Text
__
.-?
OPERATING DATA REPORT' DOCKET NO. 50 266 -
i DATE: 12/02/97 COMPLETED BY: M B. Koudetka f
a TELEPHONE: 920-755-6480 OPERATING STATUS
- 1. UNIT NAME: POINT BEACH NUCLEAR PLANT - UNIT 1
. NOTES
- 2. REPORTING PERIOD: November - 1997 3 LICENSED THERMAL POWER (MWTI: '1518.5
'4. NAMEPLATE RATING (GROSS MWEl: 523.8
- 5. DESIGN ELECTRICAL RATING INET MWE): 497.0
~.
- 6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWE): 509.O i
- 7. MArtMUM DEPENDABLE CAPACITY (NET MWE): 485.0 8.. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 THROUGF Il SINCE LAST REPORT, GIVE REASONS:
NA-
- 9. POWER LEVEL.TO WHICH RESTRICTED, IF ANY (NET MWEh NA
- 10. REASONS FOR RESTRICTIOFS, llF ANY):
4 NA' j
TH:S MONTH YEAR TO DATE CUMULATIVE t
- 11. HOURS IN REPORTING PERIOD 720.0 8,016.0 237,288.0 3
'f
- 12. NUMBEet OF HOURS REACTOR WAS CRITICAL O.0 1,173.6 194,047.5...
f
- 13. REACTOR RESERVE SHUTDOWN HOURS O.0 0.0 667.3 i
- 14. HOURS GENERATOR ON LINE O.0 1.151.0 190.806.0 t
- 15. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 84G.9
?
- 16. GROSS THERMAL ENERGY GENERATED (MWH) 10,597,026.0 12,155,357.0 281,649,742.0
}
'17. GOOSS ELECTRICAL ENERGY GENERATED O.0 534.720.0 91.625.810.0 t
i
- 18. NG ELECTRICAL ENERGY GENERATED (MWH) 0.0 478,899.0 87,335,318.5 i
O.0%
_14.4%
80.4 %
[
- 19. UNIT SERVICE FACTOR
- 20. UNIT AVAILABILITY FACTOR.
O0%
14.4 %
80.8 %.
j
- 21. UNIT CAPACITY FACTOR (USING MDC NET) 0.0%
12.3 %
75.6 %
- 22. UNIT CAPACITY FACTOR (USING DER NET) 0.0%
12.0 %
74.1 %
i 1-
- 23. UNIT FORCED OUTAGE RATE 100.0 %
85.6 %
4.8%
- 24. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE. AND DURATION OF EACH):
Refueling,'02/14/98,75 days 2*i. IF SHUTDOWN AT END OF REPORT PERIOD. ESTIMATED DATE OF STARTUP:
I l'
December 2,1997, DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NRC LETTER DATED SEPTEM8ER 22.1977 9712170484 971204 i
i PDR ADOCK 05000266 i
1..
R PDR s
s t
.W.
[f,#3s W "' 4.
POINT BEACH NUCLEAR PLANT D% '2T N o.
50-266 AVERACE DAILY UNIT POWER LEVEL UNIT Nt.ME Point, Beach. UW _
MONTH NOVEMBER -
1997 Pa 'E 12/1!97 Ci>MPLETED t1Y M. B. Koudelka TELEPHONE 920-75E 8i480 AVERAGE AVERAGE-AVERAGE DAILY
'JAILY DAftY 1
POWER LEVEL POWER LEVEL l
POWER LEVEL DAY MWe NET DAY MWe NET DAY MWe NET 1
-7 11
-2 21
-11 22
-14 12 2
2
-7 3
-7 13
-2 23
-13
-2 24
-13 i
l 4
-7 14 l
l 5
-7 15
-2 25
-14 i
6
-7 16
-4 2C 13 l
7
-7 17
-7 27 14 I
8
-7 18
-7 28
-14 9
-7 19
-7 29
-13 10
-6 20
-7 30
-15
-- J o
s
f I
P91NT BEACil NUCLEr Dociet No.
50-266 Unit Name
_Ecini.lknch Unit 1 UNIT Sillm) OWNS AND POWEIGk ;:.JC[lOliS Date
_12/5/97 Comp!cted By M.B.Koudefia REPORT MONT11 NOVEMHEP.- 1992 Telephon-No.
