License Transfer - Insurance Required of a Licensee Under 10 CFR 140.11(a)(4) and 10 CFR 50.54(w)
ML20203M138
Person / Time
Site: Crystal River  Duke Energy icon.png
Issue date: 07/15/2020
From: Murray K
Duke Energy Florida
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation
References
3F0720-02
Download: ML20203M138 (6)


Text

( ~ DUKE ENERGY July 15, 2020 3F0720-02 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 Crystal River Nuclear Plant 15760 W. Power Line Street Crystal River, FL 34428 Docket 50-302 Docket 72-1035 Operating License No. DPR-72 10 CFR 50.90

Subject:

Crystal River Unit 3 - License Transfer - Insurance required of a licensee under 10 CFR 140.11(a)(4) and 10 CFR 50.54(w).

References:

1. Letter, USNRC to Duke Energy Florida, LLC, "Crystal River Unit 3 Nuclear Generating Plant - Order Approving Transfer of Licensed Authority from Duke Energy Florida, LLC to ADP CR3, LLC and draft conforming administrative license amendment (EPID L-2019-LLA-0135)," dated April 1, 2020 (ADAMS Accession Nos. ML20069A023, ML20069A024)

Dear Sir:

In accordance with the Order approving the direct transfers to ADP CR3, LLC (ADP CR3) of the Duke Energy Florida, LLC (DEF) licensed authority under Facility Operating License No. DPR 72 for the Crystal River Unit 3 Nuclear Generating Plant (CR3) (the Facility License) and the general license for the CR3 Independent Spent Fuel Storage Installation (ISFSI) (the Licenses) to possess, maintain, and decommission CR3 and the ISFSI (collectively, the CR3 Facility), dated April 1, 2020 (Reference 1 ), DEF, is providing documentary evidence that arrangements with both American Nuclear Insurers (ANI) and Nuclear Electric Insurance Limited (NEIL) to add ADP CR3 and ADP SF1, LLC to policies written for the Crystal River Unit 3 Nuclear Generating Pant.

The policies are for the appropriate amounts of insurance required of a licensee under 1 O CFR 140.11(a)(4) and 10 CFR 50.54(w), consistent with the exemptions issued for CR-3 on April 27, 2015, and March 31, 2016. This documentation is attached to this letter.

No new regulatory commitments have been made in this letter.

If you have any questions regarding this submittal, please contact Mr. Mark Van Sicklen, Licensing Lead, Nuclear Regulatory Affairs, at (352) 501-3045.

I declare under penalty of perjury that the foregoing is true and correct. Executed on July 15, 2020.

s~,/,~/

Kevin A. Murray, Vi~e /resident Management and Construction

U. S. Nuclear Regulatory Commission Page 2 of 2 3F0720-02 KAM/mvs

Attachment:

Insurance Documentation cc:

NMSS Project Manager Director, Office of Nuclear Reactor Regulation Regional Administrator, Region I State Contact

DUKE ENERGY FLORIDA, INC.

DOCKET NUMBER 50 - 302 / LICENSE NUMBER DPR - 72 ATTACHMENT INSURANCE DOCUMENTATION

Jason Martinez, CPCU, ARM, ARe Director, Underwriting American Nuclear Insurers 95 Glastonbury Blvd., Suite 300 Glastonbury, CT 06033-4453 jmartinez@nuclearinsurance.com Voice: (860) 682-1341 Fax: (860) 659-0002 June30,2020

Attn:DocumentControl Director,OfficeofNuclearRegulatoryCommission U.S.NuclearRegulatoryCommission Washington,DC205550001

Re:DukeEnergyFlorida,LLC,ADPCR3,LLCandADPSF1,LLC NRCOperatingLicenseAmendmentforCrystalRiverUnit3GeneratingPlant

ToWhomItMayConcern,

ThisletterreplacesourletterofJune10,2020,regardingthecaptionedsubjectmatter.

ThisletterconfirmsthatAmericanNuclearInsurerswillcontinuetowritenuclearliability insurancefortheCrystalRiverUnit3GeneratingPlant,locatedinCitrusCounty,FL, commensuratewiththeeffectivetransactionclosedatethattheNRCaddsADPCR3,LLCand ADPSF1,LLCtotheNRCoperatinglicense.Theeffectivetransactionclosedateisexpectedto beonorbeforeOctober1,2020.

Upontheeffectivetransactionclosedate,ANIwillamendthebelowpolicyandcertificatefor theCrystalRiverUnit3GeneratingPlantasfollows:

a. FacilityFormPolicyNo.NF0195:ANIwillamendthenamedinsuredtoDukeEnergy Florida,LLC,ADPCR3,LLCandADPSF1,LLCinlieuofDukeEnergyFlorida,LLC.ANI willalsoamendtheoperatorofthefacilitytoADPCR3,LLCinlieuofDukeEnergy Florida,LLC.
b. MasterWorkerCertificateNo.NW0579:ANIwillamendthenamedinsuredstoDuke EnergyFlorida,LLC,ADPCR3,LLCandADPSF1,LLCinlieuofDukeEnergyFlorida, LLC.ANIwillalsoamendtheoperatorofthefacilitytoADPCR3,LLCinlieuofDuke EnergyFlorida,LLC.

ThecommitmenttoaddADPCR3,LLCandADPSF1,LLCasinsuredsremainsvalidthru December31,2020.Intheeventthelicenseamendmentoccursafterthisdate,ANIwillreview theexistingcircumstancespriortoreinstatingourcommitmenttoaddtheseentities.

Pleasefeelfreetocontactmewithanyquestionsorconcerns.

Attn:DocumentControl June30,2020 Page2

Yourssincerely,

JasonMartinez,CPCU,ARM,ARe Director,Underwriting

C:DukeEnergy-TraceyLeroyandLanceBurnette Marsh-TimFarward,MarkWebster,JakeCompton,ChipHardie

June 24, 2020 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001

Subject:

Crystal River Unit 3 Nuclear Generating Plant Transfer of NRC License to ADP CR3, LLC

Dear Sir:

NEIL ~ -

BRUCE A. SASSI President & Chief Ex,*cut,vt' Officer Nuclear Electric Insurance Limited 1201 N Market St, Suite 1100 Wilmington, DE 19801 office +1302 573 2224 mobile +1484 639 7308 bsassl@myneil.com At the request of the insured, Duke Energy Florida, LLC ("Duke"), Nuclear Electric Insurance Limited (NEIL) agrees it will:

name ADP CR3, LLC as additional insured on policy no. P20-081 (Primary Property) upon being notified by Duke that the NRC has added ADP CR3, LLC to the license for Crystal River 3 Generating Plant name ADP SFl, LLC as an additional insured on policy no. P20-081 (Primary Property) upon being notified by Duke that ADP SFl, LLC has become a general licensee under 10 CFR 72.6 endorse policy no. P20-081 (Primary Property) and update the certificate of insurance to name ADP CR3, LLC as the operator of the facility, upon being notified by Duke that the NRC has added ADP CR3, LLC to the license for Crystal River 3 Generating Plant Please feel free to contact me should you have any questions.

President & Chief Executive Officer