7590-01 UNITED STATES NUCLEAR REGULATORY COMMISSION DOCKET NOS. 50-329, 50-330 l
l CONSUMERS POWER COMPANY MIDLAND PLANT, UNITS 1 AND 2 l
l NOTICE OF WITHDRAWAL OF APPLICATION FOR OPERATING LICENSE l
AND TERMINATION OF PROCEEDING On July 11, 1986, Consumers Power Company (CPC) filed a motion which requested authorization for withdrawal of its application for licenses to operate Units 1 and 2 at Midland and for dismissal of the operating license i
l proceeding before the NRC Atomic Safety and Licensing Board (ASI.8). On December 17, 1986, the ASLB issued a Memorandum and Order granting the motion and authorizing the staff to permit withdrawal of the operating license l
appitcation subject to such conditions as the NRC staff finds to be warranted.
1 i
The ASLB premised its authorization on certain commitments made by CPC.
The NRC staff finds that no conditions are warranted. However, it notes CPC's commitment to take the appropriate steps to assure that the structures, facilities and surrounding areas will be stable and suitable for their intended use in the contemplated plant in the event the site is used for a gas-fired cogeneration facility.
The NRC staff also notes CPC's commitment to modify the Emergency Cooling Water Reservoir (ECWR) by back-filling and then trenching to the #003 outfaII structure on the east side of the cooling pond, so that the entire ECWR can be gravily-drained in the event the site is completely abandoned.
CPC has also conenitted to notify the NRC staff when conversion to a gas-fired facility begins or, alternatively, when the site is abandoned.
nl 3
9 The site of the Midland Plant, Units 1 and 2, is located just south of the City of Midland in Midland County, Michigan. The Construction Pemits, CPPR-81 and CPPR-82, were issued on December 15, 1972. On May 24, 1984 and September 11, 1984, CPC filed timely requests to extend the completion dates to December l.1989 and July 1,1989, respectively. On July 1, 1986, CPC withdrew its re' quest to.axtend the latest completion dates in its Construction Permits. An Environmental Assessment and Fir. ding of No Significant Impact was published in the FEDERAL REGISTER on November 20,1986(51FR42024).
Correspondence concerning this application will continue to be maintained at the Commission's Public Document Room,1717 H Street, N.W.,
Washington, D. C.
20555 and at the Grace A. Dow Memorial Libra'ry,1710 West St. Andrews Road, Midland Michigan 48640 for at least one year.
Dated at Bethesda, Maryland, this 18th day of December 1986.
FOR THE NUCLEAR REGULATION COMMISSION e-H rbert N. Berkow, Director Standardization and Special Projects Directorate Division of PWR Licensing-B Office of Nuclear Reactor Regulation a
.