Forwards IE Insp Rept 50-364/78-16 on 781017-20.No Noncompliance Noted
ML20204D220
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 11/15/1978
From: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Barton A
ALABAMA POWER CO.
Shared Package
ML20204D216 List:
References
NUDOCS 7812110309
Download: ML20204D220 (2)


See also: IR 05000364/1978016

Text

_ _ - - _ _ _ _ ~ _ _ __

. .

UNITED ST ATES

4

[g* MCoq(o g

NUCLEAR REGULATORY COMMISSION

RE GION il

{

- -

., g

'g E 101 M ARIETT A ST REET .N.W.

ATLANT A, GEORGI A 30303

o, - [

%, ' % .- gr

in Reply Refer To:

R11:MDH

50-364/78-16

Alabama Power Company

Attn: Mr. A. R. Barton

Executive Vice President

Post Office Box 2641

Birmingham, Alabama 35291

Gentlemen:

This ref ers to the inspection conducted by Mr. M. D. Hunt of this of fice

on October 17-20, 1978, of activities authorized by NRC Construction

Permit No. CPPR-86 for the Joseph M. Farley Unit 2 facility, and to the

discussion of our findings held with Mr. J. A. Mooney at the conclusion <

of the inspection.

Areas examined during the inspection and our findings are discussed in

, the inspection

the enclosed inspection report. Within these a.

consisted of selective examinations of procedures and representative

records, interviews with personnel, and observations by the inspectors.

Within the scope of this inspection, no items of noncompliance were

disclosed.

We have examincd actions you have taken with regard to previously

reported unresolved items. The status of these items is discussed in

the enclosed report.

l In accordance with Section 2.790 of the NRC's " Rules of Practice",

Part 2, Title 10, Code of Federal Regulations, a copy of this Ictter

and the enclosed inspection report will be placed in the NRC's Pub 1.ic

' Document Room. If this report contains any information that you (or

your contractor) believe to be proprietary, it is necessary that you

make a written application within 20 days to this office to withhold

such information from public disclosure. Any such application must is

include a full statement of the reasons on the basis of which it

claimed that the information is proprietary, and should be prepared

so that proprietary information identified in the application is

contained in a separate part of the document. If we do not hear

f rom you in this regard within the specified period, the report

will be pla:ed in the Public Document Room.

7 812110 3 de/

- - - - - - - - - -_ _ _ _ _ _ , _ _

- _ _ - _ _ _ _ _ _ _ _ _ _ _ . _ .

d

. .

NOV 151978

.

Alabama Power Company -2-

Should you have any questions concerning this letter, r; will be glad

to discuss them with you.

Sincerely,

, f '/( !

.-

! / / .

/ ' ' ',7

.- -

C. E. Murphy, Chfef

Reactor Construction and

Engineering Support Branch

Enclosure: Inspection Report No.

50-364/78-16

cc w/ encl:

Mr. R. E. Hollands, Jr. , QA Supervisor

P. O. Box U

Ashford, Alabama 36312