ML20205A748

From kanterella
Jump to navigation Jump to search
Insp Repts 50-424/86-39 & 50-425/86-19 on 860505-09 & 0623. Violations Noted:Failure to Provide Accurate Info on Elimination of Intermediate Pipe Breaks & Whip Restraints & to Follow Procedures for Control of Welding Consumables
ML20205A748
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 07/15/1986
From: Blake J, Hallstrom G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20205A715 List:
References
50-424-86-39, 50-425-86-19, NUDOCS 8608110438
Download: ML20205A748 (32)


See also: IR 05000424/1986039

Text

.

e "titi,

UNITED STATES

m

-

f

  • o

NUCLEAR REGULATORY COMMISSION

~'

[

REGION 11

o

g

j

101 MARIETTA STREET, N.W.

2

ATLANTA, GEORGI A 30323

%4.....$

Report Nos.: 50-424/86-39 and 50-425/86-19

Licensee: Georgia Power Company

P. O. Box 4545

Atlanta, GA 30302

Docket Nos.: 50-424 and 50-425

License Nos.: CPPR-108 and CPPR-109

Facility Name: Vogtle 1 and 2

Inspection Condu ted: May 5-9 and June 23, 1986

7!

b

M

Inspector:

woe,

e

G /A.

trorii,

/Datd Signed

/-I/66

Approved

u

7

,

J./J. plakr, Section Chief

'Date' Signed

Eggineering Branch

ivision of Reactor Safety

,

SUMMARY

Scope:

This special announced inspection was conducted on site in the areas of

licensee action on previous enforcement matters (Units 1 and 2), housekeeping

Units 1 and 2), material control (Units 1 and 2), and safety-related piping

Unit 2)

Results:

Two violations were identified - Failure to provide accurate informa-

tion on elimination of intermediate pipe breaks and associated whip restraints;

and Failure to follow procedures for control of welding consumables.

]

eggetgggg $$8

g4

0

- --

_.

- . - _ .

'

.

.

REPORT DETAILS

1.

Persons Contacted

1

Licensee Employees

  • R. H. Pinson, Vice President, Construction
  • D. O. Foster, Vice President and Project Support Manager
  • P. D. Rice, Vice President, Engineering
  • C. W. Hayes, Project Quality Assurance (QA) Manager
  • E. D. Groover, QA Site Manager, Construction
  • C. E. Belflower, QA Site Manager, Operations
  • G. A. McCarley, Project Compliance Coordinator
  • B. C. Harbin, Manager of Quality Control (QC), Construction
  • N. Lankford, QC Support Supervisor

J. E. Seagraves, RR Discipline Manager (Construction)

  • W. C. Gabbard, Regulatory Specialist
  • H. P. Walker, Manager, Unit Operations
  • G. Bockhold, General Manager, Vogtle Nuclear Operations

Other licensee employees contacted included construction craftsmen,

engineers, technicians, operators, mechanics, and office personnel.

Other Organizations

  • W. C. Ramsey, Southern Company Services (SCS), RR Project Manager
  • 0. Batum, SCS, Deputy to Vice President of Project Engineering
  • D. W. Strohman, Bechtel Power Corporation (BPC), Project QA Engineer

D. Niehoff, BPC, Deputy Engineering Group Supervisor

  • M. R. Thaker, BPC, RR Civil-Structural Design Team Leader
  • R. C. Somerfield, BPC, RR Construction Team Leader

R. Malin, BPC, Civil / Structural Engineering Group Supervisor

D. Sewell, BPC, Plant Design / Pipe Support and Stress

Engineering Group Supervisor

A. Attor, BPC, Senior Pipe Support and Stress Engineer

NRC Resident Inspectors

  • H. Livermore, Senior Resident Inspector (Construction)
  • J. Rogge, Senior Resident Inspector (Operations)
  • Attended exit interview

2.

Exit Interview

T;ie inspection scope and findings were summarized on May 9,1986, with

those persons indicated in paragraph 1 above.

The inspector described the

areas inspected. No dissenting comments were received from the licensee.

'

.

'

.

2

(0 pen) Violation 424/86-39-01, 425/86-19-01, Failure to provide accurate

information for elimination of intermediate pipe breaks and associated whip

restraints - paragraph 3.a.(4).

(0 pen) Inspector Followup Item 424/86-39-02, 425/86-19-02, Field confirma-

tion of distance between welded attachments and the location of intermediate

pipe breaks - paragraph 3.a.(5).

(0 pen) Violation 424/86-39-03, 425/86-19-03, Failure to follow procedures

for control of welding consumables - paragraph 6.b.(4)

The licensee did identify as proprietary some of the materials provided to

and reviewed by the inspector during this inspection; however, details from

those materials are not included in this report.

3.

Licensee Action on Previous Enforcement Matters

References:

(a) Letter, dated May 9,1986, from R. E. Conway (Georgia

Power Company (GPC)) to B. J. Youngblood (NRC Office of

Nuclear Reactor Regulation (NRR)) regarding Vogtle 1 and

2 Intermediate Pipe Breaks.

(b) Memorandum, dated March 18, 1986, from C. E. Rossi

(NRC-NRR) to A. Gibson (NRC Region II) providing an

interpretation of acceptance criteria for elimination of

intermediate pipe breaks.

(c) Letter, dated February 7,1986, from D. O. Foster (GPC)

to J. N. Grace (NRC Region II) responding to unresolved

and inspector followup items described in NRC Inspection

Report 424/85-35.

(d) Letter, dated November 11, 1983, from D. O. Foster (GPC)

to H. R. Denton (NRC) requesting alternate intermediate

pipe break criteria which would allow climination of 182

previously postulated intermediate pipe breaks and 110

associated pipe whip restraints per unit.

(e) Letter, dated April 26, 1984, from D. O. Foster (GPC) to

H. R. Denton (NRC) providing technical information to

justify a request for approval of alternate pipe break

criteria.

(f) Letter, dated June 26, 1984, from T. M. Novak (NRC

Division of Licensing) to D. O. Foster (GPC) providing

an evaluation and acceptance of alternate pipe break

criteria.

(g) Letter dated April 30, 1986, from F. B. Marsh (BPC)

to 0. Batum (SCS) providing details on BPC review of

conformance to alternate intermediate pipe break

criteria.

. -

-

.

-

.

'

.

3

a.

(Closed) Unresolved item (424/85-35-03):

Design Control of Interme-

diate Pipe Breaks

(1) Background Information

This item was originated to identify NRC Region II inspectors'

concern that the licensee had not implemented a particular design

commitment in the postulation and mitigation of intermediate pipe

breaks on high-energy piping.

