Text
g ef h t C L%
APR 7 1986 Aeorgia Power Company
/ ATTN: Mr. R. J. Kelly Executive Vice President P. O. Box-4545 Atlanta, GA 30302 Gentlemen:
SUBJECT:
MEETING
SUMMARY
- V0GTLE FACILITY - DOCKET N0. 50-424 This refers to the management meeting conducted at your request in the NRC Region II Office on March 25, 1986.
This meeting was held to brief the NRC on the Vogtle Readiness Review Program submittals entitled " Module No. 9A -
Radiological Protection," " Module No. 9B - Chemistry," " Module No. 11 - Pipe Stress and Supports," " Module No.13C - Post Tensioned-Containment," and " Appendix G Measuring and Test Equipment."
It is our opinion that this meeting was beneficial and has provided a compre-hensive overview of the Vogtle Readiness Review Program and, speci#ically, the modules and appendix presented.
These in-depth presentations will better enable the NRC to conduct its evaluations of these submittals.
l In accordance with Section 2.790 of NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regulations, a copy of this letter and its enclosure will be placed in the NRC Public Document Room.
Should you have any questions concerning these matters, we will be pleased to discuss them.
Sincerely, Original Signed by Roger D. Walker /for i
J. Nelson Grace Regional Administrator
Enclosure:
List of Attendees cc w/ enc 1:
(See page 2) l 8604150147 860407 PDR ADOCK 05000424 A
PDR I '
s l
revf
APR 7 1986 i
l Georgia Power Company 2
fcw/ encl:
R. E. Conway, Senior Vice President &
j Project Director
/D. O. Foster, Vice President, Project f Support l
JP. D. Rice, Vice President, Project j Engineering JR. H. Pinson, Vice President, Project j Construction JJ. T. Beckham, Vice President &
General Manager - Operations
/R.A. Thomas,VicePresident, j Licensing JC. W. Hayes, Vogtle Quality I.AssuranceManager l
C. Ramsey, Manager -
j Readiness Review l
JG. B. Bockhold, General Manager, l
Nuclear Operations
/L.T.Gucwa, Chief l
, Nuclear Engineer vN. H. Googe, Project I.ConstructionManager D. Groover, Quality Assurance Site Manager -
l
/ onstruction C
/J. A. Bailey, Project Licensing M
/ anager vG. F. Trowbridge, Esq., Shaw,
/ Pittman, Potts and Trowbridge A3. W. Churchill, Esq., Shaw, M.Pittman,PottsandTrowbridge L. Blake, Jr., Esq., Shaw, I. Pittman, Potts and Trowbridge
. E. Joiner, Troutman, Sanders, I.LockermanandAshmore G. Ledbetter, Commissioner, Department of Human Resources
. H. Badger, Office of Planning v6.andBudget Kirkland, III, Counsel, l
l Office of the Consumer's Utility
(
vtI. Council l
C. Teper, Georgians Against l
Nuclear Energy cc w/ encl:
(Cont'd on page 3) i t
~
APR 7 1986 Georgia Power Company 3
pc w/ encl:
(Cont'd)
W. B. Margulies, Esq., Chairman, l
Atomic Safety and Licensing Board
/ Panel v0. H. Paris, Administrative Judge Atomic Safety and Licensing Board Panel l
. A. Linenberger, Jr., Administrative Judge Atomic Safety and Licensing Board i
/ Panel dB. P. Garde, Citizens Clinic Director, Government Accountability Project l
l fccw/ encl:
E. Reis, ELD i
dd. M. Hill, IE l
JH. Miller, NRR l
VW. Brach, ED0 l
'M. Sinkule, RII l
- y. Rankin, RII /
AIRC Resident Inspector Document Control Desk State of Georgia v l
l l
l l
1 RII RII RII RI h
W nkin:jk MSinkule VBrownlee er 4/4/86 4/ /86 4/Q/86 4/ /86 a
APR 7 1986 ENCLOSURE LIST OF ATTENDEES Vogtle Readiness Review Meeting March 25, 1986, at 12:30 p.m.
U. S. Nuclear Regulatory Commission R. D. Walker, Director, Division of Reactor Projects (DRP)
L. A. Reyes, Deputy Director, DRP C. A. Julian, Chief, Operations Branch, Division of Reactor Safety (DRS)
D. M. Collins, Chief, Emergency Preparedness and Radiological Protection Branch, Division of Radiation Safety and Safeguards (DRSS)
M. V. Sinkule, Chief, Reactor Projects Section (RPS) 3C, DRP l
F. Jape, Chief, Test Programs Section, DRS l
J. J. Blake, Chief, Materials and Processes Section, DRS l
C. M. Hosey, Chief, Facilities Radiation Protection (FRP) Section, DRSS G. A. Belisle, Acting Chief, Quality Assurance Programs Section, DRS P. G. Stoddart, Acting Chief, Radiological Effluents and Chemistry Section, DRSS W. H. Rankin, Tecnnical Assistant, DRSS i
l J. W. Thompson, Project Engineer, NRR J. R. Harris, Reactor Engineer, Module 13C, Plant Systems Section, DRS i
J. J. Lenahan, Reactor Engineer, Module 13C, Test Programs Section, DRS S. J. Vias, Lead Inspector, Module 11, Materials and Processes Section, DRS G. L. Troup, Senior Radiation Specialist, FRP, DRSS R. J. Serbu, Health Physicist, NRR Reviewer - Module 9A C. G. Hammer, Mechanical Engineer, NRR Reviewer - Module 11 S. P. Chan, Structural Engineer, NRR Reviewer - Module 13C J. Wing, NRR Reviewer - Module 9B W. E. Scott, IE Georgia Power Company D. O. Foster, Vice President, Project Support W. C. Ramsey, Manager, Readiness Review Program i
H. P. Walker, Readiness Review Discipline Manager and Assistant Plant Manager i
I. A. Kochery, Engineer l
M. D. Llewellyn, Supervisor, Technical Support J. E. Seagraves, Discipline Manager, Readiness Review i
W. M. Wright, Discipline Manager, Southern Company Services i
J. A. Curtin, IDR Team Leader, Stone and Webster Engineering Corporation R. W. McManus, Readiness Review Technical Manager l