MONTHYEARML20217J2381999-10-13013 October 1999 Informs That Attached Questions Transmitted by Fax on 991013 to J Rainsberry of Southern California Corp to Prepare for Upcoming Telephone Call ML20212G3791999-09-24024 September 1999 Notification of 991006-07 Meeting with Industry in San Clemente,California to Discuss Technical Issues Re Industry Development of Submittals for risk-informed Technical Specification Improvements ML20211J5591999-09-0101 September 1999 Informs That Application Date in First Line of Attached Ltr Issued 990823 Corrected to Read 990625, Not 1997. Requests That Corrected Copy Be Submitted to H Ray ML20211H4441999-08-27027 August 1999 Notification of Significant Meeting with Util on 990916 & 17 in Arlington,Tx to Improve Utility & NRC Understanding of Industry & Regulatory Perspectives on Current Issues ML20211H0431999-08-0909 August 1999 Submits Comments on San Onofre Response to NRC Request for Addl Info on risk-informed IST Program ML20210G4671999-07-30030 July 1999 Forwards Draft rept,NUREG/CR-xxxx,Vol x,INEEL/EXT-99-00373, High-Pressure Safety Injection Sys Reliability,1987-1997 ML20195H7251999-06-11011 June 1999 Forwards NRC Approved Operator Licensing Exam Facility Outline & Initial Exam,Submittal for Retake Exam Administered on 990416 ML20195H6031999-06-11011 June 1999 Forwards Exam Repts 50-361/99-301 & 50-362/99-301 Administered at Facility on 990416,with as Given Written Exam Attached ML20207F1141999-06-0404 June 1999 Notification of Significant Licensee Meeting with Util on 990628 to Discuss Emergency Preparedness Program Status & Planned Changes ML20205Q4491999-04-19019 April 1999 Forwards Viewgraphs of 990419 Telcon Re SG Eddy Current Insp Results Obtained During Imminent Refueling Outage ML20205N8821999-04-15015 April 1999 Forwards Questions Transmitted by Fax on 990415 to J Rainsberry of SCE & Request for Conference Call to Be Scheduled with Staff to Discuss SG Eddy Current Insp Results Obtained During Imminent Refueling Outage ML20205N5991999-04-14014 April 1999 Forwards Questions That Were Transmitted by Fax on 990414 to J Rainsberry of Southern California Corp,In Preparation for Upcoming Telcon on Recirculation Signal/Emergency Feedwater Actuation Signal While Channel in Tripped Condition ML20205M0111999-04-13013 April 1999 Forwards Questions to Be Discussed in Upcoming Telcon on GL 95-07.Questions Transmitted by Fax on 990413 to J Rrainsberry of SCE ML20205K4621999-04-0606 April 1999 Notification of Licensee Meeting with Util on 990422 to Discuss Results of PPR 99-01 ML20207L7041999-03-0202 March 1999 Notification of 990318 Meeting with SCE in Rockville, Maryland to Discuss SCE Mgt Plans for Future risk-informed License Amend Applications for SONGS ML20207L7091999-03-0202 March 1999 Notification of 990317 Meeting with SCE in Rockville, Maryland to Discuss Topics Resulting from NRC Staff Review & Confirmatory Analysis of Licensee Request to Remove Hydrogen Control Sys from SONGS Licensing Basis.Meeting Agenda Encl ML20199L3401999-01-22022 January 1999 Forwards Facility Submitted Outline,Initial Exam & as Given Operating Exam for Test Administered on 981115-20 at San Onofre Nuclear Generation Station ML20202C3931999-01-22022 January 1999 Forwards Exam Rept Administered on 981115-20 at San Onofre Nuclear Generating Station,With as Given Written Exam Encl ML20198M3241998-12-29029 December 1998 Submits Summary of Telcon Re Proposed Criteria to Support Development of SER Constraints for Reload Analysis Tr,For Plant,Units 2 & 3 ML20196G6481998-11-0303 November 1998 Notification of Significant