September 22, 1986 Docket No. 50-260 MEMORANDUM FOR: Daniel R. Muller, Director BWR Project Directorate #2 Division of BWR Licensing FROM:
Richard J. Clark, Project Manager BWR Project Directorate #2 Division of BWR Licensing
SUBJECT:
MEETING WITH TVA ON BROWNS FERRY START-UP ISSUES On September 15-17, 1986, representatives of NRR, IE and Region II met with TVA at Browns Ferry to develop "best estimate" schedules for both TVA and NRC actions on Browns Ferry Unit 2 restart issues. The agenda for the meeting is shown in Enclosure 1. is the tentative schedules developed during the meeting.
The most significant discussions /information from the meetings is as follows:
1.
The programs at TVA are aimed at restarting Unit 2 in June or July 1987.
TVA has 4,852 people currenting onsite plus many additional supporting personnel in Knoxville, Chattanooga, Muscle Shoals, etc. TVA is attempting to add about 1,000 additional contract engineers.at the site. A significant commitment of NRC resourecs will be required in the next 9 months to review and inspect TVA activities in order to keep pace with TVA's schedule.
2.
TVA submitted Volume 3 of the Nuclear Performance Plan on August 28, 1986.
Volume 3 - in conjunction with Volume I - constitutes TVA's. plan for actions which the licensee has concluded are sufficient to restart Unit 2.
Preliminary comments on the plan have been received from all NRR and IE review groups. The schedule that has been requested from all reviewers is to provide a draft safety evaluation and/or any questions by Friday,-
October 31, 1986.
3.
Safety evaluations or inspection reports will be issued on individual issues as they are resolved. An overall safety evaluation summarizing the results of all NRC evaluations will be issued prior to Unit 2 startup.
Original signed tif ad J. Qad 8610070356 860922 PDR ADOCK 05000260 Richard J. Clark, Project Manager P
PDR BWR Project Directorate #2 Division d BWR Licensing
Enclosures:
As stated 0FFICIAL RECORD COPY DBL:PD# d DBL:PD#2y DB D#2 RClark: W '
MGrotenhuis Q) I r 9////86 9/n/86 9/jo/86
AGENDA As Revised 9/12/86 M nday. September 15.1986 - 1:00 p.m. - NRR Review plans for submittals to NRC for:
V-A Integrated Schedule V-B Unit 2 Reload Modification Amendment V-C Appendix J Exemption V-D Organizational Change Amendment V-E ISEG Site Licensing V-F Cable EQ Program V-6 In-service Pump and Valve Test Program V-H Tech Spec Clarification V-I RETS I-A Site Management Organization Monday. September 15.1986 - 5:00 - 6:00 P.M.- NRR NRC Preliminary Views of Volume 3
- 0. Muller, R. Clark, M.Grotenhuis Tuesday. September 16. 1986 - NRR and Reaion II 8:30-12:20 Management Overview: ' Program Descriptions and Status 8:30 Introduction M. J. May 8:40 Site Director Perspective H. P. Pomrehn Site Management and Organization
~
Overall Site Activities Schedule 9:00 Employee Concerns and Employee Allegations M. Martin /T. '. Newton 9:20 Design Control J. Chapman 9:50 ISSCC including Safe-Ends E. Hartwig 10:10 Welding (Structural)
L. Martin (DNE-K) 10:40 Plant Management and Organization and Training R. L. Lewis /R. McKeon 11:00 Plant Procedures Upgrade R. McKeon 11:20 Appendix R C. Anderson /R. Lemke 11:40 Environmental Qualification R. Martin 12:00 Restart Commitment Tracking M. J. May 12:30-1:15 Lunch (Ordered Individually from Catfish Inn Menu) 1:15-2:00 Review Items from Monday, September 15 with Region II and NRR l
2:00-5:00 Develop Scope for TVA-NRC Interactions on Individual Items 2:00 Employee Concerns, Employee Allegations, M. Martin /T. Newton 2:30 Design Control J. Chapman W. Pattison 3:00 Environmental Qualification R. Martin 3:30 Operational Readiness Program /RPIP Closecut R. T. Smith 4:00 Restart Test and Inspection R. McKeon 4:30 Procedures Upgrade Program R. McKeon
]
t i
As Revised 9/12/86 AGENDA (Cont'd)
Wednesday. September 17. 1986 - 8:00 - 10:30 A.M. - NRR and Reaion II Develop Scope and Plan for TVA-NRC Interactions on Individual Items:
8:00 Seismic Design E. Thomas 8:15 Appendix R C. Anderson R. Lemke 8:30 Pipe Inspection, Stress Relieving. Repairs E. Hartwig 8:45 Contractor Recommendations R. T. Smith 9:00 Electrical Design Issues R. Reeves D. Faulkner 9:15 Welding (Structural)
L. Martin 9:30 Quality Assurance G. G. Turner 9:45 Maintenance Improvement Program T. F. Ziegler 10:00 NSRS Reports C. Burke 10:15 MSIV Leakage Control Program D. C. Mims LSR:DGC 09/11/86 0160y 4
. _..~.-_._ ____...._.. _.. _ - - - _ _ _..
