Staff Requirements Memo Re 860612 Briefing in Washington,Dc Re Restart of Facility Following 851121 Water Hammer Event. EDO Concurs W/Restart
ML20206G398
Person / Time
Site: San Onofre 
Issue date: 06/19/1986
From: Chilk S
NRC OFFICE OF THE SECRETARY (SECY)
To: Stello V
NRC OFFICE OF THE EXECUTIVE DIRECTOR FOR OPERATIONS (EDO)
References
REF-10CFR9.7 M860612, NUDOCS 8606250241
Download: ML20206G398 (2)


Text

.

IN RESPONSE, PLEASE o

UNITED STATES

[

NUCLEAR REGULATORY COMMISSION (1 6 g,

.g WASHINGTON. D.C. 20555

  • %... + #

June 19, 1986 OFFICE OF THE SECRETARY MEMORANDUM FOR:

Victor Stello, Jr.

Executive Director for Operations 55'

[( [ Samuel J.

Chilk, Secretary FROM:

SUBJECT:

STAFF REQUIREMENTS - BRIEFING ON RESTART OF SAN ONOFRE-1, 2:00 P.M.,

THURSDAY, JUNE 12, 1986, COMMISSIONERS' CONFERENCE ROOM, D.C.

OFFICE (OPEN TO PUBLIC ATTENDANCE)

The Commission was briefed by the licensee and the staff on the status of San Onofre Unit 1 for return to power following the water hammer' event of November 21, 1985, which occurred in the feedwater system.

Presentations for the licensee were made by:

D.

Fogerty Executive Vice President Southern California Edison K. Baskin Vice President for Nuclear Engineering, Safety & Licensing Southern California Edison M. Medford Manager of Nuclear Safety Southern California Edison J. Rainsberry Licensing Superintendent San Diego Gas and Electric Presentations for the staff were made by:

Victor Stello, Jr.

John Martin Ellis Merschoff Richard Dudley James Milhoan 8606250241 960619 PDR 10CFR PT9.7 PDR I

, The Commission discussed whether a need existed for voting on the San Onofre-1 restart.

Subsequent to the meeting, the Commission has concluded that it need not vote on the restart of San Onofre-1.

The EDO, however, is to inform the Commission when he is ready to permit San Onofre-1 to return to power.

(EDO)

(SECY Suspense:

when ready) cc:

Chairman Palladino Commissioner Roberts Commissioner Asselstine Commissioner Bernthal Commissioner Zech Commission Staff Offices PDR - Advance DCS - 016 Phillips