'R0/7554130 l
I Method of Laensee Evem Duratasi Reactor Shur Report No.
System Componca Cause and Correctne Actum
. No.
Date Type' Olours)
Reason
- Down' Code' Code' To Prevem Recur.eme 2
970218 F
7720 il I
NA Na NA The una was in fut shunke and taken k> coh! Jaewn im Mmh 15, IW7.
j l
I 2
' Method:
' Exhibit G - Instructions
'F: Forced Reason:
S: Scheduled A - Equipreznt Failure (explain) 1 - Manual for preparation of
.11 - Maintenance oi Testing 2 - Manual Scram data entry sheets C - Refueling 3 - Automatic Scram LER Die (NUREG4;161)
D - Regulatory Restriction 4 - Co.itinuation of E - O,erator Training &
Pievious Shutdown Licensing Exam 5 - Reduced Lead F - Administrative 6 - Other (explain)
' Exhibit 1 - Same Source G - Operational Errar (explain)
II - Other (explain)
Paronsb (0341) t
DOCKET NO.
50-266 UNIT NAME Point Beach Unit.'
DATE 12/05/97 COM,PLETED BY M. B. Koudelka TELEPHONE 920/755-6480 Unit I was in cold shutdown during the November,1997 report period.
The following Licensee Event Reports (LERs) were submitted to the NRC during Novem
,1997:
LER 266/97 039-00, RHR Loop inoperable Due to an Inoperable CCW Pump.
LER 266/97-040-00, Reactor Caolant Pump Seal Water Return Overstress During Some Loss of Seal Coolant Scenarios.
LER 266/97-04100, Potential Common Mode Failure in Auxiliary Feedwater System Control Circuits.
Safety-related maintenance included:
1.
IC-2 personnel access air lock cleaned,0-rings replaced, ball valves rebuilt, and outer door drive shaft collars adjusted.
2.
ICS-481 HX-1B steam generator CS-476 feedwater regulator bypass control switch replaced.
3.
IA-1281 1VNPSE-3213 purge exhaust isolation operator air inlet accumulator check vn,e replaced.
4.
IMS 2018A&C-S main steam stop solenoid valve inspected.
5.
1MS 2019 HX-1B steam generator header P-29 auxiliary feedwater pump steam supply motor-operated valve rewired.
6.
1MS-2019-0 H.X-1B steam generator header P-29 auxiliary feedwater pump steam supply motor-operated valve operator rewired.
7.
IMS-2020 HX-1 A steam generatcr header P-29 auxiliary feedwater pump steam supply motor-operated valve rewired.
S.
1P-25A&B-M condensate pump motors beanngs lubricated.
9.
1P-29 T P-29 auxiliary feedwater turbine-driven pump turbine ball and socket assembly replaced.
10.
ISI-847A&B eductors A and B sodium hydroxide supply check valve refurbished.
r
O
^
I 1.
1S1-850B P-10B residual heat removal pump sump B suction valve cylinder rebuilt and valve '
repacked.
12.
IVNPSE-3212 W-6A&B U1C purge exhaust fan suction valve replaced.