8 1
f
?
~
BROWNS FERRY RESTART ISSUES c
50.54f Vol. III Letter Section Item I.
Management (NRR)
A.
Site Management Organization Vassallo 1
II.1, A.1.1 b, C B.
Employee Concerns Singh II.2.7, D.8 C.
Employee Allegations Muller D.
NSRS Reports Singh D.9, 0.10 II.
Design Modification (NRR)
A.
Seismic Design Liaw 5
III.3 B.
Fire Protection Hulman 11 III.5 C.
Pipe Inspection / Repairs Liaw III.7 D.
Contractor Recommendations Muller 7
B E.
Electrical Design Issues Srinivasan III.4 F.
Structural Welding Liaw III.6 III. Design Control (IE)
A.
Environmental Qualification Hubbard 8
III.1 B.
Quality Assurance Grimes II.2.6, 11.1.2.6, 0.6 C.
Design Control (Configuration Control Management)
Architzel 6
III.2 IV.
Restart Inspection (RII)
A.
Regulatory Performance Improvement Program Cantrell 2
111.2.2, A.1.2 B.
Operational Readiness Program Weiss 2
III.9, A.1.2 C.
Training Julian II.2.3 D.
Restart Test and Inspection Jape III.8 E.
Maintenance Improvement Program Monroe 3
II.4 F.
Physical Security Program McGuire II.7 G.
Post Accident Sampling System Monroe H.
MSIV Leakage Reduction Program Jape I.
Static 0 Ring V.
Licensing Review (NRR)
A.
Integrated Schedule Muller 4
11.9.3 B.
Unit 2 Reload Modification 10 A.1.10a Amendment (complete)
C.
Appendix J Exemption Liaw D.
Organizational Change Amendment Vassalo 10 E.
Independent Safety Engineering Group Evaluation Muller 9
11.1.2.7.1 F.
Cable Environmental Qualification Program Srinivasan 8 G.
Inservice Pumps and Valve Test Program Liaw H.
Technical Specification Clarification Muller
_f 50.54f Vol. III Letter Section Item I.
Radiological Environmental Technical Specifications (RETS)
Hulman 10 A.1.10e J.
Operator Overtime (complete)
A.1.10d K.
Offgas Monitors (complete)
A.I.10f V.
Licensing Review (continued)
(NRR)
L.
RHR Crosstie (complete)
A.1.10c M.
Operator Requalification (complete)
N.
PASS (interin) (complete) 0.
PRA 4
h I
i J
l i
?
I.
MANAGEMENT I.
A.
SITE MAAAGEMENT ORGANIZATION Lead: Vassallo MAJOR TASK RESPONSIBILITY DATE
- 1. Include Browns Ferry Site Management TVA Ccmplete Organization and an explanation of the functions and responsibilities of each major organization in Nuclear Performance Plan - Volume 3 (8-29-86)
- 2. Prepare draft safety evaluations NRR/IE/RII 10-31-86 and issue requests for any additional information (RAI) needed to complete reviews.
- 4. Input from Employee Concern Programs NRR 1/87
- 5. Site Visit NRR/RII 2/87 6'. Prepare safety evaluation report (SE)
NRR 3/87 i
i
t
~
I.