The commitment was part of the

licensee's design bases (Reference (e)) in obtaining NRC accept-

ance (Reference (f)) of deviation of the requirements to postulate

arbitrary intermediate pipe breaks from those included within NRC

Branch Technical Position MEB 3-1 " Postulated Breakage and Leakage

Locations in Fluid System Piping Outside Containment."

The

licensee's proposal of alternate intermediate break criteria was

made to avoid the installation of approximately 110 pipe whip

restraints per unit (Reference (d)) which MEB 3-1 would have

required for the mitigation of design postulated pipe breaks. The

alternate criteria allows elimination of arbitrary intermediate

pipe breaks together with associated whip restraints provided:

Possibility of stress corrosion cracking has been minimized;

Thermal and vibration induced piping fatigue has been

minimized;

Steam / water effects have been minimized;

Local bending stresses from welded attachments have been

minimized.

(2) 5D Criteria

The design commitment of concern was intended to minimize stress

from welded attachments.

As included in Reference (e), this

commitment was to assure that no welded attachments / supports lay

within five pipe diameters (50 criteria) from any postulated pipe

locations that would be eliminated in accordance with the alter-

nate break criteria.

The SD commitment was included as a partial

alternative to the installation of pipe whip restraints. The NRC

had accepted SD criteria at other plants as a reasonable require-

ment to assure that welded supports would not be located close

enough to postulated break points to contribute to the severity of

damage that could occur during unanticipated transients when

stresses in the involved piping can greatly exceed ASME design

,

Code allowables.

_

- -

.

_

_

_ _ _ _

. _ _ _ . _ _ _ .

_.

._.___

-

.

.

4

(3) History

Region II inspectors first identified their concern that the

licensee had not implemented the SD criteria during an inspection

of the licensce's Readiness Review work in August,1985.

The

licensee was questioned regarding the absence of any implementing

procedures during the site inspection and again in a telephone

call on September 18, 1985.

The licensee's initial informal

response was that the commitment was only required to be met at

the time of the April 26, 1984, submittal (Reference (e)), and

that it was not intended to be met for later design iterations;

i.e., new break locations due to later changes in the piping

installation.

The inspectors questioned this interpretation as

the written licensee proposal and the NRC acceptance of the

proposal did not support this view.

The inspectors formally

documented their concern to the licensee in NRC Report No.

50-424/85-35 dated December 18, 1985.

The licensee formally

responded by letter to Region II dated February 7,1986 (Refer-

ence (c)).

The licensee contended that the SD commitment had not

been a commitment but that NRC acceptance of minimized stress from

welded attachments for the alternate intermediate break criteria

was based instead on their compliance with the ASME Section III,

Subsections NC/ND-3645, generalized requirements that the design

appropriately consider the effects of welded attachments.

The

inspectors noted that NC/ND-3645 was not adequate to satisfy a

major objective of the SD criteria; i.e., minimizing the contribu-

tion of supports to the severity of damage that could occur from

unanticipated transients with stresses beyond Code allowables.

As part of a Region II inspection on February 24-28, 1986

(Inspection Report No. 424/86-11), the licensee was again

requested to provide technical support for their failure to

implement the 50 criteria as a continuing commitment.

The

l

licensee again responded that the SD criteria was not considered a

commitment based on their previous discussions which had been held

'

with reviewers from the NRC Office of Nuclear Reactor Regulation

(NRR) while obtaining NRC approval to deviate from MEB 3-1.

As a

followup to inspection 86-11, a formal response from NRR was

requested regarding the licensee's statements that the SD criteria

was not a commitment.

Formal response from NRR (Reference (b))

clarified that, contrary to the licensee's repeated explanations,

l

the SD criteria had been considered a commitment and that it had

been material to NRC acceptance of the licensee's proposal for

alternate intermediate break criteria which deviated from ME8 3-1.

- - - - - - -

_ - -

_ --.

.

- --. . _ - -

-,

.

- - . - . -

-

.

.

5

(4) May 4-9, 1986, Region II Inspection

In order to evaluate the extent of the licensee's noncompliance

during the current inspection, the inspector informed cognizant

licensee personnel on April 29, 1986, that this was an announced

inspection and requested that data be gathered for use on inspect-

ing postulated break locations to determine whether the licensee

had complied with the SD criteria when it was originally stated in

April, 1984, and to examine their current compliance.

In response

to this request the licensee performed additional review and

informed the inspector at the beginning of this inspection that

the SD criteria was not currently met and had not been met at the

time it was originally stated.

The licensee provided summary

details (Reference (a)) of the six instances identified to date of

welded attachments located within five pipe diameters from postu-

lated pipe break locations which had been eliminated in accordance

with alternate intermediate break criteria. Four of the intermedi-

ate breaks eliminated had been postulated since April 26, 1984.

Two of the breaks eliminated had been postulated before April 26,

1984.

These were main steam line breaks P-1054-C and P-1055-C.

Consequently, associated pipe whip restraints PBR-217 and PBR-218

were climinated without meeting the SD criteria.

Cognizant

licensee personnel indicated they could not determine the reason

for the inaccurate statements in their April 26, 1984, submittal

regarding pipe breaks P-1054-C and P-1055-C.

The inspector examined internal licensee correspondence dated

April 30, 1986 (Reference (g)) which established that the licensee

was aware as of July, 1984, of their noncompliance with the April,

1984 commitment. Cognizant licensee personnel offered no explana-

tion as to why the NRC had not been informed of this noncompliance

as of the date of this inspection.

The inspector informed the licensee 'that their inaccurate state-

ments regarding pipe breaks P-1054-C and P-1055-C in their

April 26,1984, submittal appeared to be a material false state-

ment as defined in 10 CFR 2 and as such was a violation of NRC

requirements.

Therefore, unresolved item 424/85-35-03 would

be closed and this matter will be identified as violation

424/86-39-01, 425/86-19-01, Failure to provide accurate informa-

tion for elimination of intermediate pipe breaks and associated

whip restraints.

Also, that this violation would be reviewed for

j

escalated enforcement action.

!

(5) Details of Region II Inspection of SD Noncompliance

!

.

In examining the licensee's findings relative to their noncom-

I

pliance with the SD criteria, the inspector completed field

examinations and examined 'oackground documentation to enable

independent verification of the summary data included in

Reference (a), attachment 1.

. _ -

.

.

-

.

.

.

.

.

.

.

.

