Discusses Arrangements Made for Disposal of Deformed Low Level Radwaste Liner from Facility
ML20206J987
Person / Time
Site: Millstone 
Issue date: 11/22/1988
From: Boyle M
Office of Nuclear Reactor Regulation
To: Mroczka E
NORTHEAST NUCLEAR ENERGY CO.
References
NUDOCS 8811290215
Download: ML20206J987 (3)


Text

_ __ -

November 22, 1988 De'cket No.:

50-245 DISTRIBUTION

,g N eh E. Jordan NRC & Local PDRs B. Grimes Mr. Edward J. Mroczka Gray File ACRS(10)

Senior Vice President S. Varga P. Reed Nuclear Engineering and Operations B. Booer Northeast Nuclear Energy Company S. Norris P. O. Box 270 M. Boyle Hartford, Connecticut 06141-0270 OGC

Dear Mr. Mroczka:

SUBJECT:

SHIPMENT OF LOW-LEVEL WASTE LINER FROM MILLSTONE UNIT N0. 1, MILLSTONE NUCLEAR POWER STATION Mr. Phillip R. Reed of the NRC Office of Nuclear Regulatory Research and I have been in contact with your staff, through Ms. Deborah L. Hersey, concerning the disposal of a defonned low-level radwaste liner at Millstone Unit 1.

Mr. Reed proposed that Northeast Utilities ship the liner to Idaho National Engineering Laboratory instead of the low-level waste disposal site at Hanford, Washington so that the NRC could investigate the liner deformation mechanism as part of an ongoing research program on decontamination radwaste.

We have contacted our contractor at INEL and they will be expecting receipt of the liner in early December 1988. The exact date and shipping address at INEL should be finalized with either Mr. Chuck McIsaac (208-526-0581) or Mr. John Mordler (208-526-4185) of INEL.

It is our understanding that Northeast Utilities would pay for the liner shipping costs.

Additional information concerning the shipment of the liner is enclosed.

If you have any questions, please contact me at (301) 492-1308.

Sincerely, original signed by Michael L. Boyle, Project Manager froject Directcrate I-4 Division of Reactor Projects I/II Office of Nuclear Reactor Regulation MBoyle:cbg Ni:PDI-4 D:P6l*

L PD -4 JStol h SNo is 11 88 11/JI/88 11/0/88

\\

/O

$$k $0$ck bbbbh Q\\

P

~

- ~~, --

<~

~

...g-

-- -m. v.

(z

..~.v-

+

  • 2

\\;

Y Mr. Edward J. Mroczka Millstone Nuclear Power Station Northeast Nuclear Energy Company Unit No. I cc:

Gerald Garfield, Esquire R. M. Kacich, Mana er Pay, Berry and Howard Generation Facilit es Licensing Counselors at Law Northeast Utilities Service Cortpany City Place Post Office Box 270 Hartford, Connecticut 06103-3499 Hartford, Connecticut CE141-0270 W. D. Romberg, Vice President D. C. Nordquist Nuclear Operations Fanager of Quality Assurance Northeast Utilities Service Company Northeast Nuclear Energy Company Post Office Box 270 Post Office Box 270 Hartford, Connecticut 06141-027C Hartford, Connceticut 06141-0270 Kevin McCarthy, Director Regional Administrator Radiation Control Unit Region I Departrient of Environr, ental Protection LT. S. Nuclear Regulatory Comissicq State Office Building 475 Allendale Poad

'trtford, Connecticut Ofl06 King of Prussia, Pennsylvania 19406 Bradford S. Chase, Under Secretary First Selectmen Energy Division Town of Waterford Office cf Policy end Managerrent Hall of Records 80 Washington Street PO0 Boston Post Road Hartford, Connecticut CC1 'C h terfcrd, Connecticut 063:'

S. E. Scace, Station Superintendent W. J. Raymond, Resident Inspector Millstent Nuclear Power Statien Millstone Nuclear Power Statien Ncrtheast Nuclear Energy Coepany c/o U. S. Nuclear Regulatory Cen ission Post Office Box !?S Post Office Box Bil Waterford, Connecticut 06385 Niantic, Connecticut 06357 J. P. Stetz, Unit Superintendent Millstone Unit No. 1 Northeast Nuclear Energy Coepany Post Office Box 128 Waterford, Connecticut 06325 1

O O

l l

1 l

l l

l

3.*

r ENCIDSURE 1 INR]RM4 TION RBOUESTED BY NORTHEAST NUGEAR EMRGY CO, CON &RNIM) BUIEED LIMR FRCN MillSTIFE 1 NLUEAR POWER STATICN R)R SHIPMNT TO IDAHO NATI(NAL EN11MERING IABORATIRY

1. Liner

Description:

LN Technologies Liner No.6291-034, Model 182 Disposal Vol. 182 Cu.Ft.

MR3 Da t e : Feb 25, 1987 Cement solidification of I.INI Decon,tamination ion-exchange resin.

Solidification date: June 27, 1987

2. Idaho National Engineering Chuck McIsaac Laboratory (INEL) Contacts:

Te1: Comunercia1 (208) 526 0581 FTS 583 0581 John Mandler Te1: ConunerciaI (208) 526 4185 FTS 583 0581

3. Shipping Location:

Idaho National Engineering Laboratory F.O. Box 1625 Idaho Falls, Idaho 83415 Contact IEL personnel in Item 2 above to receive information on the exact location at INEL for hauling the shipping cask with liner.

4. Shipping Date:

Early December, 1988. Contact INEL for specific date and shipping details.

5. Costs:

Shipping costs will be paid by Northeast Nuclear Energy Co.