Meeting with Util on 981125 at One White Flint to Discuss Licensee Views on Efforts to Maintain Safety Conscious Work Environ ML20155C9621998-10-27027 October 1998 Notification of 981124 Meeting with Util to Discuss Results of Employee Concerns Program Survey ML20153B4531998-09-0404 September 1998 Notification of Cancellation of 980924 Meeting with TVA in Rockville,Md to Discuss Review of Best Estimate of LOCA Methodology at Plant,Unit 2 ML20236Y6301998-08-0808 August 1998 Forwards Monthly Rept Reflecting Status of 10CFR2.206 Petitions as of 980731.Petitions on Plant GT97494 & GT97339 for Which DD Became Final Actions During Month Were Closed. Portion of Encl Withheld ML20237A0011998-08-0707 August 1998 Informs That Extension Granted on Envirocare Decision of 980904.Two Week Extension on Philadelphia VA Decision of 980828 Requested.Submits Concurrence of Changes.Rept on 2.206 July Status for Plants Encl ML20236K9071998-07-0707 July 1998 Notification of 980710 Meeting W/Util,Rescheduled from 980707,in Rockville MD to Discuss Proposed Amend for Extension of Allowed Outage Times for EDG ML20236K3021998-06-30030 June 1998 Notification of 980707 Meeting W/Util in Rockville,Md to Discuss Licensee Proposed Amend for Extension of Allowed Outage Times for EDG ML20249C2721998-06-19019 June 1998 Notification of 980707 Meeting W/Util in Arlington,Texas to Discuss SONGS New Security Mgt ML20249A1181998-06-11011 June 1998 Notification of 980630 Meeting W/Util in Region IV Office to Discuss Plant Performance Status & Effectiveness of Initiatives to Improve Performance ML20249A1221998-06-11011 June 1998 Forwards Unsolicited Info from San Onofre Licensee Re Emergency Diesel Generator Delegation Allowed Outage Time Extension TS Request ML20249A5621998-06-10010 June 1998 Notification of 980615 Meeting W/Util in Rockville,Md to Discuss SONGS Mgt drop-in Visit by Licensee New Manager, Regulatory Affairs ML20248L8621998-06-0909 June 1998 Forwards May 1998 Rept on Status of Public Petitioners Under 10CFR2.206.Petition on Seabrook (GT970873) for Which DD 98- 03 Became Final Agency Decision on 980413 Closed.Attachment 3 Withheld ML20248C8461998-05-29029 May 1998 Notification of 980529 Meeting W/Util in Rockville,Md for Licensee to Present Proposal for Performing Own Reload Analyses ML20248B6071998-05-26026 May 1998 Notification of Licensee Meeting W/Util on 980528 Re drop-in Visit by Licensee New Manager of Regulatory Affairs for Purpose of Meeting Senior Region IV Mgt ML20216H3281998-04-15015 April 1998 Notification of 980429 Meeting W/Util in Rockville,Md to Discuss Licensee Proposal for Changing Minimum Tcold for Plant Operation & Performing Own Reload Analyses ML20198J5461998-01-0707 January 1998 Notification of Licensee Meeting W/Util on 980120 to Discuss Apparent Violations Involving Physical Security Program. Meeting Not Open to Public ML20198F8931997-12-22022 December 1997 Informs That on 970304,San Onofre,Unit 2,pressurizer Vessel Experienced Cooldown Transient at Rate Greater than 200 F/Hr Limit Specified in Tss.Fracture Mechanics Evaluation of Pressurizer Transient Met Criteria in App G of ASME Code ML20203D4321997-12-0909 December 1997 Notifies of 971223 Meeting W/Util in Rockville,Md to Discuss Use of Mechanical Nozzle Seal Assemblies as Alternate ASME Code Replacements at Plant ML20199A7951997-11-0707 November 1997 Notification of Meeting W/Util on 971121 at Plant to Discuss Employee Concerns Program ML20198Q8611997-11-0606 November 1997 Forwards Copy of e-mail Response to e-mail Inquiry Received from J Chang of San Onofre Nuclear Station