ML20207K573
| ML20207K573 | |
| Person / Time | |
|---|---|
| Site: | Turkey Point |
| Issue date: | 01/02/1987 |
| From: | Woody C FLORIDA POWER & LIGHT CO. |
| To: | Grace J NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| References | |
| L-87-5, NUDOCS 8701090455 | |
| Download: ML20207K573 (2) | |
Text
-
Om8 g$.
P. O. BOX 14000, Juno BEACH, FL 33408-0420
[!li.
77 JM! 5 A10 : Zu JANUARY 03 1987 L-87-5 Dr. J. Nelson Grace Regional Administrator, Region 11 U. S. Nuclear Regulatory Commission 101 Marietta St., N.W., Suite 2900 Atlanto, GA 30323
Dear Dr. Grace:
Re: Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 Select System Assessment Progress Summary Attached please find the November 1986 progress summary of the Select System Assessment.
If you have any questions regarding this information, please contact us.
Very truly yours, fe, Group V*ce resident Nucle r ergy COW /TCG/gp Attachment cc:
Harold F. Reis, Esquire 8701090455 870102 DR ADOCK 05000250 i
\\
160 l TCG6/015/l PEOPLE.. SERVING PEOPLE
, /9 SELECT SYSTEM ASSESSMENT NOVEMBER 1986 PROGRESS Reconstitution of Design Basis Draf t versions of the reconstituted design bases are presently being reviewed and commented upon by oppropriate Juno Plant Engineering and Safety Engineering Group personnel. Incorporation of these comments and reissucoce for review by other FPL groups is planned for December.
Preparation and issuance of the Chemical and Volume Control System (Emergency Boration) draft reconstituted design basis is proceeding on schedule for a 2/1/87 issue.
Schedules for reconstitution of design bases for Normal Containment Coolers, Process Radiation Monitors and Area Radiation Monitors are being discussed with a planned initiation of these efforts on 1/1/88.
Walkdowns Walkdowns are proceeding on a schedule for completion concurrent with the end of the next Unit 3 refueling outage.
Small bore piping and tubing walkdowns outside Units 3 and 4 Containment are in progress.
Fifty-seven of ninety-two breaker list walkdowns outside units 3 and 4 Containments are complete.
Seventy-five of one hundred and four P&lD walkdowns outside Units 3 and 4 Containments are complete.
All (107) Operating (T&E) drawing walkdowns are complete.
Operability / functionality problems are continuing to be addressed as found and evoluoted.
SEG Comprehensive Review Review of the Select Systems and their associated reconstituted design bases continues toward the scheduled 12/1/86 completis ilty problems crising from this t
Preliminary indications show no significmt + ere review.
Other Significant Progress
- Completed modifications to provide AFW pump RPM monitoring
- Completed modifications to AFW steam vents
- Completed modifications to AFW pump trip and throttle volves
- Closed out various walkdown NCRs.
TCG6/015/2