MANAGEMENT I.
B.
EMPLOYEE CONCERNS Lead:
B.K. Singh MAJOR TASK RESPONSIBILITY DATE
- 1. Informal presentation to NRC of TVA Ccmplete Employee Concern Program (8-05-86)
- 3. Program submitted to NRC (8-19-86)
TVA Complete
- 4. Browns Ferry management reviews TVA 9/86-2/87 investigations reports and Site Director determines needed corrective actions
- 5. Submit lists-(numerically and by category)
TVA 10/86 of concerns in ECSP and new ECP (after 2-01-86).
- 6. As TVA completes subcategories in ECSP, NRR/IE/RII 10/86-3/87 evaluate the adequacy of the implementation of TVA's actions and plans to address and resolve employee concerns that are specific and generic to Brown's Ferry.
- 7. Evaluate new ECP NRR/IE/RII 9/86-4/87
I.
MANAGEMENT I.
C.
EMPLOYEE ALLEGATIONS Lead: Muller MAJOR TASK RESPONSIBILITY DATE
- 1. Provide appropriate allegations RII 09-30-86 to TVA (e.g., those allegations that can be transmitted without compromising confidentiality of alleger)
- 3. Evaluate TVA responses and corrective actions RII I/87
- 4. Investigate other allegations RII 9/86-4/87 (Those not transmitted to licensee)
- 5. Prepare final report on pending allegations
- NRR 4/87 i
- Any future allegations will be processed in accordance with NRC's normal allegation tracking system. i
\\
I I.
MANAGEMENT I.
D.
NSRS PROBLEMS Lead:
B.K. Singh MAJOR TASK RESPONSIBILITY DATE
- 1. TVA submit copies of NSRS reports along TVA 10/86 with summary of actions taken or proposed actions on recommendations (includes reports which were in final draft form prior to NSRS reorganization into NMRG).
- 3. Prepare SE on NSRS reports 12/86
TVA is including NSRS and SWEC reports in the EC progrum.
a II. DESIGN MODIFICATIONS II.
A.
SEISMIC DESIGN Lead: Liaw MAJOR TASK RESPONSIBILITY DATE OVERALL SEISMIC PROGRAM
- 1. Provide summary of overall TVA 12/86 seismic reevaluation program in response to NRC letter of 7-31-86 CABLE TRAYS
- 1. Submit UE&C Report describing TVA Complete recommended interim modifications for Unit 2 (5-02-86)
- 2. Meeting on program (5/14-5/15/86)
NRR/RII Complete
- 3. Review above report on findings, analysis, NRR 9/86-10/86 calculations, and proposed modifications (for unit 2 interim)
- 5. Complete modifications TVA 10/86
- 6. Inspection / Report RII 11/86 PIPING AND SUPPORTS (IE BULLETINS 79-02,79-14)
- 1. Request additional information (7-31-86)
NRR Complete
- 2. Provide Phase I interim program, interim TVA 12/86 operability criteria, new artificial time history for the seismic analysis, long-term program, etc.
- 3. Provide final report on program TVA 2/87
- 4. Site visit NRR/RII 2/87
- 6. Complete modifications TVA 3/87
- 7. Inspection / Report RII 4/87 _. _ -.
?
Seismic continued MAJOR TASK RESPONSIBILITY DATE CONDUIT AND SUPPORTS
- 1. Meeting on program (5-14-5/15/86)
NRR/RII Complete
- 2. Provide sumary of program, sumary TVA 10/86 of extensive test program at Wyle Labs, interim acceptance criteria and sumary of the approximately 450 modifications
- 3. Evaluate program; site visit NRR/RII 11/86
- 5. Complete modifications TVA 3/87
- 6. Inspection / Report RII 4/87 CRD PIPING
- 1. Provide sumary of reanalysis of CRD TVA 10/86 insert and withdrawal piping systems, description of modifications to existing Uni-struct supports and basis for proposed 5% damping
- 2. Meeting with TVA NRR/RII 11/86
- 3. Submit corrective action program TVA 12/86
- 5. Complete modifications TVA 3/87
- 6. Inspections / Reports RII 4/87 HVAC CONCERNS
- 1. Support sumary of reanalysis program TVA 12/66 and modifications to systems
- 2. Complete modifications TVA 3/87
- 3. Inspection / Report RII 4/87 :
?
Seismic continued MAJOR TASK RESPONSIBILITY DATE Torus Modifications
- 1. Complete modifications TVA 9/86
- 2. Inspection / Report (Projected fill RII 10/86 date for adding water into torus is mid October 1986)
Torus Attached Piping
- 1. Complete modifications TVA 12/86
- 2. Inspection / Report RII 1/87 II. DESIGN MODIFICATIONS II.
B.
FIRE PROTECTION Lead:
Hulman MAJOR TASK RESPONSIBILITY DATE 1.
Submit " Appendix R Fire Protection TVA Complete and Safe Shutdown Systems Analyses" NEDC 31119 (1-31-86) 2.
Site visit (6/23-6/24/86)
NRR/RII/IE Complete 3.
Request for additional information NRR Complete (8-07-86) 4.
Submit revised technical exemption request TVA 9/86 7.
Prepare technical exemption package NRR 10/86 8.
Prepare fire protection emergency procedures TVA 12/86 9.
Site Visit NRR 11/86
- 10. Submit TS changes TVA 12/86
Preliminary audit NRR/IE/RII 2/87 13.
Issue TS amendment NRR 3/87
- 14. Complete 2/3 of modifications TVA 4/87
- 15. Complete training on revised procedures TVA 4/87 for at least 2/3 of plant staff
- 16. Audit NRR/IE/RII 5/87
& Contractor
- 17. Complete modifications and TVA 6/87 training 18.
Inspection / Report RII 6/87
~
II. DESIGN MODIFICATIONS II.
C.
PIPE INSPECTION, STRESS RELIEVING, REPAIRS Lead: Liaw MAJOR TASK RESPONSIBILITY DATE
- 1. Request information on IGSCC (3-26-86)
NRR Complete
- 2. Respond to NRC March 26, 1986 TVA 9/86 letter including leakage limits in the Technical Specifications
- 3. Provide report of recirculation nozzle TVA Complete safe-end inspections (LER 260/86010)(8-01-86)
- 4. Provide additional evaluation of safe-end TVA 9/86 cracks
- 5. Review results of inspections, weld overlays, NRR 10/86 repairs and IHSI program which were submitted by TVA
- 6. Review the TVA response to the NRC NRR 10/86 March 26, 1986 letter
- 8. Inspection / Report RII 3/87 l
.g.
II. DESIGN MODIFICATIONS II.
D.
CONTRACTOR RECOMMENDATIONS Lead: Muller MAJOR TASK RESPONSIBILITY DATE
- 1. Include in Nuclear Performance Plan -
TVA partially Volume 3 the proposed disposition of complete contractor recommendations (8-29-86)
- 2. Provide summary of the most significant TVA 10/86 recommendations by major contractors and TVA's proposed disposition / action on these recommendations.
Include cross-references to Volume 3 and schedule for completion of TVA actions
- 3. Evaluate whether TVA's proposed actions NRR/RII 12/86 (a) prior to startup of a unit, and (b) in the longer term, are appropriate A. Site visits NRR/RII 1/87-3/87
- 5. Prepare Safety Evaluation or Inspection Report l
i
- (
O
~
II. DESIGN MODIFICATIONS II.
E.
ELECTRICAL DESIGN ISSUE Lead: Srinivasan MAJOR TASK RESPONSIBILITY DATE 1.
Provide general description of electrical TVA Complete calculations program in Nuclear Performance Plan - Volume 3 (8-29-86) 2.
Meeting to discuss areas NRR/TVA 10/E6 requiring reanalysis to demonstrate capability for restart, safe operation and safe shutdown of Unit 2 3.
Descriptionofshort-term (Unit 2)
TVA 10/86 and long-term program 4.
Perform electrical calculations TVA 10/86-3/87 S.
Provide any questions needed to clarify this issue NRR 6.
Provide responses to NRC questions TVA 7.
Perform necessary modifications TVA 8.
Prepare test procedures and test systems TVA 9.
Review electrical calculations NRR 10.
