Monthly Operating Repts for Feb 1999 for Catawba Nuclear Station,Units 1 & 2
ML20204C911
Person / Time
Site: Catawba  Duke Energy icon.png
Issue date: 02/28/1999
From: Robert Williams
DUKE POWER CO.
To:
Shared Package
ML20204C908 List:
References
NUDOCS 9903240016
Download: ML20204C911 (6)


Text

Operating Data Report Docket No. 50-413 Date March 11.1999

, , Completed By Rocer Williams Telephone 704-382-5346 Operating Status

1. Unit Name: Catawba 1
2. Reporting Period: February 1,1999-February 28, 1999
3. Licensed Thermal Power (MWt): 3411 Notes:
  • Nameplate
4. Nameplate Rating (Gross MWe): 1305
  • Rating (GrossMWe)
5. Design Electrical Rating (Net Mwe): 1145 calculated as 1450.000
6. Maximum Dependable Capacity (Gross MWe): 1192 MVA * .90 power
7. Maximum Dependable Capacity (Net MWe): 1129 factor per Page ill, NUREG-0020.
8. If Changes Occured in Capacity Ratings (Items Number 3-7) Since Last Report, Give Reasons:
9. Power Level To Which Restricted, if Any (Net MWe):
10. Reason for Restrictions,If any:

This Month YTD Cumulative

11. Hours in Reporting Period 672.0 1416.0 119833.0
12. Number of Hours Reacter was Critical 672.0 1416.0 95626.6
13. Reactor Reserve Shutdown Hours 0.0 0.0 0.0
14. Hours Generator On-Line 672.0 1416.0 94204.8 15 Unit Reserve Shutdown Hours 0.0 0.0 0.0
16. Gross Thermal Energy Generated (MWH) 2281608 4815461 309073665
17. Gross Electrical Energy Generated (MWH) 821482 1732527 109467664
18. Net Electrical Energy Generated (MWH) 780211 1645664 103088031
19. Unit Service Factor 100.0 100.0 78.6
20. Unit Availability Factor 100.0 100.0 78.6
21. Unit Capacity Factor (Using MDC Net) 102.8 102.9 76.0
22. Unit Capacity Factor (Using DER Net) 101.4 101.5 75.1
23. Unit Forced Outage Rate 0.0 0.0 7.2 i
24. Shutdown Scheduled Over Next 6 Months (Type, Date and Duration of Each)

I

25. If Shutdown At End Of Repw. Period, Estimated Date of Startup
26. Units in Test Status (Prior to Commercial Operation)

Forcast Achieved initial Criticality Initial E'ectricity Commercial Operation

~

9903240016 990315 PDR ADOCK 05000413 R PDRt

_ 1 f

o 1

e ,

g - .

a ,

P e

c n m e a r

_ r r c u S

/

c ip n e r o R T ita nu t

n l a

e ui v n n t e a r o P

o MC - -

t n 2 4 i

o t

c m

_ A a r

_ e c v S i

/)

t c i pn e ri r

r Tl a p o itcx C d l aE d o a n

a ht u n tm oeh (r

_ e e a ut s

u a

MMAO

) - - -

9 C 2 9 ( 1 35 9 t 1 r

. d o p

y e s e .

S r a nR o N u r

e c n N t

W b e

Li e v O F E D  :

I H ht U T f o/ X n n N o H O d R o n i o

S M he w M t a

n T

t T o e i I

R Md t h m a

N O

)

2 h u t r x U E P ( S o e E f s )

R n n e i a

c n s i l p

o s e L

/ x a g g E e a n ( )

R t in e r n

) u iai v roi a 1

( O r T aE t

r p x rl r t r oi s oE(

n t a n a r t

o s r ir e i r t

a o u o e pd pt meh r

uH N OA OO D

9 s EFGH 9 m 6 d 9

1 a 4 d l e

't i

l 3 5-e u 5

. l i e cr d a1 W 8 2 p o e )

3 b yF h c n 1 w hc r e 3- T - S i

a 4- a r r l a a o 40 t

F - p 0

5 CMR7 S E

(

x t

s n

o e

it OEEYE eT c NMTBN A  :

r lu r i

t r

O e ia o s

e TA EN DD H t a f e r

- K CIT ON EP TE EL LE D

y n o p t t

n n e

meli c

a nnt o gr a

el u y

DU L P T r a s n a qiu iafeg e u _

m e RE MRR M o _

O N m u ) - - - -

C 1

ABCD S (

i -

. MONTHLY REFUELING INFORMATION REOUEST i

1. Facility name: Catawba Unit 1
2. Scheduled next refueling shutdown: Aoril 1999
3. Scheduled restart following refueling: May 1999 l

THE PROJECT MANAGER HAS BEEN ADVISED BY SEPARATE COMMUNICATION OF i ANY T.S. CHANGE OR LICENSE AMENDMENT. THEREFORE, QUESTIONS 4 l THROUGH 6 WILL NO LONGER BE MAINTAINED IN THIS REPORT.  !

4. Will refueling or resumption of operation thereafter require a technical specification change or i other license amendment? I If yes, what will these be?

If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions?

5. Scheduled date(s) for submitting proposed licensir.g action and supporting information.
6. Important licensing considerations (new or different design or supplier, unreviewed design or performance analysis methods, significant changes in design or new operating procedures).
7. Number of Fuel assemblies (a) in the core: 121 j (b) in the spent fuel pool: 294
8. Present licensed fuel pool capacity: 1413.

