1 DEC 3 01986 a-t' Docket No. 50-309 Maine Yankee Atomic Power Company ATTN: Mr. J. B. Randazza Vice President Nuclear Operations 83 Edison Drive Augusta, Maine 04336 Gentlemen:
Subject:
Safeguards Regulatory Effectiveness Review at the Maine Yankee Atomic Power Station The NRC's Office of Nuclear Material Safety and Safeguards (NMSS) is in the process of conducting a Regulatory Effectiveness Review (RER) at operating nuclear power plants. The Maine Yankee Atomic Power Station is scheduled for such a review during the week of April 6-10, 1987.
The purposes of the RER are to evaluate the overall effectiveness of the safeguards program and to determine whether existing safeguards regulations yield the level of protection intended by NRC. The RER supports the NRC's quality assurance program for safeguards, as it applies to both the Maine Yankee security systems and the NRC's regulations. The RER will complement but will be independent of the licensing and inspection functions. Specific details regarding the conduct of the RER, including identification of the team members, will be provided to you at a later date.
So that NMSS can prepare for the RER at the Maine Yankee Atomic Power Station, you are requested to provide the information identified on the enclosed list directly to Mr. Robert Dube, Chief, Safeguards Evaluation Section, of that office by January 30, 1987.
If you have any questions regarding this request, please contact R. R. Keimig of my staff at (215) 337-5255.
The response directed by this letter is not subject to the clearance proce-dures of the Office of Management and Budget as required by the Papemork Reduction Act of 1980, PL 96-511.
Your cooperation with us in this matter is appreciated.
Sincerely, Original Sicnod By!
James H._ Joyner Thomas T. Martin, Director Division of Radiation Safety and Safeguards
Enclosure:
As stated
\\k 8701070369 861230 PDR ADOCK 05000309 4 600 j
p PDR T
l b'
Maine Yankee Atomic Power Company 2
DEC 3 01986 cc (w/ encl):
C. E. Monty, President C. D. Frizzle, Assistant Vice President / Manager of Operations J. H. Garrity, Plant Manager P. L. Anderson, Project Manager G. D. Whittier, Licensing Section Head J. A. Ritsher, Attorney (Ropes and Gray)
Phillip Ahrens, Esquire Public Document Room (PDR) local Public Document Room (LPCR)
Nuclear Safety Information Center (NsIC)
NRC Resident Inspector State of Maine bcc:
RegionIDocketRoom(withconcurrences) section Chief, DRP P. Sears, LPM, NRR R. Dube, NMSs
)$ss s
yMITHg pMARTIN ss Ds D ss KtIMIG J0YNER f
12-19-54 n-lHf1-gujQlGt.
OFFICIAL RECORD COPY
11550-FE-1A Main One-Line Diagram 11550-FE-1E 4160-V One-Line Diagram 11550-FE-1M 480-V One-Line Diagram 11150-FM-78A Operating Valve NOS Diagram (OVND) - Secondary Component Cool Piping 11550-FM-788 OVND - Secondary Componeni Lool Piping 11550-FM-77A OVND - Service Water (SW) Piping 115$0-FM-73A OVND - Steam Generator Feedwater 11510-FM-101 A OVNO - Misc. Piping 1155 0-FM-72A OVND - Auxiliary Steam Piping 1155S-FM-70A OVND - Main Steam Piping 11550-FM-828 OVND - Makeup Water Treating Piping 11550-FM-74A OVND - Condensate Piping
- 1155C-FM-94A 20VND - Primary Component Cool Piping 11550-FM-948 OVND - Primary Component Cool Piping 11550-FM-80A OVND - Lube and Fuei 011 Piping 11550-F8-2A Fire Protection Arrangement 11550-FM-918 OVND - C & V Cont. and MP Safety Injection System 11550-FM-92A OVND - RHR Cont. Spray and LP Safety Injection System 11550-FM-91 A OVND - C & V Cont. and MP Safety Injection System 11550-FM-90A Reactor Coolant Piping 11550-FM-1A Reactor Plant - El. 46 ft 11550-FM-18 Reactor Plant - El. 20 ft 11550-FM-1C Reactor Plant - El. 2 ft, 19 ft 2 in.
11550-FM-10 Reactor Plant Drawing 11550-FM-1E Reactor Plant Sections AA and CC 11550-FM-2A Arrangement - Primary Auxiliary Building 11550-FM-28 Arrangement - Primary Auxiliary Building 11550-FM-38 T8 Mezzanine Floor 11550-FM-3J Auxiliary Bay 11550-FM-3L Service Building l
l e
Enclosure
.