Inspect modifications RII 1 i
.--,-.----n
---~~.--,--ac..
II. DESIGN MODIFICATIONS II.
7.
WELDING Lead: Liaw MAJOR TASK RESPONSIBILITY DATE
- 2. Request for additional information NRR 9/86
- 4. Submit Phase I report TVA 11/86
- 5. Site visit to review NRR/RII/IE 11/86 reinspection program
- 6. Submit Phase II report TVA 1/87
- 7. Review Phase I and II reports NRR/IE/RII 2/87
- 9. Inspection / Report NRR/IE/RII 4/87
& contractor 12 -
n
,,,,,.,-,,,,-a-
n.
=
III. DESIGN CONTROL III.
A.
ENVIRONMENTAL QUALIFICATION PROGRAM Lead: Hubbard MAJOR TASK RESPONSIBILITY DATE 1.
Describe EQ program and status in the TVA 8/29/86 Nuclear Performance Plan - Volume 3 2.
Conduct a preliminary audit of documentation NRR/IE/RII 11/86 packages for selected pieces of equipment 3.
Inform NRC when TVA is 30-40% complete on TVA 1/87 EQ packages 4.
Conduct an inspection of TVA's program to IE/NRR/RII 2/87 implement 10 CFR 50.49 Subtasks:
- a. Follow up on audit findings
- b. Review selected packages for completeness
- c. Review programs to maintain qualification status
- d. Physical verification of as-installed condition
- e. Review corrective actions for Westec findings
- f. Review internal procedures for implementing 10 CFR 50.49
- g. Review resolution of employee concerns on EQ 5.
Write SE input to support startup NRR/IE NRR/IE 1/87 Write-up will identify issues that remain as potential enforcement items / unresolved items /open items 6.
TVA Certification that program is complete TVA 6/87 7.
Reinspect corrective actions and perform IE/NRR/RII final review of related documentation packages 8.
Evaluate TVA 10 CFR 50.49 certification NRR/IE/RII submittal 9.
Write final inspection report IE/NRR/RII
- 10. Prepare supplement to SE NRR/IE I I I.' DESIGN CONTROL III.
B.
QUALITY ASSURANCE PROGRAM Lead: Grimes MAJOR TASK RESPONSIBILITY DATE
- 1. Submit QA organization and TVA Complete responsibilities in Nuclear Performance Plan, Volume 3 (8-29-86)
- 3. Review revised QA topical report NRR/IE/RII
- 4. Itemized verification by direct inspection RII/IE 1/87-2/87 of selected items contained in the Browns Ferry Performance Plan
- 5. Itemized verification by direct inspection RII/IE 1/87 of selected items contained in the Corporate Nuclear Performance Plan
- 6. Assessment of corrective action program at RII Browns Ferry relative to audit findings and i
other TVA identified problem areas
- 7. Assessment of TVA's ability to identify RII problems and to correct those problems
- 8. Prepare SE Input RII 4/87
- 9. Complete inspection report RII I4
.~,
--,--..-=--.,---,--,,n-
.-.-------,.,,-,,---,,,--,.,.,r
,---.-----....-_n,
?
- ' III. DESIGN CONTROL III.
C.
CONFIGURATION CONTROL MANAGEMINT Lead: Architzel MAJOR TASK RESPONSIBILITY DATE 1.
Provide response to 50.54(f) letter, item TVA Complete 8.6 on design control in-Nuclear Performance Plan - Volume 3 (8-29-86) 2.
Provide questions / comments on above NRR/IE 9/86 3.
Meeting for TVA to present programmatic TVA/IE/NRR/RII 10/86 description of Browns Ferry Design BaselineandVerificationProgram(DBVP) 4.
Submit DBVP TVA 11/86 5.
Review and evaluate TVA's response to the IE/RII 11/86 50.54(f) letter, Item B.6 on design control 6.
Review and evaluate the independent assessment IE/RII 11/86 of engineering design control at Browns Ferry, which was completed by TVA personnel 7.
Review and evaluate any design control items IE/RII 11/86 resulting from employee concerns / allegations 8.
Review, inspect, and evaluate seismic design NRR/IE/RII (SeeItemII.A) of cable trays, piping supports and HVAC system 9.