Size of requested or planned increase: =

9. Projected date of last refueling which can be accommodated by present license capacity: l November 2009 i

i i

DUKE POWER COMPANY DATE: March 15.1999 j Name >fContact: R. A. Williarm Phone: (704b 382-5346 l

i i

+

Operating Data Report l

l Docket No.10-414 Date March 11.1999

, Completed By Bocer Williams Telephone 704-382-5346 l

Operating Status l

1. Unit Name: Catawba 2
2. Reporting Period: February 1,1999-February 28, 1999 l 3. Licensed Thermal Power (MWt): 3411 Notes:
  • Nameplate
4. Nameplate Rating (Gross MWe): 1305
  • Rating (GrossMWe)
5. Design Electrical Rating (Net Mwe): 1145 calculated as 1450.000
6. Maximum Dependable Capacity (Gross MWe): 1192 MVA * .90 power
7. Maximum Dependable Capacity (Net MWe): 1129 factor per Page lil,
8. If Changes Occured in Capacity Ratings (Items Number 3-7) Since Last Report, Give Reasons:
9. Power Level To Which Restricted, If Any (Net MWe):
10. Reason for Restrictions,If any:

This Month YTD Cumulative

11. Hours in Reporting Period 672.0 1416.0 109849.0 1
12. Number of Hours Reactor was Critical 672.0 1416.0 89143.1
13. Reactor Reserve Shutdown Hours 0.0 0.0 0.0
14. Hours Generator Or Line 672.0 1416.0 87868.9
15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
16. Gross Thermal Energy Generated (MWH) 2288839 4753509 286303444
17. Gross Electrical Energy Generated (MWH) 829505 1720275 101775981
18. Net Electrical Energy Generated (MWH) 789143 !635650 96037270 q
19. Unit Service Factor 100.0 100.0 80.0 l
20. Unit Availability Factor 100.0 100.0 80.0 j
21. Unit Capacity Factor (Using MDC Net) 104.0 102.3 77.3 l
22. Unit Capacity Factor (Using DER Net) 102.6 100.9 76.4 l
23. Unit Forced Outage Rate 0.0 0.0 7.5
24. Shutdown Schedule i Over Next 6 Months (Type, Date and Duration of Each) f i

1

25. If Shutdown At End Of Report Period, Estimated Date of Startup
26. Units in Test Status (Prior to Commercial Operation)  !

l Forcast Achieved "

Initial Criticality Initial Electricity Commercial Operation

1 9

_ f 9 o /

s t

1 /

3 e -

g e c a ,

3 P

e c m n a e

r r

c r S u /

p n c

R e ir ito t T au n l a n e ui v n t er a n o P

o MC - -

t n 2 4 i

o t

c m A a r

e c v S i

t /)pn

-- i r ri u Tl ap o

C ic x o a aE t

d l d

n ht u m (r a

e n oe e a ut t h

s u

a MMAO

) - - -

9 C 2 9 ( 1 35 9 t 1 r y

. de p o S r s e .

a nR o N u r

e c n Nt W b e

i L ev O F E D  :

T H ht U T fo/X n n N o o H O d R o n i S M he w t M t a

n I'

T o e i I

R Md h m a

N O

)

2 h t

u t r x U P ( S o E e

E f s )

R n n e i a

n c o s i L lp s e g / x a g E e a n ( )

R t u in r n

) ia v e roi a 1

( O r T aE it rl r r p x r

oi s t

oE(

n t a irn t

a r o s r e i r t

a u o e pd meh pt r o u H N OA OO D - - - -

9 EFGH 9 d 9

1 Jm6 ia4 d l e

2 .

l l

3 5-e u 5 i e cr d a 1 Wr 2 p o e )

4 b h 8 yF h c n 1 w e 3- T i 4- ta c r g - S a 0 a a o 0 4 F - l p

5CMR7 S

E

(

x t

s i n

o OEEYE e r T e t c

NMTBNO  :

luo r i

t r

TA A H e i s EN DD t

a fa e e

r K EP D c y CIT t

TE n e na gro ON L EL  :

y n o pmel el n inta DU L E r t n u ug P T a s a

e q iuiaf e e o

m M N m R E MRR O u ) - - - -

C S 1

( ABCD

r' .

MONTHLY REFUFI ING INFORMATION REOUEST 1, Facility name: Catawba Unit 2

2. Scheduled next refueling shutdown: March 2000
3. Scheduled restart following refueling: April 2000 THE PROJECT MANAGER HAS BEEN ADVISED liY SEPARATE COMMUNICATION OF ANY T.S. CHANGE OR LICENSE AMENDMENT. THEREFORE, QUESTIONS 4

. THROUGH 6 WILL NO LONGER BE MAINTAINED IN THIS REPORT.

4. Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?

If yes, what will these be?

If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions?

5. Scheduled date(s) for submitting proposed licensing action and supporting information.
6. Important licensing considerations (new or different design or supplier, unreviewed design or performance analysis methods, significant changes in design or new operating procedures).
7. Number of Fuel assemblies (a) in the core: .191 j (b) in the spent fuel pool: 684
8. Present licensed fuel pool capacity: 1418 Size of requested or planned increase: =
9. Projected date of last refueling which can be accommodated by present license capacity:

May 2012 DUKE POWER COMPANY DATE: March 15.1999 Na'v. of

Contact:

R. A. Williams Phone: (704)- 382-5346

(

I I-i l: