Notification of 880830 & 31 Meetings W/Util in San Clemente, CA to Conduct Audit of Pipe Wall Thinning Insp Program
ML20207H260
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 08/18/1988
From: Trammell C
Office of Nuclear Reactor Regulation
To: Knighton G
Office of Nuclear Reactor Regulation
References
NUDOCS 8808240419
Download: ML20207H260 (7)


Text

, ,. August 18, 1988 i

Docket Nos.: 50-206, 50-361, and 50-362 MEMORANDUM FOR: George W. Knighton, Director Project Directorate V Division of Reactor Projects - III, IV, Y and Special Projects

  • FROM: Charles M. Trannell, Project Manager Project Directorate V Division of Reactor Projects - III.,

IV, V and Special Projects

SUBJECT:

FORTHCOMING MEETING *WITH SOUTHERN CALIFORNIA EDISON COMPANY ON SAN CN0FRE NUCLEAR GENERATING STATION DATE & TIME: Tuesday, August 30, 1988 - 9:00 a.m. entrance meeting Wednesday, August 31, 1988 - 3:00 p.m. exit meeting LOCATION: San Onofre Nuclear Generating Station San Clemente, California PURPOSE: To conduc', an audit of Southern California Edison's pipe wall thinning inspection program. See enclosed agenda.

  • PARTICIPANTS: NRC KE, Don Hickman Tony Llorens Paul Wu Brian Katz Carl Gzakoski (BNL) Craig Harberts original signed by Charles M. Trammell, Senior Project Manager Project Directorate V Division of Reactor Projects - III, i IV, V and Special Projects

Enclosure:

A.genda cc: See next page CONTACT: Charles M. Trannell (301) 492-3121

  • Meetings between NRC technical staff and applicants or licensees are open for interested members of the public, petitioners, intervenors, or other parties to attend as observers pur ant to "Open Meeting Statement of NRC Staff Policy,"

43 Federal Register 28058 6/28/78.

PDV/PM [R D:PDV 11:cw GWk ighton i gee eq ,ee J

4x\

8808240419 ggoggg DR ADOCK 05000206 PDC

>RRE:p

. 'o UNITED STATES g

  • 8 o NUCLEAR REGULATORY COMMISSION

$  ; ,E WASHINGTON, D C 20555 August 18, 1988

'g +... /

Docket Nos.: 50-206, 50-361, and 50-362 MEMORANDUM FOR: George W. Knighton, Director Project Directorate Y Division of Reactor Projects - III, IV, Y and Special Projects FROM: Charlos M. Trrwnell, Project Manager Project Directorate V Division of Reactor Projects - III, IV, Y and Special Projects

SUBJECT:

FORTHCOMING MEETING *WITH SOUTHERN CALIFORNIA EDISON COMPANY ON SAN ONOFRE NUCLEAR GENERATING STATION DATE & TIME: Tuesday, August 30s 1988 - 9:00 a.m. entrance meeting Wednesday, August 31, 1988 - 3:00 p.m. exit meeting LOCATION: San Onofre Nuclear Generating Station San Clemente, California PURPOSE: To conduct an audit of Southern California Edison's pipe wall thinning inspection program. See enclosed agenda.

  • PARTICIPANTS: NRC 3CE Doh Hickman Tony Llorens Paul Wu Brian Katz Carl Gzakoski (BNL) Craig Harberts
k. /[

Charles H. Trameil, Senior Project Manager Project Directorate Y Division of Reactor Projects - III, IV, Y and Special Projects

Enclosure:

Agenda ec: See next page CONTACT: Charles M. Trannell (301)492-3121

  • Meetings between NRC technical staff and applicants or licensees are open for interesteo members of the public, petitioners, intervenors, or other parties to attend as observers pursuant to "Open Meeting Statement of NRC Staff Policy "

43 Federal Register 28058,6/28/78.

i'

]

Mr. Kenneth P. Baskin San Onofre Nuclear Generating i Southern California Edison Company Station, Unit No. I cc Charles R. Kocher, Assistant Mr. Jack McGurk, Acting Chief General Counsel Radiological Health Branch James Beoletto, Esquire State Department of Health Southern California Edison Company Services Post Office Box 800 714 P Street, Office Bldg. 8 Rosemead, California 91770 Sacramento, California 95814 David R. Pigott Mr. Hans Kaspar, Executive Director Orrick, Herrington & Sutcliffe Marine Review Comittee Inc.

