Informs That Review of Dockets Re Schedule for Implementation of 10CFR50.48 Complete.Based on Review,Fire Protection & Alternate or Dedicated Shutdown Sys Mods,Per 10CFR50.48,scheduled to Be Completed by Sept 1988
ML20206B290
Person / Time
Site: Fort Saint Vrain Xcel Energy icon.png
Issue date: 04/06/1987
From: Miraglia F
Office of Nuclear Reactor Regulation
To: Robert Williams
PUBLIC SERVICE CO. OF COLORADO
References
GL-86-10, NUDOCS 8704090060
Download: ML20206B290 (3)


Text

.

Docket No. 50-267 APR 0 61987 Mr. R. O. Williams, Jr.

Vice President, Nuclear Operaticns Public Service Company of Colorado P. O. Box 840 Denver, Colorado 80201-0840

Dear Mr. Williams:

SUBJECT:

IMPLEMENTATION SCHEDULE FOR 10 CFR 50.48 FIRE PROTECTION MODIFICATIONS - FORT ST. VRAIN NUCLEAR GENERATING STATION Generic Letter 86-10. " Implementation of Fire Protection Requirements" stated that the NRC would (1) review the dockets of plants covered by 50.48 to determine the schedule deadlines for those plants and (2) inform licensees of those schedule deadlines.

Ve have reviewed the docket related to the schedule for implementation of 10 CFR 50.48 for fort St. Vrain. Based on that review, we have determined that the fire protection and alternate or dedicated shutdown system modifications required to meet 10 CFR 50.48 are scheduled by Public Service Company of Colorado to be completed by startu) from the fourth refueling outage (estinated to be September 19E8). Alt 1ough the modifications were not completed consistent with the schedule requirements of 10 CFR 50.48, the plant has been allowed to operate because of your compensatory measures which have been approved by the NRC.

By our letter dated January 23, 1987, you were advised that we would consider your dates for completion of these items as schedule comitments.

If this schedule is not correct, please contact the NRC Project Manager in writing within 30 days.

In addition, please notify the NRC Project Manager in writing if schedule delays develop and notify the NRC after you have completed the 50.48 modifications.

Sincerely, Original signed by, FmA J. Miraglia ank J. W aglia, W ec W n704090060 070406 PDR ADOCK 05000267 Division of PWR Licensing-B F

PDR Office of Nuclear Reactor Regulation cc: See next page DISTRIBUT"0N:

Docket Fi e /

IViraglia JPartlow KHeitner DKubicki NRC PDR OGC-BETH llThompson Olynch Local POR EJordan ACRS(10)

Huerkow PBSS Reading BGrimes PNoonan T00rian Ch.

PBS5ih OGC ETHg')

PPE PBSS ynch HBe w

.Ti W

FMio a

kHeitner:cw(f%4/t/87 p an 04/*/87 04/J/07 04/&

7 04/),/87 04/"L/87

P

/

o UNITED STATES g

['

p, NUCLEAR REGULATORY COMMISSION rn j

WASHINGTON, D. C. 20555

%,...../

APR 0 61987 Docket No. 50-267 Mr. R. O. Williams, Jr.

Vice President Nuclear Operations Public Service Company l

of Colorado l

P. O. Box 840 j

Denver, Colorado 80201-0840

Dear Mr. Williams:

l

SUBJECT:

IMPLEMENTATION SCHEDULE FOR 10 CFR 50.48 FIRE PROTECTION PODIFICATIONS - FORT ST. VRAIN NUCLEAR GENERATING STATION I

l l

Generic Letter 86-10. " Implementation of Fire Protection Requirements" stated i

that the NRC would (1) review the dockets of plants covered by 50.48 to determine the schedule deadlines for those plants and (2) inform licensees of those schedule deadlines.

l We have reviewed the docket related to the schedule for implementation of i

10 CFR 50.48 for Fort St. Vrain. Based on that review, we have detemined that the fire protection and alternate or dedicated shutdown system modifications required to meet 10 CFR 50.48 are scheduled by Public Service Company (of Colorado to be completed by)startus from the fourth refueling t

outage estimated to be September 1988. Altiough the modifications were not completed consistent with the schedule requirements of 10 CFR 50.48, the plant has been allowed to operate because of your compensatory measures which have been approved by the NRC.

l By our letter dated January 23, 1987, you were advised that we would consider your dates for completion of these items as schedule commitments.

If this schedule is not correct, please contact the NRC Project Manager in writing I

within 30 days.

In addition, please notify the NRC Project Manager in writing I

if schedule delays develop and notify the NRC after you have completed the 50.48 modifications.

Sincerely, M

P.,

FrankJ.41raglia,Nrector Division of PWR Licensing B Office of Nuclear Reactor Regulation cc: See next page

y 1

l j

l

!?

Mr. R. O. Williams Public Service Company of Colorado Fort St. Vrain cc:

Mr. D. W. Warembourg, Manager Albert J. Fazle, Director i

Nuclear Engineering Divisien Radiation Control Division l

Public Service Company Department of Health 1

of Colorado 4210 East lith Avenue i

P. O. Box 840 Denver, Colorado 80220 Denver, Colorado 80201 j

Mr. David Alberstein, 14/159A Mr. R. O. Williams, Acting Manager GA Technologies, Inc.

Nuclear Production Division l

Post Office Box 85608 Pub 1fc Service Company of Colorado.

San Diego, California 92138 16805 Weld County Road 19-1/?

i Platteville, Colorado 80651 Mr. H. L. Brey, Manager Nuclear Licensing and Fuel Division Mr. P. F. Tomlinson, Manager Public Service Company of Colorado Ouality Assurance Division P. O. Box 840 Public Service Company of Colorado Denver, Colorado 80201 16805 Weld County Road 19-1/2 i

Platteville, Colorado 80651 i

Senior Resident Inspector l

U.S. Nuclear Regulatory Commission Mr. R. F. Walker P. 0. Box 840 Public Service Company of Colorado Platteville Colorado 80651 Post Office Box 840 i

Denver, Colorado 80201-0840 1

Kelley, Stansfield A 0'Donnell i

"i Public Service Company Building Commitment Control Program l

Room 900 Coordinator

)

550 15th Street Public Service Company of Colorado l

Denver, Colorado 80202 2420 W. 26th Ave. Suite 100-0 i

Denver, Colorado 80211 l

}

Regional Administrator, Region IV t

i U.S. Nuclear Regulatory Connission j

611 Ryan Plaza Drive Suite 1000 l

Arlington, Texas 76011 i

Chainnan, Board of County Commissioners of Weld County, Colorado Greeley, Colorado 80631 i

t Regional Representative i

Fadiation Programs Environmental Protection Agency 1 Denver Place

)

999 18th Street, Suite 1300 Denver, Colorado 80202-2413 i

i i

.