ML20206G398

From kanterella
Jump to navigation Jump to search
Staff Requirements Memo Re 860612 Briefing in Washington,Dc Re Restart of Facility Following 851121 Water Hammer Event. EDO Concurs W/Restart
ML20206G398
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 06/19/1986
From: Chilk S
NRC OFFICE OF THE SECRETARY (SECY)
To: Stello V
NRC OFFICE OF THE EXECUTIVE DIRECTOR FOR OPERATIONS (EDO)
References
REF-10CFR9.7 M860612, NUDOCS 8606250241
Download: ML20206G398 (2)


Text

.

IN RESPONSE, PLEASE o UNITED STATES

[ ,., NUCLEAR REGULATORY COMMISSION (1 6 g, .g WASHINGTON. D.C. 20555 June 19, 1986

  • % . . . + #

OFFICE OF THE SECRETARY MEMORANDUM FOR: Victor Stello, Jr.

Executive Director for Operations 55' FROM: [( [ Samuel Chilk, J. Secretary

SUBJECT:

STAFF REQUIREMENTS - BRIEFING ON RESTART OF SAN ONOFRE-1, 2:00 P.M., THURSDAY, JUNE 12, 1986, COMMISSIONERS' CONFERENCE ROOM, D.C.

OFFICE (OPEN TO PUBLIC ATTENDANCE)

The Commission was briefed by the licensee and the staff on the status of San Onofre Unit 1 for return to power following the water hammer' event of November 21, 1985, which occurred in the feedwater system.

Presentations for the licensee were made by:

D. Fogerty Executive Vice President Southern California Edison K. Baskin Vice President for Nuclear Engineering, Safety & Licensing Southern California Edison M. Medford Manager of Nuclear Safety Southern California Edison J. Rainsberry Licensing Superintendent San Diego Gas and Electric Presentations for the staff were made by:

Victor Stello, Jr.

John Martin Ellis Merschoff Richard Dudley James Milhoan 1

8606250241 960619 PDR 10CFR PT9.7 PDR I

The Commission discussed whether a need existed for voting on the San Onofre-1 restart. Subsequent to the meeting, the Commission has concluded that it need not vote on the restart of San Onofre-1. The EDO, however, is to inform the Commission when he is ready to permit San Onofre-1 to return to power.

(EDO) (SECY Suspense: when ready) cc: Chairman Palladino Commissioner Roberts Commissioner Asselstine Commissioner Bernthal Commissioner Zech Commission Staff Offices PDR - Advance DCS - 016 Phillips