6

The inspector verified that break locations postulated after

April 26, 1984, with welded attachments within five pipe diameters

were as follows:

Stress

Break

Support

Item

Isometric

Calc

Data

Within

X4CP

Point

5 pipe diameter

1

IK3-1206-066-01

7001A

26A

V1-1208-066-H006

2

1K3-1314-DB4-03

7063A

800

V1-1314-084-H013

3

1K4-1208-005-02

7092

88

V1-1208-005-H006

4

IK4-1208-005-02

7092

156

V1-1208-005-H001

During the above examination the inspector noted that support

location tolerances for the small diameter pipe involved amounted

to as much as three pipe diameters. Therefore, the application of

a five pipe diameter minimum distance criteria could not be

assured without field investigation. Cognizant licensee personnel

informed the inspector that the licensee's reviews involved had

been based on design stress isometrics and field verification had

been conducted only for the six instances identified on Attach-

ment 1.

The inspector stressed the need for measurements in the

field to enable proper application of the SD criteria and was

informed that modifications to the confirmation program for IEB 79-14 would be considered so as to assure the BPC review of

1

pertinent as-built dimensions from welded attachments to inter-

t

mediate break locations.

The inspector informed cognizant licensee personnel that the need

for further NRC examination of proper application of the criteria

including field measurements would be identified as Inspector

Followup Item 424/86-39-02, 425/86-19-02, Field confirmation of

distance between welded attachments and the location of inter-

mediate pipe breaks.

The inspector also verified that break locations postulated prior

to April 26, 1984, with welded attachments within five pipe

diameters were as follows:

'

Stress

Break Support

Referenced

Calc

Data

Within

Item

Break No.

Isometric

X4CP

Point 5 pipe diameter

5

P-1055-C

1K5-1301-001-01 7073/74

68 V1-1301-008-H052

6

P-1054-C

1K5-1301-001-01 7073/74

75 V1-1301-008-H055

.

During field inspection of main steam line break locations listed

above, the inspector noted that associated pipe whip restraints

!

(PBR-217 and PBR-218) had been partially completed since they were

also to function as pipe supports. However, they had been elimi-

i

nated as whip restraints without meeting the required SD criteria

.

.

7

and were not presently able to meet this required design

function.

Cognizant licensee personnel and supporting data

verified that the licensee did not intend to complete fabrication

of these whip restraints as of the date of this inspection.

(6) NRC/GPC Enforcement Conference

Subsequent to this inspection, Region II reviewed the need for

escalated enforcement on this matter.

A decision was reached to

schedule an enforcement conference with the licensee on this

matter.

This conference was held in the NRC Region II office,

Atlanta, Georgia, on June 23, 1986. Attendees were as follows:

Licensee Attendees: R. E. Conway, Vogtle Project Director, Georgia

Power Company (GPC)

P. D. Rice, Vice President, Vogtle Engineer-

ing, GPC

C. W. Hays, Vogtle Project Quality Assurance

Menager, GPC

J. Bailey, Vogtle Project Licensing Manager,

Southern Company Services (SCS)

0. Batum, Deputy to Vogtle, Engineering Vice

President, SCS

F. B. Marsh, Vogtle Project Engineering Manager

Bechtel Power Corporation (BPC)

S. J. Cereghio, Nuclear Group Supervisor, BPC

W. E. Burns, Nuclear Licensing-Nuclear

Operations, GPC

C. W. Whitney, GPC-Vogtle Legal Counsel

NRC Attendees:

R. D. Walker, Acting Deputy Regional

Administrator

L. A. Reyes, Acting Director, Division of

Reactor Projects (DRP)

B. W. Jones, Regional Counsel, RII

V. Panciera, Deputy Director, Division of

Reactor Safety (DRS)

V. L. Brownlee, Chief, Reactor Projects

Branch 3, DRP

A. R. Herdt, Chief, Engineering Branch, DRS

i

L. Trocine, Enforcement Specialist, RII

M. V. Sinkule, Chief, Reactor Projects

'

Section 3C, DRP

H. H. Livermore, Senior Resident Inspector,

Construction, Vogtle

E. F. Christnot, Vogtle Project Engineer, DRP

E. H. Girard, Reactor Inspector, DRS

G. A. Hallstrom, Reactor Inspector, DRS

S. J. Vias, Reactor Inspector, DRS

M. Miller, Vogtle Project Manager, Office of

Nuclear Reactor Regulation (NRR)

- _ _ _

. _ -

-

_

_

_ - - - .-

_

_

'

.

.

8

R. L. Balland, Chief. Engineering Branch,

PWR-A, NRR

G. Bagchi, Section Leader, Engineering Branch,

PWR-A, NRR

E. Holler, Enforcement Specialist, Office of

Inspection and Enforcement (IE)

The meeting was convened at 10:00 a.m., on June 23, 1986.

The

licensee was informed of the Region II decision that this matter

was considered a material false statement, but that the questions

of severity level and potential civil penalty were not yet decided.

GPC Vice President Conway responded that GPC's position has been

and continues to be one of complete, cpen, and honest communica-

tion with the NRC but that there had been a QA breakdown on this

matter.

Vice President Rice then submitted a proposed agenda and

summary of points for discussion.

This licensee submittal is

included as an attachment to this report.

Significant clarifications / amplifications obtained during the

licensee's presentation were as follows:

Arbitraryintermediatepipebreak(AIPB) concept

-

Mis-communication had occurred between the licensee

and NRR regarding the need of SD criteria to mitigate

the severity of potential damage from unanticipated

transients.

The licensee had understood that conformance to

-

NC/ND-3645 would satisfy the need to minimize stress

l

from welded attachments.

This view is supported by

other existing design features to accomplish defense on

I

depth objectives.

!

BPC design engineers had considered SD criteria to be

-

non-relevant since conformance to NC/ND-3645 was main-

tained.

Chronology

l

!

The BPC review which commenced in June, 1984, was for

-

completeness regarding AIPB requirements and was the

first review with supporting documentation.

Supporting

documentation is unavailable for reviews occurring

before the April 26, 1984, submittal.

l

The BPC review completed in July,1984, did establish

-

!

the lack of conformance to SD criteria for main steam

breaks P-1054-C and P-1055-C.

However, this lack of

conformance was not reported to the NRC since the 50

criteria was considered non-relevant as reported above.

.

-

. - - _ .

.

.

_

_

- - _ _ _

'

.

.

9

Error in Project Proposal

The initial review of baseline data was not done in

-

accordance with formally established GPC policies and

procedures.

The initial review was completed as an

engineering study and no formal policies and procedures

had existed to control this type of activity similar to

those controlling other formal licensee submittals such

as 10.55(e) and Part 21 reports.

For the 11 cases where welded attachments within SD of

-

the break point which have been identified through the

June, 1986, licensee engineering review, there were 11

cases in the main steam system.