Re Info Notice 97-038, Level Sensing System Initiates Common Mode Failure of High Pressure Injection Pumps ML20217J6961997-10-16016 October 1997 Notification of Meeting W/Util on 971023 in Rockville,Md to Discuss Plans for Inspecting SG at Plant,Units 2 & 3 & Runtime Analysis Submitted on 970925 ML20211C4001997-09-22022 September 1997 Notification of Revised Licensee Meeting W/Util on 970930 in Arlington,Tx Re Predecisional Enforcement Conference ML20210T2841997-09-10010 September 1997 Notification of 970924 Licensee Meeting W/Sce in in Arlington,Tx Re Predecisional Enforcement Conference ML20141J8201997-08-18018 August 1997 Notification of 970821 Licensee Meeting W/Util in Arlington, Tx to Discuss RCS Nozzle Penetration Cracking ML20217G5901997-08-0202 August 1997 Informs That Notification Was Made to NRC Operations Center on 970802 as Listed ML20149F8771997-07-18018 July 1997 Notification of 970827 Licensee Meeting W/Util in San Clemente,Ca Re SALP ML20149D7881997-07-15015 July 1997 Revised Notice of Licensee Meeting W/Util in Arlington,Tx on 970805 to Discuss Employee Concerns Program ML20140B6061997-06-0303 June 1997 Notification of 970611 Meeting in Rockville,Md to Discuss Evaluation Rept Re Eggcrate Support Degradation Identified in San Onofre Unit 3 SG ML20141K8751997-05-27027 May 1997 Notifies of 970529 Meeting W/Util in Rockville,Md to Discuss San Onofre Unit 3 SG Eggcrate Visual Exam Results ML20138G2891997-04-30030 April 1997 Notification of 970509 Meeting W/Util in Rockville,Md to Discuss Operational Issues Re Eggcrate Support Degradation Recently Identified in Plant,Unit 3 SGs ML20149H5221997-04-25025 April 1997 Amended Emergency Petition Re Degradation of Steam Generator Internal Tube Supports (Egg Crates),Based on 970417 Rept. Plant Will Not Be Able to Completely Withstand Major Seismic Event 1999-09-24
[Table view] Category:MEMORANDUMS-CORRESPONDENCE
MONTHYEARML20217J2381999-10-13013 October 1999 Informs That Attached Questions Transmitted by Fax on 991013 to J Rainsberry of Southern California Corp to Prepare for Upcoming Telephone Call ML20212G3791999-09-24024 September 1999 Notification of 991006-07 Meeting with Industry in San Clemente,California to Discuss Technical Issues Re Industry Development of Submittals for risk-informed Technical Specification Improvements ML20211J5591999-09-0101 September 1999 Informs That Application Date in First Line of Attached Ltr Issued 990823 Corrected to Read 990625, Not 1997. Requests That Corrected Copy Be Submitted to H Ray ML20211H4441999-08-27027 August 1999 Notification of Significant Meeting with Util on 990916 & 17 in Arlington,Tx to Improve Utility & NRC Understanding of Industry & Regulatory Perspectives on Current Issues ML20211H0431999-08-0909 August 1999 Submits Comments on San Onofre Response to NRC Request for Addl Info on risk-informed IST Program ML20210G4671999-07-30030 July 1999 Forwards Draft rept,NUREG/CR-xxxx,Vol x,INEEL/EXT-99-00373, High-Pressure Safety Injection Sys Reliability,1987-1997 ML20195H7251999-06-11011 June 1999 Forwards NRC Approved Operator Licensing Exam Facility Outline & Initial Exam,Submittal for Retake Exam Administered on 990416 ML20195H6031999-06-11011 June 1999 Forwards Exam Repts 50-361/99-301 & 50-362/99-301 Administered at Facility on 990416,with as Given Written Exam Attached ML20207F1141999-06-0404 June 1999 Notification of Significant Licensee Meeting with Util on 990628 to Discuss Emergency Preparedness Program Status & Planned Changes ML20205Q4491999-04-19019 April 1999 Forwards Viewgraphs of 990419 Telcon Re SG Eddy