ML20206D147

From kanterella
Jump to navigation Jump to search
Insp Repts 50-424/87-19 & 50-425/87-19 on 870223-27. Violations Noted:Failure to Implement Fire Protection Procedures
ML20206D147
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 03/27/1987
From: Conlon T, Wiseman G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20206D057 List:
References
50-424-87-19, 50-425-87-19, NUDOCS 8704130257
Download: ML20206D147 (7)


See also: IR 05000424/1987019

Text

.

.

S

[>SK8GO

UNITED STATES

'o

NUCLEAR REGULATORY COMMISSION

[ -

REGION 11

3

g

.-j

101 MARIETTA STREET, N.W.

  • '

C

AT1.ANTA, GEORGI A 30323

\\...+/

+

Report Nos.:

50-424/87-19 and 50-425/87-19

Licensee: Georgia Power Company

P. O. Box 4545

. Atlanta, GA 30302

Docket Nos.: 50-424 and 50-425

License Nos.: 'NPF-61 and CPPR-109

.

Facility Name: Vogtle 1 and 2

Inspection Conduct d:

February 23, 7, 1987

3- N'S 7

Inspector:

b

t/[

d,-

G. R. Wiseman

~U

'

Date Signed

hf?( 109f/

3 43-?[

Approved by:

,

T. E. Conlon, Section Chief

1

Date Signed

Plant Systems Section, Engineering Branch

Division of Reactor Safety

SUMMARY

Scope: This routine, unannounced inspection was conducted:in the areas of Fire

Protection / Prevention and followup on Previously Identified Inspection Items.

Results: One violation was ident1fied - Failure to Implement Fire Protection

Procedures

paragraph 5.c.

4

87041302S7 870327

PDR

ADOCK 05000424

G

PDR

.

-

- - -

.-

_

_

.

'

REPORT DETAILS

1.

Persons Contacted

Licensee Employees

  • C. E. Belflower, QA Site Manager
  • R. M. Bellamy, Plant Support Manager
  • D. M. Fiquett, Field Construction Manager Unit 2
  • W. C. Gabbard, Senior Regulatory Specialist
  • T. Greene, Plant Manager
  • R. Sprankle, Senior Engineer, Fire Protection
  • H. Varnadoe, Plant Engineering Supervisor

Other licensee employees contacted included construction craftsmen,

engineers, technicians, operators, mechanics, security force members, and

office personnel.

Other Organizations

  • G. H. Jones, Utility Support Corporation

G. VanGemer, General Physics Corporation

NRC Resident Inspectors

  • J.

Rogge

  • Attended exit interview

2.

Exit Interview

The inspection scope and findings were summarized on February 27, 1987,

with those persons indicated in paragraph 1 above.

The inspector

described the areas - inspected and discussed in detail the inspection

i

findings.

No dissenting comments were received from the licensee. The

following items were identified during this inspection.

a.

Inspector Followup Item (424/87-19-01) - Incorporate Inspection and

"

Testing of Fire Hose Station Pressure Reducing Valves Into the Fire

'

Protection Surveillance Program, paragraph 5.b.

b.

Inspector Followup Item (424/87-19-02) - Incorporate Inspection of

Both Sides of Temporary Fire Barriers between Unit 1 and Unit 2 into

Procedure 92445-C, paragraph 5.b.

s

4

.-.

.

.

-

-

-

.

1

.

.

2

c.

Violation Item (424/87-19-03) - Failure to Implement Fire Protection

Procedures, paragraph 5.c.

d.

Inspector Followep Item (424/87-19-04) - Provide Identification and

Procedures for Use of the Emergency Fire Control Shutoff Valve for

the H Storage Tank, paragraph 6.

2

e.

Unresolved Item (425/87-19-01) - Identification of Combustible

Scaffolding Exposing the Temporary Fire Barrier Between Unit -1 and

Unit 2 Control Rooms, paragraph 6.

The licensee did not identify as proprietary any of the materials provided to

or reviewed by the inspector during this inspection.

3.

Licensee Action on Previous Enforcement Matters

This subject was not addressed in the inspection.

4.

Unresolved Items

Unresolved items are matters about which more information is required to

determine whether they are acceptable or may - involve violations or-

deviations.

New unresolved items identified during this inspection are

discussed in paragraph 6.

5.

Fire Protection / Prevention Program (64704)

a.

Fire Prevention / Administrative Control Procedures

The inspector reviewed the following Fire Prevention / Administrative

Procedures:

Procedure No.