Of these, only break

P-1054-C is considered by the licensee to require

further deliberations regarding its lack of conformance

to the SD criteria.

Root Cause

The licensee agreed that a QA program weakness had

-

existed due to lack of formality in controlling the

-

engineering studies associated with the SD criteria.

The licensee agreed that the materiality of the lack of

-

conformance with the 50 criteria should have been

identified in July 1984 when the nonconformances were

first identified.

The licensee's failure to identify

materiality was attributed to the failure to properly

interpret the SD criteria versus NC/ND-3645 conformance.

The interpretation failure was attributed to mis-

communication with NRR which would have been rectified

under formal controlling procedures.

The lack of notification to NRC of the inaccuracies in

-

the April 26, 1984, submittal which were discovered on

July, 1984, was attributed to the licensee's failure to

recognize the materiality of the 50 requirements.

Corrective Actions

The relevant design criteria (DC-1018) has been revised

-

to include the 50 criteria.

However, the revised

DC-1018 will not be implemented until resolution of the

technical issue with NRC.

The licensee's objective is

to avoid imposing the SD criteria due to potential

rework required.

1

-

.

.

10

The QA audit of similar engineering studies / proposals

-

included a sample of five which were similar to the AIPB

studies.

These five had not been examined during

readiness review activities.

No discrepancies were

identified.

.

The training seminar for project managers who prepare or

-

approve regulatory comitments will be conducted by Vice

President Rice.

-

The letter to NRC on a proposed AIPB concept to resolve

the technical issue is expected to be transmitted during

the first week of July, 1986.

The meeting was adjourned at 11:50 a.m., on June 23, 1986.

NRC escalated enforcement activities on this matter is not complete.

Therefore no Notice of Violation on this matter is enclosed with this

report.

Separate correspondence will be issued on the results of NRC

deliberations on this matter,

b.

(Closed) Unresolved Item (424/86-03-02, 425/86-02-02):

Polar Crane

Design

This item concerns potentially inadequate design calculations for

seismic qualification of the VEGP Polar Crane. Apparent discrepancies

were identified during the NRC review of the Seismic design calcula-

tion package (BPC leg AXAL01-46-2) provided by the VEGP Polar Crane

Supplier.

BPC specification X4AL01, Revision 1, dated December 14,

1978, requires dynamic analyses for eight different loading conditions

for both Safe Shutdown Earthquake (SSE) and Operational Basis Earth-

quake (0BE).-

Analyses for two of the required loading conditions

(trolley in center of span with full load in mid position and trolley

at end of span with full load in mid position) were not included. NRC

concern was also expressed due to the possibility that the worst case

for hook

height may not have been included in the load conditions

originally specified for analysis.

The technical adequacy of the initial BPC response was questioned on

two points as follows:

The implication that crane girder seismic stresses are essentially

unaffected by the lifted load.

Stated reasoning is that all

Z-component (vertical direction) earthquake stresses are absorbed

in the rope;

i.e., that these stresses are r.ever transmitted to

the Polar Crane Bridge Girder.

.

---

-.

, - _ - - . .

-

-

'

,,

>

,

.

.

11

-

,

,a

w

i

p/

i

The contentien thatathe up-position of lifted load is the worst

2

case for hook height.

The stated basis f6r this contention is

~-

-

that the natural . structural frequency (about 2 hertz) for the

! a j;

load /ropeicombination in the up position corfesponds to the peak

..

-

acceleration of the vertical seismic response , spectra.

Further

.

support of an accurate coincidence of the1 frequencies is necessary

F

since lowering the load could increase the seismic acceleration if

'

the frequencies do not coincide.

k

.

s

i

-

Further GPC response on this issue was transmitted [GN-892)~.

y letters, dated

i

April 17, 1986, (Log: GN-864) and May 1, 1986 (Log:

Engineer-

ing justification in response to the above questioqs was as follows:

-

'

!

Calculated stresses from model response specfrum { worst-case load)

!

analyses were provided to show that the .Y-component (tangential

1

direction) stresses are the major contributor to the Crane girder

'

seismic stresses.

The vertical (Z-direction) load ~c'ontributes

p

^

{

primarily to rope stresses and is transferred from the rope to the

l

girder.

However, the resultant bending stress is ~ considerably

^

less than the Y-component stresses and, therefore, contributes

'

little to the Crane girder seismic. stresses.

'

i

Further support of the up-position of- lifted load as the worst

!

case for hook height was provided through a comparison of the

j

natural frequencies of the polar Crane system as obta'ined through

l.

finite element model analysis by the polar crane vendor with

!

additional calculations completed by BPC on Apr.11 14,1986.

Additional clarification established that. the initial _ response

!

spectra reviewed represented the response of a cingle-degree-of-

!

freedom oscillator mounted on the lifted load and not the response

i

of the polar crane structure.

The basis for seismic analysis of

1

the polar crane girders is a set of in-siiructure response spectra

!

-developed from a time-history analysis of the b'ilding.

The set

u

of vertical response spectra show ' peak responses to lie in the

range from 2 to 10 cps. Below 2 cps, the response is a descending

i

j

ramp. Therefore, as the load is lowered and frequency reduced the

j

crane will experience progressively lower levels of , amplification

'

p

in response.

,.

!

During review of the above information prior to this inspection further

question was . raised regarding conformance with allowable stress

criteria specified in FSAR paragraph 9.1.5.2.3.1.B versus stress values

stated from the model response spectrum analyses. Additional clarifi-

-

cation transmitted with the letter of May 1,1986, indicated acceptable

polar crane component stresses.

During this inspection the inspector' examined background data support-

.-

ing the engineering justification provided within GPC's April 17, 1986,

and May 1, 1986 letters.

No discrepancies were identified and this

item is considered closed.

-

-

.

.

.

12

c.

(0 pen) Unresolved Item (424/86-03-03, 425/86-02-03)

High Strength

Bolted Connections

This item concerns ASTM A325 and A490 high strength steel bolts

installed at plant Vogtle.

Discussions with QC inspectors and other

cognizant licensee personnel had identified potential overtensioning of

bolts on mainplate girder #5 at elevation 240' in the Control Building.

The girder was installed in August 1982, and potential overtorquing

was observed due to lack of conformance to " turn-of-nut" installation

requirements within construction procedure CD-T-16. Bolts in girder #5

were replaced.

However, followup discussions with cognizant licensee personnel

had established additional potential for overtensioning due to the

following:

A common philosophy that bolt overtensioning would not present a

problem as long as the bolts did not break during installation. A

technically supported justification of this philosophy was

requested.

