Final Deficiencty Rept CDR 84-00-13 Re Portions of Control Circuits Not Considered When Evaluating Total Circuit Length for Voltage Drop Calculations.Initially Reported on 840830. Independent Review Confirms Corrective Actions Completed
ML20204H148
Person / Time
Site: Seabrook  NextEra Energy icon.png
Issue date: 10/14/1988
From: George Thomas
PUBLIC SERVICE CO. OF NEW HAMPSHIRE
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
CDR-84--13, CDR-84-00-13, NYN-88137, NUDOCS 8810240335
Download: ML20204H148 (2)


Text

_ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _

,. ... 1 George S. Thomas Vice President Nuclear Production UI NYN-88137 October 14, 1988 P25c Service of New Hampshire New Hampshire Yankee Division United States Nuclear Regulatory Commission Washington, DC 20555 Attention: Document Control Desk

References:

a) Facility Operating License No. NPF-56, Construction Permit CPPR-136, Docket Nos. 50-443 and 50-444 b) PSNH Letter SBN-709, dated August 30, 1984, ' Interim 10CFR50.55(e) Report: Control Circuit Cable Lengths,'

J. DeVincentis to R. W. Starostecki c) PSNH Letter SBN-737, dated December 6, 1984, ' Interim 10CFR50.55(e) Report: Control Circuit Cable Lengths,'

J. DeVincentis to R. W. Starostecki d) PSNH Letter SBN-826, dated June 17, 1985, ' Final 10CFR50.55(e)

Report: Control Circuit Cable Lengths,' J. DeVincentis to R- W. Starostecki

~

e) PSNH Letter SBN-1071, dated May 28, 1986, ' Final 1,0CFR50.55(e)

Report: Control Circuit Cable Lengths " J. DeVir.centis to R. W. Starostecki f) PSNH Letter NYN-87130, dated November 12, 1987, ' License Event Report (LER) No. 87-019-00: Failure of Gould/Telemecanique J '.0 Relays' g) PSNH Letter NYN-87134, dated November 20, 1987, ' Revision to 10CFR50.55(e) Report: Control Circuit Cable Lengths (CDR 84-00-13),' G. S. Thomas to W. T. Russell h) PSNH Letter NYN-88074, dated May 24, 1988, ' Control Circuit Cable Lengths (CDR 84-00-13),' G. S. Thomas to W. T. Russell

Subject:

Completion of Corrective Action Regarding Control Circuit Cable Longths (CDR 84-00-13)

Gentlemen Reference (b) reported that portions of control circuits were not considered in certain cases when evaluating total circuit length for voltage i drop calculations. Reference (h) identified that less than the minimum specified voltage could exist under certain conditions for Westinghouse contactors on the hydrogen recombiner skids. Subsequently the control circuits for hydrogen recombiners CGC-MM-284A and CGC-MM-284B have been modified to ensure that greater than the minimum specified voltage will be present during the concurrent conditions of low grid voltage and a fully loaded electrical bus.

8710240335 881014 PDR ADOCK 05000443 p

S PDC i 4

P.O. Box 300. Seabrook. NH 03874 . Telephone (603) 474 9574

l , . s . . 's l

Unit d Statss.Nuclocr Regulctory Commission OctobIr 14, 1988 Attentien Document Control. Desk Pegs 2

~

l l

t This completes all corrective actions associated with safety related control circuit cable lengths that have been tracked by CDR 84-00-13. An independent review also confirms that corrective actions have been completed.

Should you have any questions regarding this information, please contact Mr. John G. Tefft at (603) 474-9521, extension 4039.

Very truly yours, 7

George S. Thomas cc: Mr. William T. Russell Regions 1 Administrator Region I United States Nuclear Regulatory Commission 475 Allendale Road King of Prussia PA 19406 Mr. David G. Ruscitto NRC Senior Resident Inspector P. O. Box 1149 Seabrook, NH 03874 i