ML20203N365

From kanterella
Jump to navigation Jump to search
Suppl 1 to Special Rept 2-SR-86-008:on 860331,condenser Evacuation Sys high-range Monitor RU-142 Inoperable for More than 72 H Due to Failure of low-range Monitor RU-141. Caused by Moisture Trapped in Process/Sample Flow Media
ML20203N365
Person / Time
Site: Palo Verde Arizona Public Service icon.png
Issue date: 09/07/1986
From: Haynes J
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Martin J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
2-SR-86-008, 2-SR-86-8, ANPP-00041-JGH, ANPP-41-JGH, NUDOCS 8609230349
Download: ML20203N365 (2)


Text

R Arizona Nuclear Power Project '#if '

P O. Box 52034 e PHOENIX ARIZONA 85072-2034 g/

0l' September 7, 1 9, !h ANPP-00041-JGH/TDS/dSPg 96.03 Mr. John B. Martin, Regional Administrator Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Region V 1450 Maria Lane, Suite 210 Walnut Creek, CA 94596-5368

Subject:

Palo Verde Nuclear Generating Station (PVNGS)

Unit 2 Docket No. STN 50-529 (License NPF-51)

Special Report-2-SR-86-008 File: 86-020-404

Dear Mr. Martin:

The attached supplement 01 to Special Report (2-SR-86-008) is submitted to provide additional information subject to the requirements of Technical Specifications 3.5-13 and 6.9 2.

If you have any questions, please contact T. R. Bradish, Compliance Supervisor at (602)932-5300 Ext. 6936.

Very truly yours, Y

J. G. Haynes Vice President Nuclear Production JGH/ ESP /dh Attachment ec: 0. M. DeMichele (all w/a)

E. E. Van Brunt, Jr.

R. P. Zimmerman A. L. Hon E. A. Licitra A. C. Gehr h

dg INPO Records Center I l 8609230349 860907 PDR ADOCK 05000529 S PDR

~

PALO VERDE NUCLEAR GENERATING STATION UNIT 2 Supplement to Special Report No. 2-SR-86-008 RADIATION MONITORING UNIT NOT RESTORED TO OPERABLE STATUS WITHIN 72 HOURS Docket No. STN 50-529 License No. NPF-51 m

This supplement to Special Report No. 2-SR-86-008 provides updated information on the event of March,1986, in which Radiation Monitoring Unit RU-142 was declared inoperable and subsequently exceeded Action Statement 42b of Palo Verde Unit 1 Technical Specification, Table 3.3-13 The Condensor Evacuation System High Range Radiation Monitor RU-142 was declared inoperable on March 31, 1986, due to spurious high and alert radiation alarms. Coincident spurious detector failure alarms caused RU-141 to be declared INOPERABLE. Since RU-141 supplies the sample. flow to RU-142, RU-142 was also declared INOPERABLE. A work authorizing document was issued to troubleshoot the cause of the alarms and to repair the radiation monitor as appropriate. At 1710 on March 31, 1986,'the 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> Action Statement for.

operability of the monitor was exceeded.

The initiation of the Preplanned Alternate Sampling Program (PASP) of Technical Specification 6.16 may be used as a compensatory measure during the inoperability of RU-142, to monitor the appropriate parameter (s) when necessary. However, since no source term is present at this time, implementation of the PASP was not required.

The root cause of this event was determined to be moisture trapped in the process / sample flow media, causing sample flow filter clogging from the condensor air removal system. To address the root cause, a moisture trap was.

installed in the monitor line under work order 143916. The radiation monitor was declared' OPERABLE on April 15, 1986.