t e
o
(
e a
OPERATING DATA REPORT DOCKET NO. 50-301 DATE: 12/03/97 COMPLETED BY: M. B. Koudelka
'. ELEPHONE: 920-755-6480 OPERATING STATUS
- 1. UNIT NAME: POINT BEACH NUCLEAR PLANT - UNIT 2 NOTES
- 2. REPORTING PERIOD: November - 1997
- 3. LICENSED THEllMAL POWER (MWT): 1518.5
- 4. NAMEPLATE R ATING (GROSS MWE): 523.8
- 5. DESIGN ELECTRICAL RATING (NET MWE): 497.0
- 6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWE): 509.0
- 7. MAXIMUM DEPENDABLE CAPACITY (NET MWE): 485.0
- 8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS:
NA
- 9. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWE): NA
- 10. REASONS FOR RESTRICilONS, (IF ANY):
NA THIS MONTH YEAR TO DATE CUMULATIVE 720.0 8,016.0 222.073.0
- 11. HOURS IN REPORTING PERIOD
- 12. NUMBER OF HvURS REACTOR WAS CRITICAL 355.0 1.897.4 187,885.0 0.0 0.0 233.9
- 13. REACTOR RESERVE SHUTDOWN HOURS
- 14. HOURS GENERATOR ON LINE 35's.9 1,788.5 185,296.8
- 15. UNIT RESERVE SHUTDCWN HOURS 0.0 0.0 302.2
- 16. GROSS THERMAL ENERGY GENERATED (MWH) 523,920.0 2,570.941.0 26G,17E,948.0
- 17. GROSS ELECTRICAL ENERGY GENERATED 181.560.0 877,230.0 90,480,540.0 18 NET ELECTRICAL ENERGY GENERATED (MWH1 170,279.5 811.842.0 86,223,425.5 19.. UNIT SERVICE FACTOR 49.0 %
22.3 %
83.4 %
- 20. UNIT AVAILABILITY FACTOR 49.0 %
22.3 %
83.6 %
- 21. UNIT CAPACITY FACTOR (USING MDC NET) 48.8%
20.9 %
79.6 %
- 22. UNIT CAPACITY FACTOR (USING DER NET) 47.6 %
20.4 %
78.1 %
- 23. UNIT FORCED OUTAGE RATE 51.0 %
29.5 %
1.3 ?'
- 24. SHUTDOWNS SCHEDULED OVER NEXT 6 MON 1.s (TYPE, DATE. AND DURATION OF EACH):
f None
- 25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:
01/23/98 DATA REPORTED AND FACTORS CALCULATED AS REQUESTED IN NHC LETTER DATED SEPTEMBER 22,1977 r
l j
POINT BEACH NUCLEAR PLANT DOCKET NO -
50-301 AVERAGE DAILY UNIT POWER LEVEL UNIT NAME Point, Beach. Urut 2 MONTH NOVEMBER -
1997 DATE 12/1/97 COMPLETED 3Y M. B Koudelka 920-755-6480 TELEPHONE AVERAGE AVERAGE AVERAGE dally DAILY DAILY POWER LEVEL POWER LEVEL POWER LEVEL DAY MWe NET DAY MWe NET DAY
- MWe AET 1
502 11 501 21
-11 2
SOO 12 501 22
-8 3
500 13 501 23
-8 4
500 14 502 24
-8 5
501 15 217 25
-7 l
6 501 16
-15 26
-3 7
501 17
-15 27
-3 l
501 18
-16 28
-3 l
8 9
501 19
-16 29
-3 1
10 500 20
-15 30
-3 l
l l
4 POINT DEACil NUCLEAR PLANT DxLet No.
50-V)I Unit Name
. Point Ikvh Unit 2 UNIT 3111IJ110WNS AND 14)WER HI: DUCTIONS Date
_12/SN7 Completed By h1. n Korntelka REPORT MONTil NOVEMBER - 1997 Telephone No.
920n554*80 Metthd of' Ikemee Evers Duranon Reactor 9sur Repwt No.
Sysaem Compeers Cause ars! Corrective Acike No
' Date Type' (Ilours)
Reawn' ikmn' Cale*
Cale' To P!cve:s Recurre x l
Usur 2 was talen k) coki stunamn mi acccardane testang of the reacsx prontam sysnern togst I
6
~ 971115 F
3o?
B 1
2t&d764340 IA INSTRUX perrmssives.
l l
'F: Forced
' Reason:
'Metixxt:
' Exhibit G - Instructions S: Scheduled a - Equipment Failure (explain) 1 - Manual for preparation of B - Maintenance or Testing 2 - Manual Scram data en'ry sheets C - Refueling 3 - Automatic Scram LER file (NUREG-0161)
D - Ref,alatory Restriction 4 - Continuation of E - Operator Training &
Previous Shutdown 1 Wnsing Exam 5 - Reduced laud F - Administrative 6 - Other (explain)
' Exhibit I - Same Source G - Operational Error (explain)
II - Other (explain)
PHF4028b (03-93)
~
DOCKET NO. 301-UNIT NAME Point Beach Unit 2
-DATE 12/05/97 COMPLETED BY.
M. B. Koudelka TELEPHONE 920/755-6480-Unit 2 opetated at a daily average of 236 Mwe net during the November,1997 report period.
Safety related maintenance included:
Nuclear instrumentation system logic contacts tested (see LER 266/97-043-00).