control Program Director

bectoDMD(IE01)

bec distrib. by RIV:

RPB

RRI

R. D. Martin, RA

R&SPB

Section Chief (RPD/B)

D. Weiss, RM/ALF

RIV

DRSP

RSB

HIS System

RSTS Operator

Project Inspector

-

-

-

--

- - -

-

-

- -

-

- -

-

-

- -

-

'

,

.

ARKANSAS POWER & LIGHT COMPANY

POST OFFICE BOX 551 UTTLE ROCK. ARKANSAS 72203 (501) 3716

,,

August 29, 1986

.-

3 dM DMIR {

q

v

SEP - 8 g !

'

OCAN088614

Jj

j

'

Mr. J. E. Gagliardo, Chief

,

Reactor Projects Branch

-

U. S. Nuclear Regulatory Commission

Region IV

611 Ryan Plaza Drive, Suite 1000

Arlington, TX 76011

SUBJECT:

Arkansas Nuclear One - Units 1 & 2

Docket Nos. 50-313 and 50-368

License Nos. DPR-51 and NPF-6

Response to Inspection Report

50-313/86-18 and 50-368/86-19

Dear Mr. Gagliardo:

The subject report has been reviewed.

A response to the Notice of Violation

is attached.

Very truly yo

s,

gl

f /~'

J. T

os, Manager

Nuclea Engineering and Licensing

JTE:RJS:1w

Attachment

1otYA3AY

yq-

e.~rr--

MEMSER MiOOLE SOUTH UTILITIES system

\\

.

.

.

NOTICE OF VIOLATION

.

During an NRC inspection conducted during.the period May 1-31, 1986,

MbyM

violations of the NRC requirements were 1Jentified.

The violations involved-

failure to lock a manual valve in positian as required, failure to have

p

adequate controls over the installation of temporary scaffolds in the

p/

,

vicinity of safety-related equipment, and lack of calibration data that

ff

would demonstrate the accuracy of measurement of the admixture liquid

dispenser being utilized at the concrete supplier's facility.

The specific

findings and AP&L's response to each are listed below.

,

A.

10 CFR 50, Appendix B. Criterion V states, in part, " Activities

affecting quality shall be prescribed by documented instructions,

procedures, ... of a type appropriate to the circumstances and shall be

accomplished in accordance with these instructions, procedures, ... ANO

procedures 1000.04, " Procedural Program Requirements," Revision 20, and

1000.06, " Procedure Review, Approval, and Revision Control," Revision

22, implemented these requirements.

Contrary to the above, a number of deficiencies were found in various

procedures which could result in performance errors.

The following are

examples:

1.

The last sentence in paragraph 6.2.2 of procedure 1000.09,

" Surveillance Test Program Control," is grammatically incorrect

and should be considered for deletion.

Paragraph 6.2.3 contains

the accurate statement.

Additionally, paragraphs 6.2.6 and 6.2.8

referred to nonexistent procedures.

2.

Pages 23 and 24 of Attachment 2 to procedure 1022.06, "ASME Code

Section XI, Inservice Testing Program Unit 1," were incorrect.

The correct information (page 24) was not included.

3.

Paragraphs 2.0, 3.0, and 3.3 of procedure 1032.07, "ISI Program

Requirements," does not reference procedure 1022.07 (Unit 2) even

though procedure 1032.07 was written for both units.

4.

Forms 1000.06B and 1000.06C in procedure 1000.06, " Procedure

Review, Approval, and Revision Control," contained wording in the

10 CFR 50.59 applicability block that stated, in part, " involves a

change to a test or experiment" instead of " involves a test or

experiment" which would be consistent with the language ia 10 CFR 50.59.

5.

Question 2 in Form 1000.06E read, in part, "would the proposed

procedure change ... ." which does not address the fact that

10 CFR 50.59 applies to both proposed procedures and changes.

This is a Severity Level V violation.

(Supplement 1.E) (313/8618-02;

368/8619-02)

.

.

.

RESPONSE

.

The specific examples cited in the violation are discussed below:

1.