Current Insp Results Obtained During Imminent Refueling Outage ML20205N8821999-04-15015 April 1999 Forwards Questions Transmitted by Fax on 990415 to J Rainsberry of SCE & Request for Conference Call to Be Scheduled with Staff to Discuss SG Eddy Current Insp Results Obtained During Imminent Refueling Outage ML20205N5991999-04-14014 April 1999 Forwards Questions That Were Transmitted by Fax on 990414 to J Rainsberry of Southern California Corp,In Preparation for Upcoming Telcon on Recirculation Signal/Emergency Feedwater Actuation Signal While Channel in Tripped Condition ML20205M0111999-04-13013 April 1999 Forwards Questions to Be Discussed in Upcoming Telcon on GL 95-07.Questions Transmitted by Fax on 990413 to J Rrainsberry of SCE ML20205K4621999-04-0606 April 1999 Notification of Licensee Meeting with Util on 990422 to Discuss Results of PPR 99-01 ML20207L7091999-03-0202 March 1999 Notification of 990317 Meeting with SCE in Rockville, Maryland to Discuss Topics Resulting from NRC Staff Review & Confirmatory Analysis of Licensee Request to Remove Hydrogen Control Sys from SONGS Licensing Basis.Meeting Agenda Encl ML20207L7041999-03-0202 March 1999 Notification of 990318 Meeting with SCE in Rockville, Maryland to Discuss SCE Mgt Plans for Future risk-informed License Amend Applications for SONGS ML20199L3401999-01-22022 January 1999 Forwards Facility Submitted Outline,Initial Exam & as Given Operating Exam for Test Administered on 981115-20 at San Onofre Nuclear Generation Station ML20202C3931999-01-22022 January 1999 Forwards Exam Rept Administered on 981115-20 at San Onofre Nuclear Generating Station,With as Given Written Exam Encl ML20198M3241998-12-29029 December 1998 Submits Summary of Telcon Re Proposed Criteria to Support Development of SER Constraints for Reload Analysis Tr,For Plant,Units 2 & 3 ML20196G6481998-11-0303 November 1998 Notification of Significant Meeting with Util on 981125 at One White Flint to Discuss Licensee Views on Efforts to Maintain Safety Conscious Work Environ ML20155C9621998-10-27027 October 1998 Notification of 981124 Meeting with Util to Discuss Results of Employee Concerns Program Survey ML20153B4531998-09-0404 September 1998 Notification of Cancellation of 980924 Meeting with TVA in Rockville,Md to Discuss Review of Best Estimate of LOCA Methodology at Plant,Unit 2 ML20236Y6301998-08-0808 August 1998 Forwards Monthly Rept Reflecting Status of 10CFR2.206 Petitions as of 980731.Petitions on Plant GT97494 & GT97339 for Which DD Became Final Actions During Month Were Closed. Portion of Encl Withheld ML20237A0011998-08-0707 August 1998 Informs That Extension Granted on Envirocare Decision of 980904.Two Week Extension on Philadelphia VA Decision of 980828 Requested.Submits Concurrence of Changes.Rept on 2.206 July Status for Plants Encl ML20236K9071998-07-0707 July 1998 Notification of 980710 Meeting W/Util,Rescheduled from 980707,in Rockville MD to Discuss Proposed Amend for Extension of Allowed Outage Times for EDG ML20236K3021998-06-30030 June 1998 Notification of 980707 Meeting W/Util in Rockville,Md to Discuss Licensee Proposed Amend for Extension of Allowed Outage Times for EDG ML20249C2721998-06-19019 June 1998 Notification of 980707 Meeting W/Util in Arlington,Texas to Discuss SONGS New Security Mgt ML20249A1221998-06-11011 June 1998 Forwards Unsolicited Info from San Onofre Licensee Re Emergency Diesel Generator Delegation Allowed Outage Time Extension TS Request ML20249A1181998-06-11011 June 1998 Notification of 980630 Meeting W/Util in Region IV Office to Discuss Plant Performance