Informs of Major Mods to Security Bldg to Enhance Security & Resolve NRC Concerns.Temporary Fence Installed on 860702-03. Mods Scheduled for Completion Prior to Mar 1987.Site Security Plan Will Not Be Revised Until Const Completed
ML20203L140
Person / Time
Site: Fort Calhoun 
Issue date: 08/13/1986
From: Andrews R
OMAHA PUBLIC POWER DISTRICT
To: Gagliardo J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
LIC-86-376, NUDOCS 8608250028
Download: ML20203L140 (2)


Text

.

Omaha Public Power District 1623 Harney Omaha. Nebraska 68102 2247 g@@

//

402;536-4000 1

August 13, 1986 AUb I b IObb ;

LIC-86-376 lb/

l J. E. Gagliardo, Chief Reactor Projects Branch U.S. fluclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 1000 Arlington, Tx. 76011 Reference Docket flo. 50-285

Dear Mr. Gagliardo:

Security Building Modifications This letter is being provided to inform you of OPPD's intention to make major modifications to the Security Building.

The building will be expanded and the traffic flow improved.

The changes will enhance the security at Fort Calhoun Station and resolve some prior f1RC concerns. The planned modifications have been reviewed with f1RC personnel.

The construction includes installation of a temporary fence and perimeter intru-sion detection system (PIDS).

This change will allow the construction activity to take place outside the protected area.

The modification also includes re-placement of the existing E-Field with microwave coverage over the building i tsel f.

The addition to the building will allow separate exit and entrance routes.

It will also require personnel to pass through the search equipment before picking up their key card badge, flow personnel get their badge before being searched.

The modification has begun in that the temporary fence was installed on July 2-3, 1986.

Installation of the PIDS for the temporary fence has started. The work on the building itself will start about August 25, 1986.

The modification is scheduled for completion prior to March, 1987.

This schedule does not ac-count for weather delays.

l The construction sequence has been planned to minimize the impact on security.

During the external construction, when there will be activity in the isolation zone, a nuclear watch officer will be posted for surveillance of the area.

An armed guard will be posted for the period of time while the new bullet resis-ting door is installed in the security work area.

An armed guard will also

'~

mo p

fg id u -

q)

.t

\\Q

-., = _

'J. E. Gagliardo LIC-86-376 Page 2 be posted in the access lane area during the search equipment removal and re-installation.

Each step of the construction will be analyzed for security requirements before the work starts. Appropriate compensatory actions will be taken when needed to ensure adequate security. No Site Security Plan Revisions are planned regarding this modification prior to completion. At that time an appropriate revision will be developed in accordance with 10 CFR 50.54(p).

If you have any questions about this process or the construction sequence, please contact us.

Sincerel,

R. L. Andrews Division Manager Nuclear Production RLA/JRG/me cc: LeBoeuf, Lamb, Leiby & MacRae 1333 New Hampshire Ave., N.W.