') Commonwealth Edison
~
\\
"7_, 4 One First National Plaza, Chicago, Illinois
/ Address Reply to: Post Offic2 Box 767 Nd Chicago, Ulinois 60690 - 0767 July 25, 1986 Mr. James G. Keppler Regional Administrator U.S. Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, IL 60137
Subject:
Zion Nuclear Power Station Units 1 and 2 Response to I&E Inspection Report Nos.
50-295/85-005 and 50-304/85-005 NRC Docket Nos. 50-295 and 50-304
Reference:
March 6, 1986 letter from W. D. Shafer to Cordell Reed.
Dear Mr. Keppler:
The referenced letter confirmed the results of a conference call held on February 4, 1986 with representatives of NRR, Region III, and Commonwealth Edison Company. In addition to reaching agreement cn the performance of a leakage test of the control room ductwork, Commonwealth Edison Company committed to providing NRC with a copy of the test procedure.
This procedure is enclosed with this letter.
The currently scheduled time period for the test's performance is during the middle of August. The specific date will be finalized.through this office in the near future.
If any further questions arise concerning this matter, please contact this office.
Very truly yours,
\\p P. C. LeBlond Nuclear Licensing Administrator i
1 l
1m Enclosure cc: NRC Resident Inspector - Zion C. F. Gill - Region III J. J. Hayes - NRR J. A. Norris - NRR 8608190328 860725 PDR ADOCK 05000295 1903K G