Requests Concurrence in Return to Power After Completion of Actions Required for Restart from Cycle IX Refueling Outage
ML20207D869
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 07/10/1986
From: Papay L
SOUTHERN CALIFORNIA EDISON CO.
To: Martin J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
NUDOCS 8607220209
Download: ML20207D869 (2)


Text

"

l

{

r~ ? "'

wu Southem Califomia Edison Company

p. o. eOx 800 2244 WALNUT GROVE AVENUE ROSEMEAD, CALWORNIA 91770 PAPAY TELEPHONE scnion vice entsiotar eisaoa-un

)

July 10, 1986 Mr. John B. Martin U. S. Nuclear Regulatory Commission Region V 1450 Maria Lane, Suite 210 Walnut Creek, California 94596-5368

Dear Mr. Martin:

Subject:

Docket No. 50-206 Completion of Actions Required for Restart from Cycle IX Refueling Outage San Onofre Nuclear Generating Station Unit 1

References:

A.

Letter, J. B. Martin, NRC, to Harold B. Ray, SCE, dated November 21, 1985 8.

Letter, M. O. Medford, SCE, to A. E. Chaffee, NRC, dated April 8, 1986 San Onofre Unit 1 is currently in the startup process and is expected to enter Mode 2 late in the day on July 11, 1986. As a result of the November 21, 1985 water hammer event, you sent us a letter (Reference A) confirniing that we would not restart the unit without your concurrence.

The purpose of this letter is to request your concurrence for return to power.

As a result of our investigations into the events surrounding the water hammer, we submitted the Reference B report. That report included a i

listing of' actions we would be taking both prior to returning the unit to service and in the future.

By this letter, I certify that all the actions required for return to service of that report as amended by subsequent correspondence have been completed or will be completed at the appropriate point in the startup process.

In addition to our in-place management control processes, this certification is based on a special surveillance of these commitments by the Quality Assurance Organization.

In addition to the actions required as a result of the water hammer event, other commitments are required to be completed during this outage.

I i

fDR607220209 860710 ADOCK 05000206 p

PDR llI Inlb

.?

Mr. J. B. Martin 21' July 10, 1986 certify that these commi,tments have been completed or will be completed at the appropriate point in the startup process. This certification is based on a review of our in-place management control processes performed by my staff.

If there are any questions, or you require further information, please let me know.