Direct inspection of DBVP to assess adequacy IE/RII 12/86-1/87 of Browns Ferry program for design modifications, incorporation of contractor recommendations, and resolution of ECN's.
10.
Followup inspections IE/RII
- 11. Notification to NRC that 2/3 of systems to be TVA covered in Design Baseline Verification Program are completed 12.
From review Design Control Program at Browns IE/RII 3/87 Ferry, provide input to NRR for SE 13.
Prepare draft SE input covering program NRR 3/87
- 14. Followup inspections IE/RII 15.
Complete remaining 1/3 of systems and identify TVA 5/87 items that may be deferred past restart III.
C.
CONFIGURATION CONTROL MANAGEMENT cont.
MAJOR TASK RESPONSIBILITY DATE
- 16. Complete procedures upgrade and retraining TVA retraining resulting from DBVP 17.
Follow-up inspection for design control IE/RII related items.
- 18. Final inspection, prepare summary IE/RII inspection report and supplemental SE input 19.
RESTART INSPECTION IV.
A.
REGULATORY PERFORMANCE IMPROVEMENT PLAN Lead: Cantrell MAJOR TASK RESPONSIBILITY DATE
- 1. Include in Nuclear Performance Plan TVA 8/29/86 Volume 3 the programs which address RPIP items
- 2. Review outstanding RPIP items to determine RII 9/86 which item (complete or incomplete) should beincludedintheNPP-Volume 3)
- 3. Verify each of the above items judged to be RII included are included in the NPP
- 4. Verify each of those itens is implemented as part of the NPP (Not a separate effort).-
- 5. Issue an order to TVA confirming that the RPIP RII is closed and the open item will be completed as part of NPP
- 6. Prepare a safety evaluation documenting RII justification for the above IV. RESTART INSPECTION IV.
B.
OPERATIONAL READINESS PROGRAM.(ORP)
Lead: Weise MAJOR TASK RESPONSIBILITY DATE 1.
Describe Operational Readiness Program TVA Complete in Nuclear Performance Plan, Volume 3 -
(8-29-86) 2.
Develop policy position regarding TVA 10/86 implementation at ORP 3.
Complete review of ORP portion of RII 10/86 Nuclear Performance Plan 4.
Meet to programmatically review TVA/NRC 12/86 Operational Readiness Plan 5.
Provide detailed ORP to NRC TVA 6.
Review HP Program to determine acceptability RII of equipment, personnel, procedures, etc.
s,
4 7.
Review Open Items List (0IL) for issues that RII must be resolved / corrected prior to operation 8.
Review outstanding NUREG-0737 issues and RII determine acceptability of TVA action 9.
Review licensee procedures and training to RII assure proper assessment of 10 CFR 50.59 issues and potentially reportable occurrences under 10 CFR 21, 50.72 and 50.73
- 10. Review licensee procedures and implementation RII of corrective actions as committed to in Nuclear Performance Plan
- 11. Review implementation of site security plan RII
- 12. Review adequacy of interface controls between RII units, including temporary alternation controls
- 13. Review operating, emergency operating, and RII surveillance procedure adequacy
- 14. Review plant todifications since last shutdown RII to determine if additional testing needed
- 15. Review surveillance test results to assure RII readiness to change mode IV.
B.
OPERATIONAL READINESS PROGRAM (ORP) cont.
MAJOR TASK RESPONSIBILITY DATE
- 16. -Inspect operator actions while making RII system lineups for operation
- 17. Final Inspection report RII l
l 1
1 2
1 19 -
4 j
T
..--r
~...,-..-._w
--_.._,,_,.-y.
..--,_m,--.,.-..--.,----c,--.mwo-.
.~ws,.,.-_..e-.e.,-
. -. - ~- - -... -,e.,
IV. RESTART INSPECTION IV.
C.
TRAINING Lead: Julian MAJOR TASK RESPONSIBILITY DATE
- 1. Verify that the requalification program has been successful in maintaining the competency of license operators for restart and safe operation.