600 Montgomery Street 531 Encinitas Boulevard, Suite 105 San Francisco, California 94111 Encinitas, California 92024 Mr. Robert G. Lacy Mr. Dennis M. Smith, Chief Manager, Nuclear Radiological Programs Division San Diego Gas & Electric Company Governor's Office of Emergency Sycs.

P. O. Box 1831 State of California San Diego, California 92112 . 2800 Headowview Road Sacramento, California 95832 Resident Inspector / San Onofre NPS <

U.S. hRC '

P. O. Box 4329 San Clemente, California 92672 Mayor City of San Clemente

  • San Clemente, California 92672 Chairman Board of Supervisors County of San Diego 1600 Pacific Highway Room 335 San Diego, California 92101 Director Energy Facilities Siting Division Energy Resources Conservation &

2 Development Consnission 1516 - 9th Street Sacramento, California 95814 Regional Administrator, Region Y U.S. Nuclear Regulatory Comission 1450 Maria Lane, Suite 210

, Walnut Creek, California 94596

Mr. Kenneth P. Bassin San Onofre Nuclear Generating

, Southern California Edison Company Station, Units 2 and 3 cc:

Mr. Gary D. Cotton Mr. Hans Kaspar, Executive Director Senior Vice President Marine Review Comittee, Inc.

Engineering and Operations 531 Encinitas Boulevard, Suite 105 San Diego Gas & Electric Company Encinitas, California' 92024 101 Ash Street Post Office Box 1831 S:n Diego, California 92112 Mr. Mark Medford Southern California Edison. Company Charles R. Kocher, Esq. 2244 Walnut Grove Avenue James A. Beoletto, Esq. P. O. Box 800 Southern California Edison Company Rosemead, California 91770 2244 Walnut Grove Avenue P. O. Box 800 Mr. Robert G. Lacy Rosemead, California 91770 Manager, Nuclear Department San Diego Gas & Electric Company Orrick, Herrington & Sutcliffe P. O. Box 1631 ATTH: David R. Pigott, Esq. '

San Diego, California 921P2 600 entgomery Street San eiancisco, California 94111 Richard J. Wharton, Esq.

University of San Diego School of Alan R. Watts, Esq. Law Rourke & Woodruff Environmental Law Clinic 701 S. Parker St. No. 7000 San Diego, California 92110 Orange, California 92668-4702 '

Charles E. McClung,-Jr., Esq.

Attorney at Law Mr. S. McClusky .

24012 Calle de la Plaza / Suite 330 Bechtel Power Corporation Laguna Hills, California 92653 P. O. Box 60360, Terminal Annex Los Angeles, California 90060 Regional Administrator, Rogion Y U.S. Nuclear Regulatory Comission Mr. C. B. Brinkman 1450 Maria Lane / Suite 210 Corbustion Engineering, Inc. Walnut Creek, California 94596 7910 Woodmont Avenue, Suite 1310 Bethesda, Maryland 20814 Resident inspector, San Onofre NPS c/o U. S. Nuclear Regulatory Comission Mr. Dennis F. Kirsh Post Office Box 4329 U.S. Nuclear Regulatory Comission San Clemente, California 92672 Region V 1450 Maria Lane, Suite 210 Mr. Sherwin Harris Walnut Creek, California 94596 Resource Project Manager Public Utilities Department Mr. Dennis M. Smith, Chief City of Riverside Radiological Progra:ns Division City Hall Govcrnor's Office of Emergency Services 3900 Main Street 2800 Meadowview Road Riverside, California 92522 Sacramento, California 95832