An apparent inability of the QC inspection program (past or

present) to identify overtensioning (overtorquing) to near failure

limits.

QC inspection personnel uniformly stated that CD-T-16

specified only that the minimum required torque be checked; i.e.,

no check for potential overtorque is required or conducted and QA

surveillance of " snug tightening" or application of reference

match marks is not required.

Installation of high strength bolts by craftsmen who had not

received training on the " turn-of-nut" method.

The turn-of-nut

method was initiated on Revision 3, dated July 23, 1982, of

CF-T-16.

Initial training of construction craftsman was completed

on September 8,1982.

Statements by cognizant licensee personnel that the minimum time

frame during which installation by turn-of-nut method could be

suspect and overtorque a potential problem is from July 23 to

September 8, 1982.

Further GPC response on this issue was transmitted by letter to

Region II dated April 17,1986, (Log:

GN-864) and reviewed by the

inspector prior to this inspection.

The adequacy of the engineering

justification was questioned on several points and discussed with

cognizant licensee personnel during this inspection. Further justifi-

cation was requested on the following apparent inconsistencies, as a

minimum.

.

-

-

-

-

-

- -.

.-

-

- - - -

.

.

13

!

>

The contention that bolt overtension would have been identified by

i

the QC inspection program; i.e., on overtensioned bolt would turn

(or break) prior to reaching the minimum torque setting on the

calibrated torque wrench.

(This contention apparently ignores

i

test data showing significant remaining bolt tension capacity

above the ASTM proof load (elastic limit) versus CD-T-16 require-

ments that test torque wrenches be calibrated below proof load.)

The contention that the credibility of the GPC bolting program to

identify overtensioned bolts is established by GPC audits and

audits by others.

(This contention apparently ignores the fact

that installation methods and QC procedures which were audited are

4

i

structured to locate and correct undertorqued bolts - overtensioned

bolts are not addressed.)

I

The contention that design in accordance with the 1969 AISC

specification will yield factors of safety of a least 3 and 5,

respectively against ultimate tension and shear failures.

(This

,

contention apparently ignores the 'more germain safety factors

j

associated with the shear capacity of a friction connection using

tensioned bolts and the tensile capacity of these bolts,

i.e.,

j

those safety factors actually prevailing in the design.)

'

The contention that a direct tension load applied to a previously

torque-tightened bolt ultimately approaches the direct tension

load characteristic curve for the bolt; i.e., severely overtorqued

bolts have a tensile load reserve that will provide additional

safety against a failure should additional stress be applied by

,

i

additional strain.

(The test data referenced generally support

l

this conclusion.

However, test data limitations apparently

ignored included thread length of 9/16" within the grip rather

than the more severe 1/8" which would be applicable to the

j

majority of bolts used at plant Vogtle. The 1/8" length provided

'

the significantly more drooping curve.

Therefore, the data

i

referenced is not considered to verify the contention of strength

recovery to the direct tension characteristic for the majority of

bolts used at plant Vogtle.)

'

The contention that initial bolt preload has little effect on the

ultimate shear strength of the bolt in a connection.

(The test

data referenced generally support this conclusion. However, test

data referenced were from bolts in double sheer with both sheer

i

planes passing through the bolt shank. The test jig was designed

to keep the bolt shank in as near to pure shear as possible. No

information was offered relative to the more severe situation of

single shear through the thread root under grip conditions that

,

t

could offer prying tension.

Therefore, additional assurance is

l

needed that the more severe situation is not applicable to con-

l

nections at plant Vogtle.)

, _ . _

. _

..--

.

--

.-,. _ ._ _ . _ _ _ _ _ _.

_-

.

14

During this inspection, additional potential for overtensioning was

identified due to deviation report CD-1417 issued October 8,1981, due

to high tension values in high strength bolted connections within the

turbine building.

A total of 484 connections were inspected with 403

connections exhibiting approximately 850 ft. Ibs. of torque.

Testing

of sample bolts on a hydraulic tensioner established the tensile load

associated with this torque to be equivalent to the ASTM specified

ultimate tensile strength for the 7/8" diameter A325 bolts involved.

The bolts were installed with the calibrated impact wrench method (not

turn-of-nut method) and those methods together with identical impact

wrenches was also used for installation of high strength bolts in the

auxiliary building (levels D and C) during the same time frame.

Therefore, additional engineering justification was requested regarding

any potential long-term adverse affects (stress corrosion cracking, or

other failure mechanisms) for high strength bolts preloaded to near

ultimate tensile strength values.

Additional GPC response was transmitted by letter, dated May 12, 1986

(Log: GN-908) and NRC evaluation is not complete.

This item remains

open.

d.

(Closed) Unresolved Item (425/85-40-02, 425/85-31-02):

Assurance of

adequate backpurge for welding stainless steel piping

This item concerned the use of adequate backpurge when welding stain-

less steel piping.

During previous examinations of welding activities

on stainless steel piping, the inspector noted that oxygen analyzers

were not used to assure the 1% minimum oxygen requirement and that

welders involved were uncertain as to the required argon flow rates and

minimum oxygen required.

Further that clarifying information was not

included on some of the welding technique sheets provided to the

welders involved.

During this inspection, the inspector examined

revised technique sheets and records of additional welder training and

QC surveillance activities which were conducted to assure meeting

backpurge requirements.

The inspector observed uniform use of oxygen

analyzers and adequate backpurge for the welding activities reported in

paragraph 6.b.(1).

This item is considered closed.

4.

Unresolved Items

No unresolved items were identified during this inspection.

'

5.

Independent Inspection Effort

Housekeeping (54834B), Material Identification and Control (429028), and

Material Control (429408)

The inspector conducted a general inspection of Units 1 and 2 containments,

,

,

the control building and the reactor auxiliary building to observe activi-

l

ties such as housekeeping, material identification and control; material

control, and storage,

i

!

,.

.

15

Within the areas examined, no violations or deviations were identified.

6.

Safety-Related Piping (Unit 2)

The inspector examined welding and nonwelding activities for safety-related

piping to determine whether applicable code and procedure requirements were

being met. The applicable code for safety-related piping is the ASME Boiler

and Pressure Vessel Code,Section III,1977 Edition with Addenda through

W77. .

a.

Review of Nonwelding Quality Records (49065)

The inspector selected various safety-related piping components (e.g.,

pipe, fittings and welded-in components) for review of pertinent

records to determine conformance with procurement, storage and

installation specifications and QA/QC site procedures.

Records of the following items were selected for review to ascertain

whether they (records) were in conformance with applicable requirements

relative to the following areas: material test reports / certifications;

vendor supplied NDE reports; Nuclear Steam Service Supply quality

release; site receipt inspections; storage; installation; vendor

nonconformance reports.