The specific paragraphs of the administrative procedure 1000.09,

" Surveillance Test Program Control," noted in the violation are

provided below:

"6.2.2

Surveillance tests that are the scheduling responsibility

of WCC are controlled by this procedure. This includes

most tests with a test frequency of once per week or

longer. Those tests of shorter frequency are scheduled by

responsible departments should be controlled by

departmental procedures."

"6.2.3

Surveillance tests that must be performed more than once

per week are scheduled by the responsible department and

should be governed by departmental procedures."

The last sentence of paragraph 6.2.2 lacks the word "and" to be

grammatically correct and will be revised accordingly. As noted in the

violation, " Paragraph 6.2.3 contains the accurate statement." AP&L

contends that no performance error would have resulted as procedures

'.

are utilized as complete documents and the noted paragraphs would not

be taken out of context of the complete procedure.

The nonexistent procedures cited in the violation, specifically

paragraph 6.2.6 which references procedure 1015.06, "ASME Code Section

XI Operational Readiness Testing," and paragraph 6.2.8 which

references procedure 1005.01, "M&TE Calibration Program," do in fact

exist but have been assigned different numbers under a reorganization

of administrative procedures. Paragraghs 6.2.6 and 6.2.8 will be

revised to referenct the appropriate procedure numbers. AP&L does not

have an automatic system that identifies all cross referenced

procedures. Several methods do exist for a user to correctly locate

cross referenced procedures. As an example, the procedure tab in the

station procedure manual for procedure 1015.06 contains a form which

informs the user of this procedure's deletion and references the

appropriate replacement procedure number. Additionally the ANO Document

Control System contains the information needed to establish the

chronology of procedure issuance, deletion, renumbering, etc., to

establish necessary cross referencing. AP&L contends that the needed

procedure cross referencing updates cited, though desirable from an

ease of use perspective, would not have resulted in performance errors.

2.

As noted in the Inspection Report, a reproduction error was made during

procedure 1022.06, "ASME Code Section XI Inservice Testing Program

ANO-1," copying for distribution. The data contained on page 24 of the

procedure was a duplication of the data contained on page 23 of the

procedure. This error was made when tne data pages were reducad onto

the procedure form pages. Page 23 contained the correct data. The

correct data for procedure page 24 of the current revision has now been

distributed. This administrative procedure provides an overall

. _ _

.

_

..

__

.

.

.

.

description of the ANO-1 Inservice Testing Program at:d does not control

pump and valve testing. Actual in-service testing of pumps and valves

l

is performed utilizing plant operating procedures; therefore, AP&L

.

contends this error would not have resulted in a performance error of

the testing program.

..

3.

Procedure 1022.07, "ASME Code Section XI Inservice Testing Program

ANO-2," was originally issued on August 24, 1985.

The current

revision of 1032.07, "ISI Program Requirements," was effective August

1, 1985.

Therefore, procedure 1022.07 was not issued prior to the last

revision of 1032.07.

The noted paragraphs of procedure 1032.07 cited

in violation as not containing a reference to procedure 1022.07 were

'

paragraphs 2.0, 3.0 and 3.2.

Paragraph 2.0 of procedure 1032.07

details the scope of the procedure, specifically that "The pump and

valve test program to meet Section XI of the ASME Code is not addressed

by this procedure, but rather is covered by procedure 1022.06 ...."

Paragraph (section) 3.0 of procedure 1032.07 details the references

used to develop procedure 1032.07 in paragraph 3.1 and related ANO

i

administrative procedures in paragraph 3.3.

Procedure 1032.07

paragraph 3.2 does not require a reference to procedure 1022.07.

Procedure 1022.07 is not required for implerentation of procedure

1032.07.

Appropriate references to procedure 1022.07 will be added to

procedure 1032.07.

AP&L contends that the omission of the references

to procedure 1022.07 would not have resulted in a performance error of

the Inservice Inspection Program requirements.

Additionally, procedure

1032.07 is an administrative procedure which describes the program and

is not a performance procedure.

4.

