ML20206D792
| ML20206D792 | |
| Person / Time | |
|---|---|
| Site: | FitzPatrick |
| Issue date: | 04/06/1987 |
| From: | Johnston W NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | Radford Converse POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK |
| References | |
| NUDOCS 8704130425 | |
| Download: ML20206D792 (2) | |
See also: IR 05000333/1987014
Text
{{#Wiki_filter:* e APR 0 61987 Docket No. 50-333 Power Authority of the State of New York James A. FitzPatrick Nuclear Power Plant ATTN: Mr. Radford J. Converse Resident Manager P. O. Box 41 Lycoming, New York 13093 Gentlemen: Subject: EQUIPMENT QUALIFICATION INSPECTION OF FITZPATRICK NUCLEAR POWER PLANT (INSPECTION NO. 050-333/87-14) This letter confirms the dates of April 27 - May 1,1987 for the NRC equipment qualification (EQ) inspection for FitzPatrick Nuclear Power Plant. These dates were established during a previous telephone conversation with Mr. Mogan Hansen on April 2, 1987 by Mr. Leonard Cheung of this office. The inspection will take place at the plant site. A management entrance meeting is scheduled for 1:00 p.m. on April 27, 1987 with a management exit meeting tentatively scheduled for 10:00 a.m. on May 1,1987 at the plant site. A plant walkdown inspection of specific EQ equipment is planned for Wednesday, April 29, 1987. The inspection will include the following: 1. Review of your implementation of a 10 CFR 50.49 program including preservation of the qualified status of qud ified equipment. 2. Review of your implementation of Technical Evaluation Report / Safety Evaluation Report EQ corrective action commitments. 3. Review of EQ documentation files.# 4. Physical inspection of selected plant equipment and selected field wiring. i , l Your cooperation with us during this inspection will be appreciated. Should you have any questions regarding this inspection, please contact either , ' Mr. Leondard Cheung (215-337-5296) or Mr. C. J. Anderson (215-337-5376) of this office. Sincerely, I 1 it7 OriC r01 UI# i - Ja:G ?* E bbOb333 am o nston, W ng W ector D DO [[ G PDR Division of Reactor Safety OFFICIAL RECORD COPY CHEUNG4/2/87 - 0001.0.0 8 D l 04/02/87 l l _
4 e PASNY 2 cc: L. W. Sinclair, President J.- P. Bayne, First Executive Vice President and Chief Operations Officer A. Klausmann, Vice President.- Quality Assurance an ' 'iability R. L. Patch, Quality Assurance Superintendent George M. Wilverding, Chairman, Safety Review Committs. Gerald C. Goldstein, Assistant General Counsel NRC Licensing Project Manager Dept. of Public Service, State of New York Public Document Room (PDR) Local Public Document Room (LPDR) Nuclear Safety Information Center (NSIC) NRC Resident Inspector State of New York bec: Region I Docket Room (with concurrences) Management Assistant, DRMA (w/o enc 1) Section Chief, DRP Robert J. Bores, DRSS cc RI:DRS M RI: S RI:DRS Cheung/cgl Anderson Durrf- ! ypf&7 y/>/i1 VA,r/11 0FFICIAL RECORD COPY CHEUNG4/2/87 - 0002.0.0 04/02/87
.. , . . - . - - - - , . .. , - . . . }}