Title

92005-C, (Rev. 2)

Fire Response Procedure

92015-C, (Rev.1)

Control of Transcient Combustibles

92020-C, (Rev. 1)

Control of Ignition Sources

92028-C, (Rev. 1)

Control of Fire Area Boundaries

92035-C, (Rev. 0)

Fire Protection Operability Requirements

Based on this review, it appears that the above procedures meet the

NRC guideline of: NUREG-0800, Section 9.5.1, " Standard Review Plan -

Fire Protection Program; and the licensee's commitments in Section 9B

of the Vogtle FSAR.

-

-

- -

-

-

-

.

- -

-0

'

.

3

b.

Fire Protection Surveillance Procedures

The inspector reviewed the following Fire Protection System Surveil-

lance Procedures:

Procedure No.

Title

92010-C (Rev. 1)

Weekly Fire Inspection

92025-C (Rev. 2)

Fire Protection Surveillance Program

92400-C (Rev. 4)

Portable Fire Extinguishers and Fire

Hose Stations Monthly Visual Inspection

92401-C (Rev. 0)

Monthly Emergency Lighting Surveillance

Test Procedure

92403-C (Rev. 3)

Hydrant Hose House Monthly Visual

Inspection

92413-C (Rev. 2)

Fire Pump Starting Batteries Quarterly

Inspection

92424-C (Rev. 1)

Fire Door Inspection

92445-C (Rev. 0)

Fire

Barrier

and

Fire

Barrier

Penetration Seals - 18 Month Visual

Inspection

The above surveillance procedures were reviewed to determine if the

various test outlines and inspection instructions adequately

implement the surveillance requirements of the plant's Fire

Protection Operability Requirements.

In addition, these procedures

were reviewed to determine if the inspection and test instructions

followed general industry fire protection practices, NRC fire

protection program guidelines and the guidelines of the National Fire

Protection Association (NFPA) Fire Codes. Based on this review, it

appears that the above procedures are satisfactory, except for

procedures 92400-C and 92445.

Procedure 92400-C provides for monthly visual inspections of the

plant's fire hose stations. During the preoperational testing of the

firehouse stations, tre pressure reducing valves at the stations were

tested and set to maintair. the hose pressure to 100 psig or less.

After the valves were set, a tamper seal was installed on the

adjusting mechanism to deter inadvertent misadjustment. The monthly

visual inspection procedure 92400-C; however, does not provide for a

visual inspection of these tamper seals to verify the seal integrity.

This

is identified as Inspector Followup Item 424/87-19-01,

Incorporate Inspection and Testing of Fire Hose Station Pressure

Reducing Valves into the Fire Protection Surveillance Program, and

will be reviewed during a subsequent NRC inspection.

.

.

4

Procedure 92445-C describes criteria for inspection of plant fire

barriers on an- 18 month basis. This procedure includes inspection

of the temporary plaster. and gypsum wa11 board fire barriers which

provide fire separation between Unit 1 and the construction

activities of Unit 2.

The surveillance procedure 92445-C does not

provide periodic inspection for the fire barrier on the Unit 2

construction side of the separation wall.

In addition, it was a

concern of the inspector that the frequency of inspection of the

construction side of the barrier should be increased due to the ever

changing activities of the construction phase of Unit 2 which may

increase the probability of physical damage to the barrier. These

concerns are identified as Inspector Followup Item (424/87-19-02),

Incorporate Inspections of Both Sides of Temporary Fire Barriers

between Unit 1 and Unit 2 into Procedure 92445-c.

This will be

reviewed during a future NRC inspection.

c.

Fire Protection System Surveillance Inspections and Tests

The inspector reviewed the following surveillance inspection and test

records for the dates indicated:

(1) 92010-C,

Housekeeping Inspection (Weekly)

January 17, 1987 through February 20, 1987

(2) 92401-C,

Emergency Lighting Surveillance Test Procedure, Data

Sheet 3, (Monthly)

December 15, 1986 through February 16, 1987

(3) 92413-C,

Fire Pump Starting Batteries Inspection (Quarterly)

September 8, 1986, November 19, 1986 and February 19, 1987

(4) 92424-C,

Fire Doors, Fire Door Mechanisms (6 Months)

August 24, 1980 and February 20, 1987

The surveillance test record data and testing frequency associated

with the above fire protection system surveillance test / inspections

were found to be satisfactory with regard to meeting the requirements-

of the plant's Fire Protection Final Safety Evaluation Report, except

that it wcs noted in the review of the inspection record for

Procedure 92010-C that after the January 24, 1987 licensee weekly

housekeeping inspection six failure to correct discrepancy reports,

which identified and described plant housekeeping discrepancies that

had been observed over a 3 week period were transmitted to plant

management for their disposition to take corrective actions. Based

upon these reports, the identified discrepancies were to be corrected

within a time requirement of one week as established in procedure

92010-C Sections 5.3.4 and 5.3.5.