Status & Effectiveness of Initiatives to Improve Performance ML20249A5621998-06-10010 June 1998 Notification of 980615 Meeting W/Util in Rockville,Md to Discuss SONGS Mgt drop-in Visit by Licensee New Manager, Regulatory Affairs ML20248L8621998-06-0909 June 1998 Forwards May 1998 Rept on Status of Public Petitioners Under 10CFR2.206.Petition on Seabrook (GT970873) for Which DD 98- 03 Became Final Agency Decision on 980413 Closed.Attachment 3 Withheld ML20248C8461998-05-29029 May 1998 Notification of 980529 Meeting W/Util in Rockville,Md for Licensee to Present Proposal for Performing Own Reload Analyses ML20248B6071998-05-26026 May 1998 Notification of Licensee Meeting W/Util on 980528 Re drop-in Visit by Licensee New Manager of Regulatory Affairs for Purpose of Meeting Senior Region IV Mgt ML20216H3281998-04-15015 April 1998 Notification of 980429 Meeting W/Util in Rockville,Md to Discuss Licensee Proposal for Changing Minimum Tcold for Plant Operation & Performing Own Reload Analyses ML20198J5461998-01-0707 January 1998 Notification of Licensee Meeting W/Util on 980120 to Discuss Apparent Violations Involving Physical Security Program. Meeting Not Open to Public ML20198F8931997-12-22022 December 1997 Informs That on 970304,San Onofre,Unit 2,pressurizer Vessel Experienced Cooldown Transient at Rate Greater than 200 F/Hr Limit Specified in Tss.Fracture Mechanics Evaluation of Pressurizer Transient Met Criteria in App G of ASME Code ML20203D4321997-12-0909 December 1997 Notifies of 971223 Meeting W/Util in Rockville,Md to Discuss Use of Mechanical Nozzle Seal Assemblies as Alternate ASME Code Replacements at Plant ML20199A7951997-11-0707 November 1997 Notification of Meeting W/Util on 971121 at Plant to Discuss Employee Concerns Program ML20198Q8611997-11-0606 November 1997 Forwards Copy of e-mail Response to e-mail Inquiry Received from J Chang of San Onofre Nuclear Station Re Info Notice 97-038, Level Sensing System Initiates Common Mode Failure of High Pressure Injection Pumps ML20217J6961997-10-16016 October 1997 Notification of Meeting W/Util on 971023 in Rockville,Md to Discuss Plans for Inspecting SG at Plant,Units 2 & 3 & Runtime Analysis Submitted on 970925 ML20211C4001997-09-22022 September 1997 Notification of Revised Licensee Meeting W/Util on 970930 in Arlington,Tx Re Predecisional Enforcement Conference ML20210T2841997-09-10010 September 1997 Notification of 970924 Licensee Meeting W/Sce in in Arlington,Tx Re Predecisional Enforcement Conference ML20141J8201997-08-18018 August 1997 Notification of 970821 Licensee Meeting W/Util in Arlington, Tx to Discuss RCS Nozzle Penetration Cracking ML20217G5901997-08-0202 August 1997 Informs That Notification Was Made to NRC Operations Center on 970802 as Listed ML20149F8771997-07-18018 July 1997 Notification of 970827 Licensee Meeting W/Util in San Clemente,Ca Re SALP ML20149D7881997-07-15015 July 1997 Revised Notice of Licensee Meeting W/Util in Arlington,Tx on 970805 to Discuss Employee Concerns Program ML20140B6061997-06-0303 June 1997 Notification of 970611 Meeting in Rockville,Md to Discuss Evaluation Rept Re Eggcrate Support Degradation Identified in San Onofre Unit 3 SG ML20141K8751997-05-27027 May 1997 Notifies of 970529 Meeting W/Util in Rockville,Md to Discuss San Onofre Unit 3 SG Eggcrate Visual Exam Results ML20138G2891997-04-30030 April 1997 Notification of 970509 Meeting W/Util in Rockville,Md to Discuss Operational Issues Re Eggcrate Support Degradation Recently Identified in Plant,Unit 3 SGs ML20149H5221997-04-25025 April 1997 Amended Emergency Petition Re Degradation of Steam Generator Internal Tube Supports (Egg Crates),Based on 970417 Rept. Plant Will Not Be Able to Completely Withstand Major Seismic Event 1999-09-24
