Requests Supplemental Info Re 860514 Response to IE Bulletin 85-003,including Valve Differential Pressure Determination & Switch Setting Estimation & Verification Methods.Response Requested within 30 Days of Ltr Date
ML20203H705
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 07/30/1986
From: Gagliardo J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Campbell G
ARKANSAS POWER & LIGHT CO.
References
IEB-85-003, IEB-85-3, NUDOCS 8608050067
Download: ML20203H705 (2)


Text

c

~

. o, NN In Reply Refer To:

Docke' : 50-313 50-368 Arkansas Power & Light Company

)

. ATTN: Mr. Gene Campbell Vice President, Nuclear.

Operations P. O. Box 551 Little Rock, Arkansas 72203 Gentlemen:

Thank you for your letter of May 14, 1986, in response to IE Bulletin No. 85-03 dated November 15, 1985. As a result of our preliminary review, we find that additional information is needed.

l Specifically, we request that you provide us with the following:

^

Your method to determine the differential pressure (DP) across the valves.

Your method to estimate switch settings, A; detailed step-by-step. program to verify the switch settings.

Included in this:is'how will the valves be verified operable if not tested at full operation.

Please provide the supplemental information within 30 days of the date of this letter.

Sincerely,

///

C608050067 860730 PDR ADOCK 05000313 PDR g

J. E. Gagliardo, Chief Reactor Projects Branch cc:

J. M. Levine, Director Site Nuclear Operations Arkansas Nuclear One P. O. Box 608 Russellville, Arkansas 72801 Arkansas Radiation Control Program Director bec:

(see,nextpage) f[

h RIV:RPf C:RPB,fB C:RPB RPMylli in/tw DRHun' r

JEGa 1 ip do A p /86 4AA/86 7/ f 61 r y lgl

2-Arkansas Power & l.ight Company 1

'bcctoDMB(IEll) bec distrib. by RIV:

  • R&SPB
  • Section Chief (RPB/B).

R. D. Martin, RA

  • RPB

-

  • Resident Inspector M. Murphy

- *RIV File DRSP

  • RSB 1.

E 1

4