Ack Receipt of Which Appealed NRC Staff Determination That Util Had Not Raised Valid Backfit Claim in to Nrc.Staff Began Process of Convening Backfit Review Panel to Evaluate Appeal
ML20205N621
Person / Time
Site: Maine Yankee
Issue date: 04/07/1999
From: Zwolinski J
NRC (Affiliation Not Assigned)
To: Meisner M
Maine Yankee
References
NUDOCS 9904190048
Download: ML20205N621 (4)


Text

April 7, 1999 Mr. Michael J. Meisner, President Maine Yankee Atomic Power Company 321 Old Ferry Road Wiscassett, Maine 04578-4922

SUBJECT:

APPEAL OF NRC DETERMINATION CONCERNING MAINE YANKEE ATOMIC POWER COMPANY CLAIM OF BACKFIT REGARDING PERMANENTLY SHUTDOWN REACTOR SECURITY PLAN

Dear Mr. Meisnes:

By letter dated March 16,1999, Maine Yankee Atomic Power Company (MYAPC) appealed a U.S. Nuclear Regulatory Comtr'?sion (NRC) staff determination that MYAPC had not raised a valid backfd claim in a July 16, W98, letter to the NRC. In accordance with Office of Nuclear Reactor Regulation (NRR) Office Letter 901, " Procedures for Managing Plant-Specific Backfits and 10 CFR 50.54(f) Information Requests," this letter acknowledges your backfit appeal. The staff has begun the process of convening a backfit review panel to evaluate your appeal.

In your letter you stated that, normally, if MYAPC were to appeal an NRC staff position, you would provide some discussion conceming the differing opinions, but that in this case, you believe the staff misunderstood what your backfit claim sought. Therefore, you reiterated a previous request that the NRC staff meet with you to clarify these misunderstandings. Based on your letter and a phone conversation with George Zinke of your staff, we believe that i

resolution of the issues at this meeting could obviate the need for the backfit appeal process.

Accordingly, we would like to schedule a_ meeting with you later this month and defer appointing a backfit review panel until after that meeting. If you believe that we should not wait and desire that we go forward with appointing the backfit review panel, please contact your Project Manager, Michael Webb at (301) 415-1347.

If you have any questions or concerns regarding this matter, please do not hesitate to contact me at (301) 415-1453.

Sincerely, original signed by Suzanne Black for:

John A. Zwolinski, Director Division of Licensing Project Manage.nent Office of Nuclear Reactor Regu1ation Docket No. 50-309

_ DISTRIBUTION:

Docket File ; 9 OGC

[

cc: See next page PUBLIC ACRS

)

PDIV&D r/f EPeyton O

WTravers, EDO CHehl, Region i RZimmerman MWebb pid 160040 JZwoiinski/SBiack

^

SRichards MMasnik DOCUMENT NAME: A:\\MYAPPLTR.WPD To RECElvE A COPY oF THis DOCUMENT, INDICATE IN THE box: "C" = COPY WITHoUT ENCLOSURES "E" = COPY WITH ENCLOSURES "N" OFFICE PM:PDIV&D LA:PDIV-2 SC:PDIV&D D:PDIV&D C-D:DLP3 o

NAME MWebb:sp '

EPey N MMasnik P{ N SRichards 6fW JZwolinNi DATE 4/'4

/99 4/' 6 /99 4/

$ /99 4/ [o

/99 4/ */

/99 OFFICIAL RECORD COPY

(

9904190048 990407$

l,

April 7g 1999 Mr. Michael J. Meisner, Presideni Maine Yankee Atomic Power Company 321 Old Ferry Road Wiscassett, Maine 04578-4922

SUBJECT:

APPEAL OF NRC DETERMINATION CONCERNING MAINE YANKEE ATOMIC POWER COMPANY CLAIM OF BACKFIT REGARDING PERMANENTLY SHUTDOWN REACTOR SECURITY PLAN

Dear Mr. Meisner:

By letter dated March 16,1999, Maine Yankee Atomic Power Company (MYAPC) appealed a U.S. Nuclear Regulatory Commission (NRC) staff determination that MYAPC had not raised a valid backfit claim in a July 16,1998, letter to the NRC. In accordance with Office of Nuclear Reactor Regulation (NRR) Office Letter 901, " Procedures for Managing Plant-Specific Backfits and 10 CFR 50.54(f) Information Requests," this letter acknowledges your backfit appeal. The staff has begun the process of convening a backfit review panel to evaluate your appeal.

In your letter you stated that, normally, if MYAPC were to appeal an NRC staff position, you would provide some discussion concerning the differing opinions, but that in this case, you believe the staff misunderstood what your backfit claim sought. Therefore, you reiterated a previous request inat the NRC staff meet with you to clarify these misunderstandings. Based on your letter and a phone conversation with George Zinke of your staff, we believe that resolution of the issues at this meeting could obviate the need for the backfit appeal process.

Accordingly, we would like to schedule a meeting with you later this month and defer appointing a backfit review panei until after that meeting. If you believe that we should not wait and desire that we go forward with appointing the backfit review panel, please contact your Project Manager, Michael Webb at (301) 415-1347.

If you have any questions or concerns regstding this matter, please do not hesitate to contact me at (301) 415-1453.