.

.

,

5-

On February 26, 1987, the inspector accompanied a member of the plant

fire protection staff during the conduct of the weekly housekeeping

inspection per the criteria of procedure 92010-C.

During this

walkthrough the inspector observed combustible cardboard, wood and

plastics material located within safety related plant areas. Also,

identified was the storage of flammable / explosive gas cylinders in

the power block and improperly supported and secured high pressure

compressed gas cylinders in safety related areas of the Auxiliary,

Fuel Handling, and Control Buildings.

These conditions were verified as being those which were identified

from the licensee's previous discrepancy reports to plant management.

Failure to correct the above mentioned housekeeping discrepancies is

considered a failure to implement procedure 92010-C. This constitutes

a violation of Technical Specification 6.7.1.h which requires that

written procedures for the fire protection program for the fire

protection program be implemented and -is identified as Violation

(424/87-19-03), Failure to Implement Fire Protection Procedures.

Also, during the February 26, 1987, plant walkthrough, the inspector

observed evidence that cigarette smoking had recently occurred in

posted "No Smoking" safe-shutdown plant areas within the power block.

This is considered a failure to implement Procedure 00253, Smoking,

Eating, and Drinking Policy and is identified as another example

l

of Violation 424/87-19-03 Failure to Implement Fire Protection

Procedures.

6.

Permanent Plant Fire Protection Features (64704)

i

Several plant tours were made by the inspector. During the plant tours,

the following plant areas and their related fire protection features were

inspected:

Auxiliary Building Unit 1 - Levels D. C. and A

)

Control Building Unit 1 - Levels 1, 2, and 3

Control Building Unit 2 - Levels 1, 2, and 3

Hydrogen Storage Tank - Yard

The fire / smoke detection systems, manual fire fighting equipment (i.e. ,

portable extinguishers, hose stations, etc.) and the fire area boundary .

l

doors, walls, floors, and ceilings were inspected. A number _of fire doors

i

in Unit I have been identified as nonfunctional due to the doors not

l

!

meeting their design and installation criteria. Work is in process to

l

correct the identified deficiencies.

The fire watch compensatory

'

measures of the FSAR had been implemented for those plant areas that

contain fire doors which were deficient or out of service.

.

6

A walkdown of the liquid hydrogen storage tank unit located outside

the auxiliary building in the yard area indicated that the system was

operational; however, the Emergency Fire Control Shutoff Valve located

.

approximately 25 feet from the storage unit was not prominately identified

so that it could be used to isolate the H

supply in a fire emergency

2

situation as described in the National Fire Protection Association (NFPA)

Standards 50A and 54. Operational instructions for this valve should be

provided on the plant prefire plans.

This is identified as Inspector

Followup item (424/87-19-04), Provide Identification and Procedures for

Use of the Emergency Fire Control Shutoff Valves for the H2 Storage Tank.

This will be reviewed during a subsequent NRC inspection.

4

During the walkthrough of Unit 2 which was under construction it was noted

that a significant amount of combustible wood scaffolding was erected in

the Unit 2 control room very near the temporary 3 hour3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> rated gypsum wall

board fire barrier which separates this area from the Unit 1 control room.

Some Unit 1 Control Room ceiling assembly steel support beams penetrate

the temporary fire barrier into the Unit 2 area and are not provided with

fire proofing. The inspector was concerned that the significant fire load

comprised of wood scaffolding may provide a significant fire exposure to

the fire barrier and support steel for the Unit 1 Control Room. The

licensee's fire hazards analysis did not identify this type of fire

loading hazard for the control room.

This is identified as Unresolved

Item (425/87-19-01),

Identification of Combustible Scaffolding Exposing

the Temporary Fire Barrier Between Unit 1 and Unit 2 Control Rooms,

pending the licensee's review of the situation.

7.

Inspector Followup Item (IFI)

A.

(Closed) (425/86-07-03), Engineering Analysis, Testing and Justifica-

tion for Non-Standard Penetration Seal Configurations. The licensee

provided additional information to the NRC/NRR staff by letter, dated

October 24, 1986, and during a meeting on November 4,1986. This

information included a test report on a penetration fire barrier seal

of similar design to the oversized penetrations at plant Vogtle.

NRC's Supplemental Safety Evaluation Report (SSER) No. 4, Appendix Q

stated that the oversized penetrations seals at Vogtle had been

reviewed and were acceptable. This item is closed.

!

- -

-

-

-

-

-

- -

-

-

- -

-

-

-

-

.

- -

- -

-

-