Form 1000.06B, Procedure / Work Plan Request, is designed to provide a

description of the purpose or reason for procedure development or

procedure revisions.

It also documents the review and approval process

as delineated in procedure 1000.06.

Form 1000.06C, Temporary Procedure

Change Request, is designed as a method for temporary changes to

procedures.

It is not applicable to original procedure development.

The 10CFR50.59 applicability section of these two forms is formatted to

determine if an unreviewed safety question evaluation is required by

use of the following questions:

.

Involves a change to a procedure described in the FSAR

-

YES

NO

Involves a change to a test or experiment not described in the

-

l

FSAR

YES

NO

Involves a change that affects compliance with the Technical

-

  • Specification

,

f

j

~YES

NO

These forms are utilized for original procedure review but are

primarily structured for procedure changes.

The wording of these three

questions reflect this structure, and this should be recognized by the

..

. - .

--

__

_

-

-

.

-

.

-

..

.

procedure reviewers.

For an incident in which a new procedura is

developed to perform a test or experiment not the FSAR and the

procedure writer misinterprets the question, the review process would

identify the error and return the procedure to the writer.

This

process, by its basic design, would prevent performance errors from

resulting in approval procedure without the proper evaluation for an

unreviewed safety question.

5.

Form 1000.06E, Unreviewed Safety Question Determination, is designed to

document an evaluation of a procedure or a procedure change for an

unreviewed safety question.

The form consists of seven yes or no

questions which directly paraphrase the guidance of 10CFR50.59.a.2.

Each question begins with the phrase "Would the proposed procedure or

change" except that in question 2 the word "or" has been inadvertently

omitted.

Because the questions are applicable in the same sense to a

procedure or procedure change as directed by procedure 1000.06, the

procedure writer should answer the question appropriately.

In fact,

without the word "or" in the question, for a new procedure a yes or no

answer would not be applicable. AP&L contends that this would not

result in a performance error and that even if it was misinterpreted by

the procedure developer, the review process would prevent a performance

error from resulting in an approved procedure with an inadequate

evaluation.

As the Inspector only speculated that performance errors could have resulted

and did not substantiate this inference in the scope of the inspection, AP&L

does not agree that a violation of 10CFR50, Appendix B, Criterion V has

occurred.

-

_ _ . _

_

, _ _ - - _ _ _ _ _ _ _ _ - _ - _ _ _ - _ _ - _ _ _ _ _ _ _ _ _ _ _

___

_

e

.

,

8.

10 CFR 50.59(b) states, in part, "The licensee shall maintain records

.*

of changes in the facility and of changes in procedures made pursuant

to this section ... The licensee shall furnish ... annually or at such

-

shorter intervals as may be specified in the licensee, a report

containing a brief description of such changes, tests, and experiments,

including a summary of the safety evaluation of each."

Contrary to the above, the licensee failed to submit a report of

activities for the years 1984 and 1985.

This is a Severity Level V violation (Supplement I.E.) (313/8618-01;

368/8619-01)

RESPONSE

The preparation of the 198410CFR50.59 report was more extensive than in the

past to ensure that the report contained more detailed summaries of the

activities performed under the guidance of this regulation.

This effort

required additional coordination between Licensing and the groups who

performed the safety evaluations.

However, the result was a more accurate

reflection of the activities that occurred during 1984.

Additionally, both

the 2R4 and 1R6 refueling outages began in 1984, during which an unusually

large number of design changes, processed under the provisions of

10CFR50.59, were implemented.

The 1984 Summary Report has now been completed and was issued to the NRC

July 15, 1986 (0CAN078604). The 1985 report, which will also contain the

more detailed summaries, is currently being prepared for issuance by

September 18, 1986.

In recognition of the problem of timely submittals and in an effort to make

program improvements while maintaining the quality of the reports, AP&L is

currently undertaking corrective action to develop a more efficient and

systematic means of compiling 10CFR50.59 Summary Reports to avoid such

delays. Actions include additional staff guidance on tracking, compiling

.

and reporting 50.59 affected changes. These actions should ensure timely

'

reporting in the future.

l

.