Sincerely, Original signed by Suzanne Black for:

John A. Zwolinski, Director Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-309 DISTRIBUTION:

Docket File OGC cc: See next page PUBLIC ACRS PDIV&D r/f EPeyton WTravers, EDO CHehl, Region I RZimmerman MWebb JZwolinski/SBlack SRichards MMasnik DOCUMENT NAME: A:\\MYAPPLTR.WPD To RECEfVE A COPY OF THis DOCUMENT,INolCATE IN THE box:"C" = COPY WITHoUT ENCLOSURES "E" = COPY WITH ENCLOSURES *N" OFFICE PM:PDIV&D LA:PDIV-2 SC:PDIV&D D:PDIV&D L

D:DLPM, p{ Yl SRichards GF JZwoinlsk'i NAME MWebb:sp

EPe M P MMasnik DATE 4/ k

/99 4/ 5 /99 4/

$ /99 4/ 5

/99 4/

7

/99 OFFICIAL RECORD COPY I

s p***c%

l y"

t UNITED STATES e

l j

j NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001

,o l

April 7, 1999 Mr. Michael J. Meisner, President Maine Yankee Atomic Power Company 321 Old Ferry Road Wiscassett, Maine 04578-4922

SUBJECT:

APPEAL OF NRC DETERMINATION CONCERNING MAINE YANKEE ATOMIC POWER COMPANY CLAIM OF BACKFIT REGARDING PERMANENTLY SHUTDOWN REACTOR SECURITY PLAN

Dear Mr. Meisner:

By letter dated March 16,1999, Maine Yankee Atomic Power Company (MYAPC) appealed a U.S. Nuclear Regulatory Commission (NRC) staff determination that MYAPC had not raised a valid backfit claim in a July 16,1998, letter to the NRC. In accordance with Office of Nuclear Reactor Regulation (NRR) Office Letter 901, " Procedures for Managing Plant-Specific Backfits and 10 CFR 50.54(f) Information Requests," this letter acknowledges your backfit appeal. The staff has begun the process of convening a backfit review panel to evaluate your appeal.

In your letter you stated that, normally, if MYAPC were to appeal an NRC staff position, you would provide some discussion concerning the differing opinions, but that in this case, you believe the staff misunderstood what your backfit claim sought. Therefore, you reiterated a previous request that the NRC staff meet with you to clarify these misunderstandings. Based on your letter and a phone conversation with George Zinke of your staff, we believe that resolution of the issues at this meet;ng could obviate the need for the backfit appeal process.

Accord ngly, we would like to schedule a meeting with you later this month and defer appointing a backfit review panel until after that meeting. If you believe that we should not wait and desire that we go forward with appointing the backfit review panel, please contact your Project Manager, Michael Webb at (301) 415-1347.

If you have any questions or concerns regarding this matter, please do not hesitate to contact me at (301) 415-1453.

Sincerely,

( -

41( Id C- (4 C

/

John A. Zwolinski, Director Division of Licensing Project Management i

Office of Nuclear Reactor Regulation Docket No. 50-309 cc: See next page

)

1 J

I O

o I

Maina Yankee Atomic Power Company Docket No. 50-309 cc:

Mr. Charles B. Brinkman Friends of the Coast Manager - Washington Nuctuar P.O. Box 98 Operations Edgecomb, ME 04556 ABB Combustion Engineering 12300 Twinbrook Parkway %te 330 Mr. William O' Dell Rockville, MD 20852 Operations Director Maine Yankee Atomic Power Company Thomas G. Dignan, Jr., Esquire 321 Old Ferry Road Ropes & Gray Wiscasset, ME 04578-4922 One International Place Boston, MA 02110-2624 Mr. George Zinke, Director Nuclear Safety and Regulatory Affairs Mr. Uldis Vanags Maine Yankee Atomic Power Company State Nuclear Safety Advisor 321 Old Ferry Road State Planning Office Wiscasset, ME 04578-4922 State House Station #38 Augusta, ME 04333 Mr. Jonathan M. Block Attorney at Law Mr. P. L. Anderson, Project Manager P.O. Box 566 Yankee Atomic Electric Company Putney, VT 05346-0566 580 Main Street Bolton, MA 01740-1398 Mr. Michael J. Meisner, President Main Yankee Atomic Power Company Regional Administrator, Region 1 321 Old Ferry Road U.S. Nuclear Regulatory Commission Wiscasset, ME 04578-4922 475 Allendale Road King of Prussia, PA 19406 Mr. Robert Fraser, Director Engineering First Selectman of Wiscasset Maine Yankee Atomic Power Company Municipal Building 321 Old Ferry Road I

U.S. Route 1 Wiscasset, ME 04578-4922 Wiscasset, ME 04578 Mr. Patrick J. Dostie Mr. Mark Roberts State of Maine Nuclear Safety U.S. Nuclear Regulatory Commission inspector 475 Allendale Road Maine Yankee Atomic Power Company King of Prussia, PA 19406 321 Old Ferry Road Wiscasset, ME 04578-4922 Mary Ann Lynch, Esquire Maine Yankee Atomic Power Company Mr. Mark Ferri, \\ ice President 321 Old Ferry Road Decommissioning nirector Wiscasset, ME 04578-4922 Maine Yankee Atomic Power Company 321 Old Ferry Road Mr. Neil Sheehan Wiscasset, ME 04578-4922 U.S. Nuclear Regulatory Commission i

475 Allendale Road King of Prussia, PA 19406 I

l I

I