Item

Heat / Control No.

System

3/4" dia. SS

S/N B7459

Safety Injection

angle globe valve

3/4" dia. SS

S/N H178 ABE

Safety Injection

SS Gate Valve

1" dia sched 160

8 8607

Chemical and Volume

SS 90 ell

Control

Within the areas inspected, no violations or deviations were identified.

b.

Welding Activities

(1) Production Welding (55050)

The inspector observed in-process welding activities of safety

injection and chemical volume and control system piping field

welds inside of containment as described below to determine

whether applicable code and procedure requirements were being met.

. .

_

_

t

.

16

The below listed welds are examined in-process to verify work

conducted in accordance with traveler, welder identification and

location, welding procedures, WPS assignment, welding technique

and sequence, materials identity, weld geometry, fit-up; temporary

attachments, gas purging, preheat, electrical characteristics,

shielding gas, welding equipment condition, interpass temperature,

interpass cleaning, process control systems, qualifications of

inspection personnel, and weld history records.

ISO

Weld

Size

Status

2K4-1208-015-02 R/1

112-W-115

1"

Final Pass

112-W-109

1"

First Pass

2K4-1204-030-02 R/3

034-W-109

2"

Root Pass

030-W-136

3/4"

Final Pass

030-W-137

3/4"

Final Pass

030-W-140

3/4"

Second Pass

The following inspector qualification status records and QA/QC

Inspector Qualification / Certification records were reviewed

relative to inspection of the weld joints listed above.

Inspector

Type of Certification

PEM-PPP

VT-II

MSG-PPP

VT-II

(2) Welding Procedures

Welding procedure specifications (WPS) applicable to the weld

joints listed in paragraph 6.b.(1) were selected for review and

comparison with the ASME code as follows:

Procedure Qualification

WPS

Process

PQR Reports

1/

29-111/1-8-08-1

GTAW

125,132,133

(9/7/83)

l

38-111/1-KI-1

GTAW

120,121

(12/6/85)

l

l

l

- - - , ,

~l

.

17

General welding standard BWS-111/1 (4/15/85)

1/ GTAW - Gas Tungsten ARC-Welding

The above WPSs and their supporting Procedure Qualification

Records (PQRs) were reviewed to ascertain whether essential,

supplementary and/or nonessential variables, including thermal

treatment, were consistent with Code requirements; whether the

WPSs were properly qualified and their supporting PQRs were

accurate and retrievable; whether all mechanical tests had been

performed and the results met the minimum requirements; whether

the PQRs had been reviewed and certified by appropriate contractor /

licensee personnel; and whether essential were noted.

WPSs are

qualified in accordance with ASME Section IX, the latest edition

and addenda at the time of qualification.

(3) Welder Performance Qualification

The inspector reviewed the PPP program for qualification of

welders and welding operators for compliance with QA procedures

and ASME Code requirements.

The following welder qualification status records and " Records of

Performance Qualification Test" were reviewed relative to the weld

joints-listed in paragraph 6.b.(1).

Welder Symbol

WPS

FV

29-III/I-8-0B-1

CZ1

38-III/I-8-KI-1

(4) Welding Filler Material Control

The inspector reviewed the PPP program for control of welding

materials to determine whether materials were being purchased,

accepted, stored and handled in accordance with QA procedures and

applicable code requirements.

The following specific areas were

examined.

-

Purchasing, receiving, storing, and distribution and handling

procedures; material identification; and inspection of

welding material issuing stations.

-

Welding material purchasing and receiving records for the

following material applicable to current production welding

were reviewed for conformance with applicable procedures and

code requirements.

.

. . . .

--

-

.

18

Tyge

Size

Heat, Lot, Batch /No.

ER308L

1/16" X 36"

26245

ER308L

3/32" X 36"

05394

ER308L

1/8" X 36"

P0443

E309L-16

5/32" X 14"

X45602

During the above inspection, the inspector observed apparent

documentation deficiencies for E309L electrodes stored in the

"doublewide" welding materials distribution center (WMDC).

The

covering of these electrodes were not marked with heat, lot, or

control number and the inspector requested documentation which

independently verified that the electrodes involved were from heat

X45602 as was indicated on the stationary holding oven door. WMDC

personnel informed the inspector that the electrodes involved had

been received via GPC bulk materials requisition for on-site

vendor use to complete repair of ASME code valves (maintenance

work order 12607258) (50.55(e) item 424/425 CDR 85-90).

The

inspector reviewed requisition No. 221686 (dated April 26,1986)

for conformance to PPP procedure VIII-3 " Control of Welding

Consumables" dated February 27, 1985, and GPC procedure MD-T-12"

Receipt Inspection and Storage / Issue of Pipe, Pipe Components, and

Weld Filler Material" dated June 21, 1985. The inspector observed

that requisition No. 221686 did not conform to requirements in

that it did not:

Include "N/A" in the Unit No., Drawing No., Rev., System No.,

Project Class and Material Class spaces

Include the authorized signature for the owners welding

section supervisor, or his designee in the " approved by"

space

Include an "N/A" in the GPC "QC Inspection" space

Include the signature of a contractor's Q.C. representative

in the "Q.A. Appr. Doc." space

Include the Purchase Order No.; Item No.; or Heat, Lot, or

Control No.

The inspector informed cognizant licensee personnel that the above

deficiencies were considered a lack of conformance to 10 CFR 50

Appendix B, Criterion V, and would be identified as Violation

424/86-39-03, 425/86-19-03, Failure to Follow Procedures for

Control of Welding Consumables.

.

_

_-

__

_

'

.

19

7.

Previously Identified Inspector Followup Items

a.

(Closed) Inspector Followup Item (424,425/85-14-01):

Clarification of

Liquid Penetrant Inspection Procedure

This item concerned required minimum light intensity at the inspection

site under PPP procedure IX-PT-1-W77.

Cognizant licensee personnel

informed the inspector that all PPP NDE Technicians were aware of the

illumination / lighting requirements to perform penetrant examination to

ASME Section V requirements.

Further, that all technicians were

supplied flashlights to aid in inspections.

Followup discussion with

NDE technicians confirmed that flashlights are universally used for

penetrant inspections in the field. This item is considered closed,

b.

(Closed) Inspector Followup Item (424/85-40-01, 425/85-39-01):

Assurance of Necessary Minimum Clearances for Installed Piping

This item concerned need for assurance of minimum clearances between

installed piping and Unit I containment pipe racks.

There appeared to be potential for contact between the 12" X 12" X 6"

Reducing Tee in Reactor Coolant Line 1K4-1201-036-01 and the top of

column 8 in Rack R0001.