[Table view] |
Text
, ,. August 18, 1988 i
Docket Nos.: 50-206, 50-361, and 50-362 MEMORANDUM FOR: George W. Knighton, Director Project Directorate V Division of Reactor Projects - III, IV, Y and Special Projects
- FROM: Charles M. Trannell, Project Manager Project Directorate V Division of Reactor Projects - III.,
IV, V and Special Projects
SUBJECT:
FORTHCOMING MEETING *WITH SOUTHERN CALIFORNIA EDISON COMPANY ON SAN CN0FRE NUCLEAR GENERATING STATION DATE & TIME: Tuesday, August 30, 1988 - 9:00 a.m. entrance meeting Wednesday, August 31, 1988 - 3:00 p.m. exit meeting LOCATION: San Onofre Nuclear Generating Station San Clemente, California PURPOSE: To conduc', an audit of Southern California Edison's pipe wall thinning inspection program. See enclosed agenda.
- PARTICIPANTS: NRC KE, Don Hickman Tony Llorens Paul Wu Brian Katz Carl Gzakoski (BNL) Craig Harberts original signed by Charles M. Trammell, Senior Project Manager Project Directorate V Division of Reactor Projects - III, i IV, V and Special Projects
Enclosure:
A.genda cc: See next page CONTACT: Charles M. Trannell (301) 492-3121
- Meetings between NRC technical staff and applicants or licensees are open for interested members of the public, petitioners, intervenors, or other parties to attend as observers pur ant to "Open Meeting Statement of NRC Staff Policy,"
43 Federal Register 28058 6/28/78.
PDV/PM [R D:PDV 11:cw GWk ighton i gee eq ,ee J
4x\
8808240419 ggoggg DR ADOCK 05000206 PDC
>RRE:p
. 'o UNITED STATES g
- 8 o NUCLEAR REGULATORY COMMISSION
$ ; ,E WASHINGTON, D C 20555 August 18, 1988
'g +... /
Docket Nos.: 50-206, 50-361, and 50-362 MEMORANDUM FOR: George W. Knighton, Director Project Directorate Y Division of Reactor Projects - III, IV, Y and Special Projects FROM: Charlos M. Trrwnell, Project Manager Project Directorate V Division of Reactor Projects - III, IV, Y and Special Projects
SUBJECT:
FORTHCOMING MEETING *WITH SOUTHERN CALIFORNIA EDISON COMPANY ON SAN ONOFRE NUCLEAR GENERATING STATION DATE & TIME: Tuesday, August 30s 1988 - 9:00 a.m. entrance meeting Wednesday, August 31, 1988 - 3:00 p.m. exit meeting LOCATION: San Onofre Nuclear Generating Station San Clemente, California PURPOSE: To conduct an audit of Southern California Edison's pipe wall thinning inspection program. See enclosed agenda.
- PARTICIPANTS: NRC 3CE Doh Hickman Tony Llorens Paul Wu Brian Katz Carl Gzakoski (BNL) Craig Harberts
- k. /[
Charles H. Trameil, Senior Project Manager Project Directorate Y Division of Reactor Projects - III, IV, Y and Special Projects
Enclosure:
Agenda ec: See next page CONTACT: Charles M. Trannell (301)492-3121
- Meetings between NRC technical staff and applicants or licensees are open for interesteo members of the public, petitioners, intervenors, or other parties to attend as observers pursuant to "Open Meeting Statement of NRC Staff Policy "
43 Federal Register 28058,6/28/78.
i'
]
Mr. Kenneth P. Baskin San Onofre Nuclear Generating i Southern California Edison Company Station, Unit No. I cc Charles R. Kocher, Assistant Mr. Jack McGurk, Acting Chief General Counsel Radiological Health Branch James Beoletto, Esquire State Department of Health Southern California Edison Company Services Post Office Box 800 714 P Street, Office Bldg. 8 Rosemead, California 91770 Sacramento, California 95814 David R. Pigott Mr. Hans Kaspar, Executive Director Orrick, Herrington & Sutcliffe Marine Review Comittee Inc.
600 Montgomery Street 531 Encinitas Boulevard, Suite 105 San Francisco, California 94111 Encinitas, California 92024 Mr. Robert G. Lacy Mr. Dennis M. Smith, Chief Manager, Nuclear Radiological Programs Division San Diego Gas & Electric Company Governor's Office of Emergency Sycs.
P. O. Box 1831 State of California San Diego, California 92112 . 2800 Headowview Road Sacramento, California 95832 Resident Inspector / San Onofre NPS <
U.S. hRC '
P. O. Box 4329 San Clemente, California 92672 Mayor City of San Clemente
- San Clemente, California 92672 Chairman Board of Supervisors County of San Diego 1600 Pacific Highway Room 335 San Diego, California 92101 Director Energy Facilities Siting Division Energy Resources Conservation &
2 Development Consnission 1516 - 9th Street Sacramento, California 95814 Regional Administrator, Region Y U.S. Nuclear Regulatory Comission 1450 Maria Lane, Suite 210
, Walnut Creek, California 94596
Mr. Kenneth P. Bassin San Onofre Nuclear Generating
, Southern California Edison Company Station, Units 2 and 3 cc:
Mr. Gary D. Cotton Mr. Hans Kaspar, Executive Director Senior Vice President Marine Review Comittee, Inc.
Engineering and Operations 531 Encinitas Boulevard, Suite 105 San Diego Gas & Electric Company Encinitas, California' 92024 101 Ash Street Post Office Box 1831 S:n Diego, California 92112 Mr. Mark Medford Southern California Edison. Company Charles R. Kocher, Esq. 2244 Walnut Grove Avenue James A. Beoletto, Esq. P. O. Box 800 Southern California Edison Company Rosemead, California 91770 2244 Walnut Grove Avenue P. O. Box 800 Mr. Robert G. Lacy Rosemead, California 91770 Manager, Nuclear Department San Diego Gas & Electric Company Orrick, Herrington & Sutcliffe P. O. Box 1631 ATTH: David R. Pigott, Esq. '
San Diego, California 921P2 600 entgomery Street San eiancisco, California 94111 Richard J. Wharton, Esq.
University of San Diego School of Alan R. Watts, Esq. Law Rourke & Woodruff Environmental Law Clinic 701 S. Parker St. No. 7000 San Diego, California 92110 Orange, California 92668-4702 '
Charles E. McClung,-Jr., Esq.
Attorney at Law Mr. S. McClusky .
24012 Calle de la Plaza / Suite 330 Bechtel Power Corporation Laguna Hills, California 92653 P. O. Box 60360, Terminal Annex Los Angeles, California 90060 Regional Administrator, Rogion Y U.S. Nuclear Regulatory Comission Mr. C. B. Brinkman 1450 Maria Lane / Suite 210 Corbustion Engineering, Inc. Walnut Creek, California 94596 7910 Woodmont Avenue, Suite 1310 Bethesda, Maryland 20814 Resident inspector, San Onofre NPS c/o U. S. Nuclear Regulatory Comission Mr. Dennis F. Kirsh Post Office Box 4329 U.S. Nuclear Regulatory Comission San Clemente, California 92672 Region V 1450 Maria Lane, Suite 210 Mr. Sherwin Harris Walnut Creek, California 94596 Resource Project Manager Public Utilities Department Mr. Dennis M. Smith, Chief City of Riverside Radiological Progra:ns Division City Hall Govcrnor's Office of Emergency Services 3900 Main Street 2800 Meadowview Road Riverside, California 92522 Sacramento, California 95832
4 l '
, ENCLOSURT 1
[ p!PE WALL THINNING INSPECTION PROGRAM IMPLEMENTATION EVALUATION CRITERIA l
4
_p urpose ,,
l l The purpose of this instruction is to define the evaltation criteria for nytew I cf licensee's erosion /cormsfon monitoring program and its implementation. l I
Through selective examination of the licensee s crogram for monitorin pipe I
wall thinning, the procedures defining'the activities to be accomplis .ad are -'
verified for consistency with licensee s program cosmiitment.
