PHILADELPHIA ELECTRIC COMPANY 2301 MARKET STREET P.O. BOX 8699 PHILADELPHIA. PA.19101 1215)841 4500 V. S. BO Y E R SR. VICE PRESIDENT NUCLE A R POWE R May 23, 1986 Docket Nos. 50-277 50-278 Mr. Robert M. Bernero Division of Boiling Water Reactor Licensing U.S. Nuclear Regulatory Commission Washington, DC 20555
Subject:
Peach Bottom Atomic Power Station Fire Protection Modification Progress Report
References:
(1) Letter, J. W. Gallagher to D. G.
Eisenhut, dated February 25, 1983 (2) Letter, Stewart D. Ebneter to S. L.
Daltroff, dated April 11,1986 (3) Meeting; G. Gears, J. Stang, NRC; G.
Morley, G. Reid, C. Gerdes, W. Birely,
PEC0; on May 6, 1986
Dear Mr. Bernero:
Philadelphia Electric Company, in the Reference (1) letter, proposed to submit a Peach Bottom Fire Protection Modification Progress Report to the NRC every four months starting in May, 1983.
We propose that this be the tenth and last Modifications Progress
. Report submitted in accordance with our discussion during the May 6, 1986, meeting (Reference 3).
Continuation of the tri-annual Modification Progress Report beyond this submittal would provide redundant information to that which will be provided in the September, 1986, FPER submittal and confirmatory letter commitment (Reference 2).
This commitment additionally includes reporting to Region I any design deviations found during implementation of this confirmatory program.
We have included in this report (Attachment I) only those modifications completed since the last report dated January 17, 1986.
The following items summarize the remaining ongoing work and the final penetration seal and damper totals:
8605280238 860523 PDR ADOCK 0500 7
g
'Io
. 1.
Alternative shutdown Modifications III. L.
Design and installation of the required emergency lighting and communications modifications for Unit No. 3 (Mod 13531) will be completed within the Unit 2 alternative shutdown schedule. All alternative shutdown design modifications for Unit 2 are in progress and the work is scheduled for completion during the Unit 2 refueling outage in 1987.
2.
Both the Penetration Seal Program III.M and HVAC Damper Program III.G.2 are completed, with a total of 6,285 penetrations sealed and 55 dampers added to HVAC ducts.
If you have any questions regarding this matter, please do not hesitate to contact us.
Very truly yours, V. S. Boyer GMM/j et/05158601 Attachment Copy to:
T. P. Johnson, Resident Site Inspector NRC Document Control Desk Stewart D. Ebneter, Director Division of Reactor Safety
ATTACFNENT I SAFE SHUTDOWN MODIFICATIONS Expected Itsn Mod Description Status Conpletion Dates Mod. No.
1.
Replace the 480V notor Design in End of first 2-1029J, control center progress outage connencing
- 1029K, magnetic-only circuit after waterial 3-1029L breakers with thennal availability.
magnetic circuit breakers.
2.
Replace the existing ground Design carplete.
2-First Equipnent 1029N overcurrent relays for the Relays delivered.
Outage; Scheduled following 4kV circuit for 1986.
breakers: Unit 2: 152-1606 and 152-1704.
3.
Install 3-hour rated fire Conplete Conpleted 1309 danpers in HVAC ducts penetrating fire barriers.
4.
Reroute SRV/ ADS cables to Unit 2-design in 2-E00 (87) 1029B facilitate safe shutdown progress.
3-Completed (linked to 1352G (U2) &
13543G (U3)).
5.
Provide centrol roon Unit 2 - design in 2-E00 (87) 1029E Indication for 6 process progress.
3-Completed variables and 4 systen diagnostics for each Fire Area.
ALTERNATIVE SHUTDOWN MODIFICATIONS 6.
Provide a linear heat Design corplete.
6/30/86 1351B detection systen in the Installation in cable trays in fire area progress.
25.
7.
Provide a new panel to Conplete 3-Completed 1353A establish an alternative control station for the Unit 3 HPCI systan. The new panel will also house
. equipment for nods 1353B, 1353C, 1353D, 1353G, and 1353H.
- Item Mod Description Status Cmpletion Dates Mod. No.
8.
Establish alternative Complete.
3-Completed 1353A controls and indication for the Unit 3 HPCI systen at the panel Identified above.
9.
Provide alternative Complete 3-Completed 1353B diagnostic Instrunentation for Unit 3 alternative shutdown systems at the Unit 3 HPCI ACS.
10.
Establish necessary control Conplete 3-Completed 1353C Indication for the Unit 3D RHR valves at the Unit 3 HPCI ACS panel provided by Mod 1353A.
11.
Establish necessary controls Complete 3-Conpleted 1353D indication for the Unit 3D HPSW Valves at the Unit 3 HPCI ACS panel provided by 1353A 12.
Establish Unit 3 alternative Conplete 3-Completed 1353H process nonitoring instrunentation at the Unit 3 HPCI ACS.
GMM/ dun /05128603