The inspector reviewed revisions to PPP

Procedure 1 X 3 which require a general minimum separation of 1" in the

direction of the obstruction from installed piping. The inspector also

observed completed modifications to the top of column 8 in Rack R0001

to obtain adequate separation from Line 1K4-1201-036-01. The inspector

also completed random inspection on Unit 1 containment and no potential

clearances less than 1" were identified.

This item is considered

closed.

1

.

_ - - _ _

-

_

--

-

ATTACHMENT

'

1

1

'

NRC ENFORCEMENT CONFERENCE

JUNE 23, 1986

^

AGENDA

.

INTRODUCTION

R. E. CONWAY

.

BACKGROUND

P. D. RICE

.

-

AIPB CONCEPT

CHRONOLOGY

-

DISCUSSION OF PROBLEM

P. D. RICE

.

-

EVALUATION

-

ERROR IN PROJECT PROPOSAL

-

ROOT ~CAUSE

CORRECTIVE ACTIONS

P. D. RICE

'

.

i

l

l

CONCLUSIONS

P. 9. RICE

.

l

CLOSING REMARKS

R. E. CONWAY

.

R. E. CONWAY - SENIOR VICE PRESIDENT AND PROJECT DIRECTOR

P. D. RICE - VICE PRESIDENT PROJECT ENGINEERING

l

l

1

l

l

_

,

_

_

_

_

- _ _ . . , . , _ . .

- - _ - - - - - - . _ _

- --

.

.

ARBITRARY INTERMEDIATE PIPE BREAK (AIPB) CONCEPT

DEFENSE IN-DEPTH CONCEPT FOR EVENTS UNANTICIPATED IN DESIGN

,

POSTULAT!0N OF BREAK POINTS IN HIGH-ENERGY PIPING SYSTEMS

.

WHEN ACTUAL STRESSES ARE BELOW ALLOWABLE STRESSES

,

NRC AND INDUSTRY AGREEMENT IN PRINCIPLE THAT EXISTING

.

DESIGN FLATURES AND CONSERVATISMS ACCOMPLISH THE DEFENSE

IN-DEPTH OBJECTIVES

COORDINATED INDUSTRY AND NRC EFFORTS HAVE JUSTIFIED THE

.

ELIMINATION OF THIS REQUIREMENT FOR A NUMBER OF PLANTS

i

i

2

--.

__

.

-.

.

._.

.

.

.

.

CHRONOLOGY

Nov '83

GPC LETTER TO NRC PROPOSING ELIMINATION OF ARBITRARY

INTERMEDIATE PIPE BREAKS (AIPB)

.

MAR '84

GPC MEETING WITH NRC ON NOVEMBER, 1983 LETTER

APR '84

GPC LETTER PROVIDING ADDITIONAL JUSTIFICATION FOR

NOVEMBER, 1983 LETTER AND RESPONDING TO MARCH, 1984

MEETING

JUN '84

BPC COMMENCED REVIEW OF AIPB FOR COMPLETENESS IN

ANTICIPATION OF NRC APPROVAL OF GPC PROPOSALS AND IN

PREPARATION FOR FSAR CHANGE

JUN '84

NRC LETTER APPROVED DEVIATION FROM STANDARD REVIEW PLAN

TO USE ALTERNATIVE AIPB CRITERIA

JUL '84

BPC COMPLETED REVIEW STARTED IN JUNE, 1984

l

-

.

-

.

l

AuG '84

FSAR CHANGED TO INCORPORATE JUNE, 1984 NRC APPROVED

CHANGES

I

3

.

_

..

.

.

-

-

.

.

,

.

ARBITRARY INTERMEDIATE PIPE BREAKS

EXCERPTS FROM APRIL 24, 1984, GPC LETTER TO NRC

ATTACHMENT

A,

TECHNICAL JUSTIFICATION FOR ELIMINATION OF

ARBITRARY INTERMEDIATE BREAKS, STATES:

"2.

WELDED ATTACHMENTS ARE NOT LOCATED IN CLOSE PROXIMITY TO

THE BREAKS TO BE ELIMINATED.

CONSEQUENTLY, LOCAL

BENDING STRESSES RESULTING FROM THESE ATTACHMENTS WILL

NOT SIGNIFICANTLY AFFECT THE STRESS LEVELS AT THE BREAK

LOCATIONS (REFER TO ATTACHMENT E)."

ATTACHMENT

E,

PROVISIONS FOR MINIMIZING LOCAL STRESSES FROM

WELDED ATTACHMENTS, STATES:

"WE HAVE REVIEWED ALL ARBITRARY INTERMEDIATE BREAK

LOCATIONS TO BE ELIMINATED AND HAVE DETERMINED THAT IN

NO CASES ARE WELDED ATTACHMENTS CLOSER THAN FIVE PIPING

DIAMETERS FROM POSTULATED BREAK LOCATIONS.

AT THIS

DISTANCE, LOCAL BENDING STRESSES INDUCED BY THE ATTACHMENT

WILL NOT AFFECT THE STRESSES AT THE POSTULATED BREAK POINT.

TO ENSURE THAT THIS IS THE CASE, THE LOCAL STRESSES HAVE

BEEN DETERMINED AND ADEED TO THE PRIMARY STRESS REPORT."

,

.

_.

._

-

.

_

__ _

-

.

,

CHRONOLOGY, CONT'D

APR '85

GPC LETTER REQUESTING ELIMINATION OF AIPB IN MAIN

FEEDWATER SYSTEM

JuN '85

NRC LETTER APPROVED APRIL, 1985 GPC MAIN FEEDWATER

'

SYSTEM PROPOSAL

MAR '85

READINESS REVIEW IDENTIFIED LACK OF UPDATE OF DESIGN

CRITERIA IN REGARD TO ELIMINATION OF AIPB CRITERIA

DEC '85/

NRC INSPECTIONS IDENTIFIED PROBLEMS IN IMPLEMENTATION OF

APR '86

ALTERNATIVE AIPB CRITERIA

APR '86

GPC REVIEW OF CURRENT HIGH STRESS POINTS TO DETERMINE

THOSE POINTS WITHIN SD OF A WELDED ATTACHMENT

MAY '86

GPC LETTER TO NRC DOCUMENTING APRIL, 1986 REVIEW AND

DEFINING FURTHER ACTIONS

MAY '86

GPC REVIEW OF HIGH STRESS POINTS AS PROMISED IN MAY,

1986 LETTER

JUN '86

GPC AND NRC MEETING TO DISCUSS RESULTS OF MAY, 1986

REVIEW AND TO DEFINE FURTHER ACTIONS

ACTIONS CONTINUE TO ADDRESS TECHNICAL ISSUES.