4 l '

, ENCLOSURT 1

[ p!PE WALL THINNING INSPECTION PROGRAM IMPLEMENTATION EVALUATION CRITERIA l

4

_p urpose ,,

l l The purpose of this instruction is to define the evaltation criteria for nytew I cf licensee's erosion /cormsfon monitoring program and its implementation. l I

Through selective examination of the licensee s crogram for monitorin pipe I

wall thinning, the procedures defining'the activities to be accomplis .ad are -'

verified for consistency with licensee s program cosmiitment.

l Requirements i 1.. Review of Licensee's Erosion / Corrosion Monitoring Program

1. Does the licensee's program have well defined criteria for:
a. selecting inspection points ,
b. detemining inspection frequency
c. defining method of inspection
d. making replacement / repair decisions
2. Does the licenste's program meet the intent of NUMARC guidelines?

i II. Review of Licensee's Implementation of ErosioniCorrosion Monitoring i Program .

1. Inspection procedures and guidelines j I
a. Procedures have been properly reviewed and approved before their implementation. I
b. Procedures cover periodic monitoring of high energy safety- -

i I

ralated end nonsafety-related carbon steel. *

c. Procedures provide for qualification or certification of 1 personnel, equipment, or proceAres consistent with establ.shed program counttments.

[ . 2. Qualification of inspectors ,

a. Personnel conducting NDE examinations are properly certified
b. The licensee has a well developed training pmgram

) 3. Inspection method and uguipment calibration l

a. Method of NDE and related equipments have been calibratad agat, %own standards for types of metals and range of i thick, ss to be measured .

l l

L s 9

- l

. ,._y.... .

i l

./ l

b. Measurements of pipe wall thickness are being accomplisWd in j accordance with established instructions and results are being i appropriately documented.
4. Evaluation of the results of pipe wall measurements and determinations on the need for corrective action or frequency of continued periodic monitoring is being ar. comp 11shed by qualified personnel.
5. Need for replacemen.. -

ipair, or continued monitoring of piping which has been subjected to pipe wall thinning has been (or will t>e) I determined and schedule established is yet to be accomplished.

6. Administrative control and management support 111. History of Pipe Wa11 Thinning

' ~

1. When did u licensee develop its 4tesion/ corrosion monitoring program? -

I

2. History of pipe wall thinning i 1
3. Failure analysis and damage mechanism l

!Y. Review of Licensee's Plan for Developing or Revising its Erosion / Corrosion Monitoring Program .

. 1. Development of long-ters inspection program for single-phase systerr.s

2. Development of guidelines and computer code for two-phase piping systems similar to those developed for the single phase systams.

V. Verification of Licensee's Csvitments Nade In its Response to MRC bulletin 87-01 1

e 9

l e

e ,

---,v -

s v , + , - - - - , , , ,w ,,n.,a w ,,,su-,w,-n, - w,-,wwwm, .,,.,,w- --- - . - _ - - - - - - - -+,, -nw,-v,, e, -w a,e,--sm-- mw_ _m--

'e F

MEETING NOTICE DISTRIBUTION

[iEEe5Nde ~ h PDV Reading' ~"

NRC PDR Local PDR TMurley/JSniezek DCrutchfield GHolahan CMiller OGC-White Flint

-EJordan PGrimes I GKnighton ACRS(10)

OPA NRC Participants ,

Service List (See next page)

Licensee FMiraglia DKirsch 1

Project Manager j WLanning GPA/PA VWilson '

DMorley Receptionist (Building where meeting is being held) l l

)

l l

l QFot Gl,

  • Meetings between NRC technical staff nnd applicants. for licenses are open for ,

interested members of the public, petitioners intervenors, or other parties to I f attend as observers pursuant to *0 pen Meetia.4 Statement of NRC Staff Policy"  :

43 Federal Register! 28058,6/28/87. l

" l

j. p