l Requirements i 1.. Review of Licensee's Erosion / Corrosion Monitoring Program
- 1. Does the licensee's program have well defined criteria for:
- a. selecting inspection points ,
- b. detemining inspection frequency
- c. defining method of inspection
- d. making replacement / repair decisions
- 2. Does the licenste's program meet the intent of NUMARC guidelines?
i II. Review of Licensee's Implementation of ErosioniCorrosion Monitoring i Program .
- 1. Inspection procedures and guidelines j I
- a. Procedures have been properly reviewed and approved before their implementation. I
- b. Procedures cover periodic monitoring of high energy safety- -
i I
ralated end nonsafety-related carbon steel. *
- c. Procedures provide for qualification or certification of 1 personnel, equipment, or proceAres consistent with establ.shed program counttments.
[ . 2. Qualification of inspectors ,
- a. Personnel conducting NDE examinations are properly certified
- b. The licensee has a well developed training pmgram
) 3. Inspection method and uguipment calibration l
- a. Method of NDE and related equipments have been calibratad agat, %own standards for types of metals and range of i thick, ss to be measured .
l l
L s 9
- l
. ,._y.... .
i l
./ l
- b. Measurements of pipe wall thickness are being accomplisWd in j accordance with established instructions and results are being i appropriately documented.
- 4. Evaluation of the results of pipe wall measurements and determinations on the need for corrective action or frequency of continued periodic monitoring is being ar. comp 11shed by qualified personnel.
- 5. Need for replacemen.. -
ipair, or continued monitoring of piping which has been subjected to pipe wall thinning has been (or will t>e) I determined and schedule established is yet to be accomplished.
- 6. Administrative control and management support 111. History of Pipe Wa11 Thinning
' ~
- 1. When did u licensee develop its 4tesion/ corrosion monitoring program? -
I
- 2. History of pipe wall thinning i 1
- 3. Failure analysis and damage mechanism l
!Y. Review of Licensee's Plan for Developing or Revising its Erosion / Corrosion Monitoring Program .
. 1. Development of long-ters inspection program for single-phase systerr.s
- 2. Development of guidelines and computer code for two-phase piping systems similar to those developed for the single phase systams.
V. Verification of Licensee's Csvitments Nade In its Response to MRC bulletin 87-01 1
e 9
l e
e ,
---,v -
s v , + , - - - - , , , ,w ,,n.,a w ,,,su-,w,-n, - w,-,wwwm, .,,.,,w- --- - . - _ - - - - - - - -+,, -nw,-v,, e, -w a,e,--sm-- mw_ _m--
'e F
MEETING NOTICE DISTRIBUTION
[iEEe5Nde ~ h PDV Reading' ~"
NRC PDR Local PDR TMurley/JSniezek DCrutchfield GHolahan CMiller OGC-White Flint
-EJordan PGrimes I GKnighton ACRS(10)
OPA NRC Participants ,
Service List (See next page)
Licensee FMiraglia DKirsch 1
Project Manager j WLanning GPA/PA VWilson '
DMorley Receptionist (Building where meeting is being held) l l
)
l l
l QFot Gl,
- Meetings between NRC technical staff nnd applicants. for licenses are open for ,
interested members of the public, petitioners intervenors, or other parties to I f attend as observers pursuant to *0 pen Meetia.4 Statement of NRC Staff Policy" :
43 Federal Register! 28058,6/28/87. l