ML20205E544

From kanterella
Jump to navigation Jump to search
Forwards Insp Repts 50-361/99-01 & 50-362/99-01 on 990103- 0220.Three non-cited Violations Were Identified
ML20205E544
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 03/30/1999
From: Laura Smith
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Ray H
SOUTHERN CALIFORNIA EDISON CO.
Shared Package
ML20205E547 List:
References
50-361-99-01, 50-361-99-1, 50-362-99-01, 50-362-99-1, NUDOCS 9904050220
Download: ML20205E544 (5)


See also: IR 05000361/1999001

Text

.

4" "4e UNITED STATES 1

.. NUCLEAR REGULATORY COMMISSION

a o ,

i. j REG!oN IV j

611 RYAN PLAZA DRIVE, CUlTE 400

,,,g ARLINGTON, TEXAS 76011-8064

MAR 3 0 999

Harold B. Ray, Executive Vice President

Southern California Edison Co.

San Onofre Nuclear Generating Station

P.O. Box 128

San Clemente, California 92674-0128

SUBJECT: NRC INSPECTION REPORT NO. 50-361/99-01; 50-362/99-01

Dear Mr. Ray:

This refers to the inspection conducted on January 3 through February 20,1999, at the

San Onofre Nuclear Generating Station, Units 2 and 3, facility. The enclosed report presents

the results of this inspection.

l

During the 7-week period covered by this inspection, your conduct of activities at 1:ie

'

l San Onofre facility was genemlly characterized by safety-conscious operation, sound

l engineering and maintenance practices, and careful radiological work controls.

!

!

Based on the results of this inspection, the NRC has determined that three violations of NRC

( requirements occurred. These violations are being treated as noncited violations (NCVs),

consistent with Appendix C of the NRC Enforcement Policy. These NCVs are described in the

subject inspection report. If you contest the violation or severity level of these NCVs, you

should provide a response within 30 days of the date of this inspection report, with the basis for

your denial, to the Nuclear Regulatory Commission, ATTN: Document Control Desk,

i Washington, DC 20555-0001, with copies to the Regional Administrator, Region IV, the

Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington,

DC 20555-0001, and the resident inspector at the facility.

! In accordance with 10 CFR 2.790 of the NRC's " Rules of Practice," a copy of this letter and its

l enclosure will be placed in the NRC Public Documer t Room.

l

Should you have any questions concerning this inspection, we will be pleased to discuss them

with you.

Sincerely,

o

r VI -

a Joy Smith, Ac g Chief

Project Branch ,

Division of Reactor Projects 1

&

9904050220 990330

PDR ADOCK 05000361

G PDR

.

.

Southern California Edison Co. -2-

Docket Nos.: 50-361

50-362

License Nos.; NPF-10

NPF-15

Enclosure:

NRC Inspection Report No.

50-361/99-01;50-362/99-01

cc w/ enclosure:

Chairman, Board of Supervisors

County of San Diego

1600 Pacific Highway, Room 335

San Diego, California 92101

Alan R. Watts, Esq.

Woodruff, Spradlin & Smart

701 S. Parker St. Suite 7000

Orange, California 92868-4720

Sherwin Harris, Resource Project Manager

Public Utilities Department

City of Riverside

3900 Main Street

Riverside, California 92522

R. W. Krieger, Vice President

Southern California Edson Company j

San Onofre Nuclear Generating Station j

P.O. Box 128 i

San Clemente, California 92674-0128 l

l

Stephen A. Woods, Senior Health Physicist {

Division of Drinking Water and j

Environmental Management l

Nuclear Emergency Response Program j

California Department of Health Services i

P.O. Box 942732, M/S 396  !

Sacramento, California 94334-7320  ;

!

'

l Mr. Michael R. Olson

Sr. Energy Administrator

San Diego Gas & Electric Company

P. O. Box 1831  ;

San Diego, California 92112-4150 I

i

i

'

l

.

Southern California Edison Co. -3-

Mr. Steve Hsu

Radiological Health Branch

State Department of Health Services

P.O. Box 942732 z

'

Sacramento, California 94234

Mayor

City of San Clemente

100 Avenida Presidio

San Clemente, California 92672

Mr. Truman Burn.e\Mr. Robert Kinosian

California Public Utilities Commission

505 Van Ness, Rm. 4102

San Francisco, California 94102

l

!

l

l

1

l

l

l

!

l

i

l

l

1

l

l

1

MAR 3 01999

Southern California Edison Co. -4

E-Mail report to T. Frye (TJF)

E-Mail report to D. Lange (DJL)'

E-Mail report to NRR Event Tracking System (IPAS)

E-Mail report to Document Control Desk (DOCDESK)

E-Mail report to Richard Correia (RPC)

. E-Mail report to Frank Talbot (FXT)

l

bec to DCD (IE01)

bec distrib. by RIV:

Regional Administrator Resident inspector

DRP Director DRS-PSB

'

l DRS Director MIS System

Branch Chief (DRP/E) RIV File

. Senior Project inspector (DRP/E)

, Branch Chief (DRP/TSS)

l'

l

DOCUMENT NAME: R:\_SO901RP.JAS

To receive copy of document, Indicate in box: "C" = Copy without enclosures "E" = Copy with enclosures "N" = No copy

RIV:DRP/E RI:DRP/E SRI:DRP/E -

LC:DRS:PSB C:DRP/E

JGKramer %eewI DECorporandy b4 JASloan b%er*' GMGood 6htVLJSmith

'l03g99 M 03/a499 FJs 03/2299 % 03(3h9 03M99

OFFICIAL RECORD COPY

.1

y__ q

.- J

"

MG 3 0 m

l

Southern California Edison Co. -4-

l'

'

' E-Mail report to T. Frye (TJF) 1

'

E-Mail report to D. Lange (DJL)

E-Mail report to NRR Event Tracking System (IPAS)

E-Mail report to Document Control Desk (DOCDESK)

E-Mail report to Richard Correia (RPC) l

E-Mail report to Frank Talbot (FXT)

bec to DCD (IE01)

i'

'

bec distrib. by RIV: ,

i

.

Regional Administrator - Resident inspector

! DRP Director DRS-PSB

l DRS Director. MIS System

L- Branch Chief (DRP/E) RIV File

Senior Project inspector (DRP/E) l

Branch Chief (DRP/TSS) -

!

!

l

/

050030

DOCUMENT NAME: R:\_SO901RP.JAS

To receive copy of document, Indicate in box: "C" = Copy without enclosures "E" = Copy with enclosures "N" = No copy

RIV:DRP/E RI:DRP/E SRI:DRP/E l C:DRS:PSB C:DRP/E

JGKramer D ,cima I DECorporandy ow JASloan et c" GMGood (MVLJSmith

03%299 'J 03/W99 FIO 03/2299 A 03/1/99 03/W99

OFFICIAL RECORD COPY