GPC

PREPARING RESPONSE TO NRC ON QUESTIONS AND ACTIONS

DEFINED IN JUNE 1986 MEETING

5

.

.

_

- .

_. .

. - - -

_ . _ , _

-. _

-

.

I

DISCUSSION OF PROBLEM

,

,

EVALUATION

.

ERROR IN PRO.!ECT PROPOSAL

.

ROOT CAUSE

.

6

,

_

-

..

,

.

EVALUATION OF PROBLEM

CONDUCTED REVIEW FOR APPLfCABLE DOCUMENTATION

.

INTERVIEWED PERSONNEL INVOLVED

.

,

PERFORMED REREVIEW OF ARBITRARY INTERMEDIATE PIPE BREAK

.

(AIPB) LOCATIONS BASED ON MARCH, 1984 DESIGN DOCUMENTS AND

CRITERIA

-

,

t

l

l

l

_ _ _ - - .

-

.

. -

_ _ _ . . _ - . _ -

__ -_ . _ . _ _ - _ - _ - - _ _ - - _ _ _

- - - - _ .

- -

-

- - -

-

- -

-

-

.

i

.

ERROR IN PROJECT PROPOSAL

BASELINE DATA (NOVEMBER 1983 GPC LETTER)

,

576 TOTAL PIPE BREAK LOCATIONS

-

-

182 ARBITRARY INTERMEDIATE PIPE BREAKS (AIPB)

-

233 TOTAL PIPE WHIP RESTRAINTS

-

110 PIPE WHIP RESTRAINTS FOR AIPB

ERROR (JUNE 1986 ENGINEERING REVIEW)

,

-

18 CASES WHERE WELDED ATTACHMENTS WERE WITHIN SD OF

BREAK POINT

-

11 CASES IN MAIN STEAM SYSTEM

-

3 CASES IN MAIN FEEDWATER SYSTEM

-

2 CASES IN CHEMICAL AND VOLUME CONTROL SYSTEM

-

1 CASE IN STEAM GENERATOR WET LAY-UP SYSTEM

-

1 CASE IN AuxrLIARY FEEDWATER SYSTEM

i

l

8

_ . - .

.-.

-

. . . - . . . .

..

-

-- ._ _ . - . .

-

-

. - -

-.

. _ .

.

.

.

&

ROOT CAUSE

,

QA PROGRAM WEAKNESS

LACK OF FORMALITY IN DOCUMENTING THE SCOPE, CRITERIA,

.

DETAILED RESULTS, AND SUPERVISORY REVIEWS ASSOCIATED WITH

THE SD REVIEW

TIMELINESS OF IDENTIFICATION

,

FAILURE TO INCORPORATE PROPOSED SD PROVISION INTO

.

ENGINEERING DESIGN CRITERIA

0A AUDITS BASED PRIMARILY ON COMMITMENTS INCORPORATED

.

INTO PROJECT DESIGN DOCUMENTS

i

!

l

,

!

l

9

,.

,

.

.

CORRECTIVE ACTIONS

REVIEW PROJECT AND NRC CORRESPONDENCE RELATED TO

.

ELIMINATION OF ARBITRARY INTERMEDIATE PIPE BREAK (AIPB) FOR

,

ANY SIMILAR ISSUES

0A AUDITED SELECTED PAST ENGINEERING / LICENSING

.

CORRESPONDENCE TO NRC FOR SIMILAR PROBLEMS

0A AUDIT PROCEDURES STRENGTHENED TO EXAMINE FOR PROPER

.

INCORPORATION OF COMMITMENTS MADE IN NRC CORRESPONDENCE

DESIGN CRITERIA REVISED TO REFLECT CURRENT APPROVED STATUS

.

(IMPLEMENTATION ON HOLD PENDING RESOLUTION OF TECHNICAL

ISSUE WITH NRC)

ACTION INITIATED TO STRENGTHEN PROJECT PROCEDURES FOR

.

OFF-NORMAL ENGINEERING REVIEWS

PROJECT POLICY FROCEDURES WHICH CONTROL CORRESPONDENCE TO

,

NRC REVISED TO STRENGTHEN PERSONNEL ACCOUNTABILITY FOR

ACCURACY

l

TRAINING PRESENTATION DEVELOPED AND SCHEDULED FOR

.

ENGINEERING PERSONNEL TO INCLUDE ENGINEERING PROCEDURE

CHANGES AND SENSITIVITY

l

TRAINING SEMINAR DEFINED FOR PROJECT MANAGERS WHO PREPARE

.

.

OR APPROVE REGULATORY CORRESPONDENCE

LETTER TO NRC IN PREPARATION ON PROPOSED AIPB CONCEPT

.

10

.- -

. _ .

-.

-.

.__

. _ . __

_ . -

'

,

e

.

V0GTLE MANAGEMENT PHILOSOPHY

READINESS REVIEW

'

.

.

CONTINUED EMPHASIS ON PROJECT POLICY IRAINING

.

QUALITY CONCERN PROGRAM

.

ANTI-DRUG PROGRAM

.

_

SENIOR CORPORATE INVOLVEMENT (PROJECT MANAGEMENT BOARD,

.

QUALITY ASSURANCE COMMITTEE AND READINESS REVIEW BOARD)

'

NUMEROUS TECHNICAL ASSESSMENTS (3 INP0 CONSTRUCTION

.

ASSESSMENTS, SELF-INITIATED EVALUATION AND DESIGN CONTROL

REVIEW)

CONTINUING ENHANCEMENTS TO PROJECT MANAGEMENT 0RGANIZATION

.

OPENNESS IN DEALINGS WITH NRC

.

11

. .

.

.. _

-

.

.

-_

--

'

.

~

v

f.

.

CONCLUSIONS

,

WEAKNESS IN QA PROGRAM FOR OFF-NORMAL REVIEWS -

.

LACK OF FORMALITY IN DOCUMENTING THE SCOPE, CRITERIA,

DETAILED RESULTS, AND SUPERVISORY REVIEWS ASSOCIATED WITH

THE SD REVIEW

CONTINUING DIALOGUE BETWEEN GPC AND NRC IS EXPECTED TO

.

SATISFACTORILY RESOLVE TECHNICAL ISSUE

GPC HAS AND WILL CONTINUE TO DEAL WITH ALL ISSUES IN AN

,

OPEN AND FACTUAL MANNER.

i

12

.

,,

- , ,

- - , -

- - -

,,.

., -

y

-,

,n.

. - - - , - - - ,

--- -

- ----