- Audit TVA requalification program completed RII 3/13/86
- Repeat audit of requalification program RII (reactorsystems)
- Conduct requalification evaluations of the RII first trainin group (approximately June 16, 1986
- Complete evaluation report and issue SE RII
- 2. Training assessment to determine the effectiveness of licensed and unlicensed operator training
- Inspection RII
- SE input RII
- Issue inspection report RII
- 3. Issue final SE on training activities RII _
^
IV.
RESTART INSPECTION IV.
D.
RESTART TEST AND INSPECTION PROGRAM Lead: Jape MAJOR TASK RESPONSIBILITY DATE 1.
Describe restart test program in Nuclear TVA Complete Performance Plan - Volume 3 (8-29-86) 2.
Meet to review scope, test specs, punch TVA/NRC 10/86 list of restart test program 3.
Develop detailed restart test prcgram and schedule TVA 4.
Review licensee plan to determine adequacy of NRR/RII 10/E6 pre-operational test program 5.
Provide comments / questions on restart RII test program 6.
Develop test specifications and procedures TVA 7.
Develop inspection schedule for pre-operational RII test program 8.
Conduct inspections of pre-operational program RII 9.
Provide SE Input to support startup RII 10.
Develop schedule to provide 24-hour coverage RII during startup 11.
Conduct inspections during startup RII
=
~
IV.
RESTART INSPECTION IV.
E.
MAINTENANCE IMPROVEMENT PROGRAM Lead: Monroe MAJOR TASK RESPONSIBILITY DATE 1.
Describe maintenance program in Nuclear RII Complete Performance Plan - Volume 3 (8-29-86) 2.
Review TVA approach for response to Generic TVA Letter 83-28, covering incorporation of Vendor Manuals, and recommendations into Maintenance Procedures 3.
Submit details of Maintenance Improvement Program TVA 4.
Meet to review program TVA/RII 5.
Review maintenance section reorganization for RII qualification and adequacy 6.
Review maintenance equipment history tracking RII history program 7.
Evaluate control of vendor manual implementation RII schedule for adequacy 8.
Review maintenance liiictions personnel training RII program 9.
Evaluate adequacy of modification control program RII
- 10. Evaluate planning and scheduling coordination of RII maintenance activities 11.
Review the employee concerns program RII 12.
Prepare SE inputs RII 13.
Prepare inspection reports RII l l l
- IV.
RESTART INSPECTION IV.
F.
PHYSICAL SECURITY PROGRAM Lead: McGuire MAJOR TASK RESPONSIBILITY DATE
- 1. Review Security Corrective Actions RII, PSS in Licensee's RPIP
- 2. Audit Licensee's Identified Deficiencies RII, PSS
- 3. Evaluate " Employee Concerns" Regarding RII, PSS Security
- 4. Evaluate Impact of NUREG-1154 RII, PSS
- 5. Inspect Training Plan for Security Force RII, PSS
- 6. Review Licensee's use of Compensatory RII, PSS Measure
- 7. Analyze Licensee's Corporate Audits RII, PSS
- 8. Inspection Report /SE input RII I
l l
l l
l._
IV. RESTART INSPECTION IV.
G.
POST ACCIDENT SAMPLING SYSTEM (PASS)
Lead: Monroe MAJOR TASK RESPONSIBILITY DATE
- 2. Conduct training of operators on.
TVA present system
- 3. Inspection of training RII
- 4. Inspection report RII
- 5. Conduct test of system when at power TVA 1
J I f
.--. ~
IV., RESTART INSPECTION IV.
H.
MSIV LEAKAGE REDUCTION PROGRAM Lead: Jape MAJOR TASK RESPONSIBILITY DATE
- 3. Conduct inspection to determine adequacy RII of repairs (LLRT's) prior to startup of each unit
- 4. Prepare SE RII
,=.
V.
LICENSING REVIEW V.
A.
INTEGRATED SCHEDULE FOR P_LANT MODIFICATIONS Lead: Muller MAJOR TASK RESPONSIBILITY DATE
- 1. Discuss plans for Integrated Schedule in TVA Complete Nuclear Performance Plan - Volume 3 (8-29-86)
- 2. Meet to discuss process guidelines, TVA/NRR/IE 3/87 criteria, etc. for scheduling and integrating
~
work on Units 1 and 3 after restart of Unit 2 and for completing future (after cycle 5) work on Unit 2
- 3. Develop schedule for restart of Units 1 and 3 TVA l
~
9 I t
i
- - V.'i.ICENSINGREVIEW V.
B.
UNIT 2 RELOAD MODIFICATION AMEf4DMENT MAJOR TASK RESPONSIBILITY DATE
- 1. Issue amendment (8-19-86)
NRR Complete 4
I 4 :
'l n
+-.
,,m
- ,~V.
LICENSING REVIEW V.
C.
APPENDIX J EXEMPTION Lead: Liaw MAJOR TASK RESPONSIBILITY DATE
- 1. Submittal of Exemption Request (11-20-85)
TVA Complete
- 2. Request for additional information (8-7-86')
NRR Complete
- 3. Respond to NRC request for additional information TVA
- 4. Prepare exemption or dental and Environmental NRR Assessment
$ l l
l i
~
~
V.
LICENSING REVIEW 5
V.
D.
ORGANIZATIONAL CHANGE AMENDMENT Lead: Vassallo MAJOR TASK RESPONSIBILITY DATE
- 1. Provide revised submittal TVA 10/86
- 2. Provide comments and/or questions NRR 10/86
- 5. Issue amendment NRR 11/86 3
! i
- - - =,.. - -
- ,V.
LICENSING REVIEW V.
E.
INDEPENDENT SAFETY ENGINEERING GROUP Lead: Muller MAJOR TASK RESPONSIBILITY DATE
- 1. Describe duties, responsibilities, and TVA Complete organizational status of the proposed ISEG, in Nuclear Performance Plan, Volume 3 (8-29-86)
- 3. Review the duties, responsibilities, and NRR organizational status of the proposed ISEG
- 4. Prepare SE i
i l
l l
! l
- V. ' LICENSING REVIEW V.
F.
CABLE ENVIRONMENTAL QUALIFICATION PROGRAM Lead: Srinivasan MAJOR TASK RESPONSIBILITY DATE
- 1. Submit NEDE 31302P-1 and request NRC TVA 09/02/86 approval of method of qualification
- 4. Issue SE
V.' ' LICENSING REVIEW 5
V.
ri.
INSERVICE PUMP AND VALVE TEST PROGRAM Lead: Liaw MAJOR TASK RESPONSIBILITY DATE
- 1. Submit pump and valve test program (10/85)
TVA Complete
- 2. Submit revision to above program TVA 10/86
- 3. Meet to review program TVA/NRR 10/86
- 6. Inspection of Program RII e i 1.
V.. LICENSING REVIEW V.
H.
TECHNICAL SPECIFICATION CLARIFICATION Lead: Muller MAJOR TASK RESPONSIBILITY DATE
- 1. Identify TS items that require changes TVA/RII 10/86 prior to restart of Unit 2
- 2. Submit TS change requests TVA 12/86 3.PrepareShollyNotice(s)
NRR 1/87
- 4. Prepare SE(s)
NRR 3/87
- 5. Issue amendment (s)
NRR 3/87 I
l l !
i f
e *,.,
1/. LICENSING REVIEW Lead: Hulman V.
I.
RADIOLOGICAL ENVIRONMENTAL TECHNICAL SPECIFICATIONS (RETS)
MAJOR TASK
~
RESPONSIBILITY DATE 1.
NRC meeting with TVA NRR/TVA Complete 2.
TVA response to meeting TVA 10/86 3.
Review response NRR 11/86 4.
Issue Amendment NRR 12/86
4' 1L
,b U
F a;
e4 *
~ Distribution for Meeting Sumary A
NRC PDR Local PDR PDf2 Reading fh14er RClark MGrotenhuis OGC - Bethesda EJordan
'BGrimes ACRS(10)
NRC Participa'nts HDeriton HThompson.
SRichards~on, IE JTaylor, IE BHayes, 01 NGrace, RIl LSpessard, DI SWeise, RII SRConnelly, DIA
- GZech, RII.
BJYoungblood JHolonich CStahle-TKenyon WLong TAlexion FCantrell, RII RWessman RBernero i
i I-i-