Text
. _ - _ _ _ - _ _ - _ _ _ _ _ - - _ _ -
v j
Decenber 11, 1997 Mr. Nicholas J. Liparuto, Manager Nuclear Safety and Regulatory Analysis Nuclear and Advanced Technology Division Westinghouse Electric Corporation P.O. Box 355 Pittsburgh, PA 15230
SUBJECT:
- t. SPEN ITEMS ASSOCIATED WFH THE DRAFT SAFETY EVALUATION REPORT (SER) ON THE AP600 SHUTDOWN RISK SAFETY
Dear Mr. Liparulo:
The Reactor Systems Branch of the U.S. Nuclear Regulatory Commission has provided a draft SER input to the Standardization Project Directorate on the AP600 shutdown risk safety evaluation including the shutdown evaluation report, WCAP-14837. The draft SER input will t,e SER Section 19.3. The input has open items which have been extracted and designated as FSER open items in the enclosure to this letter.
If you have any questions regarding this matter, you may contact me at (301) 415-1141.
Sincerely, origi:
signed by:
William C. Huffman, Project Manager Standardization Project Directorate Division of Reactor Program Management Office of Nuclear Reactor Regulation Docket No. 52 003
Enclosure:
As stated cc wiencl See next page f
Oid i RIBUTION:
Docket File.
PDST R/F TQuay I I PUBLIC TKenyon WHuffman JSebrosky DScabu JNWilson ACRS (11)
WDean,0-5 E23 JMoore,0-15 B18 SSun,0-8 E23 RCaruso,0-8 E23 TCollins,0-8 E23 SNewberr 0-8 E2 GHolahan,0-8 E2 DDiec,0-8 E23 MPohida, v8 E23
(
OOCUMENT NAME: A:SHDNEVAL.OI To receive a copy of this document, Indicate in the box: "C" = C yW; ithout attachment / enclosure "E" = Copy with attachmentlenclosure "N" = No c)py g Is
! OFFICE PM:PDST:DRPM l B_C SRXB:DSSA 3.5 D:PDSTdDJRPM l l
NAME-WCHuffman$pW TLillins chf TRQdat DATE u 12//t/97 12/1o l97
_12/ u 19%
OFFICIAL RECORD CCPY 70 F?!" R T"Pm riq:~p'lJ 9712170226 971211 p
h.-[ kr> h- [ .
h k.J a u L QCid k Ci ht PDR ADOCK 05200003 A
PDR a
s
Mr. Nicholas J. Liparuto Docket No. 52 003 Westinghouse Electric Corporation AP600 cc:
Mr. B. A. McIntyre Mr. Rus Bell Advanced Plant Safety & Licensing Senior l'roject Manager, Programs i
Westinghouse Electric Corporation Nuclear Bergy Institute Energy Systems Business Unit 1776 l Strev. NW P.O. Box 355 -
Suite 300 Pittsburgh, PA 15230 Washington, DC 20006-3706 Ms. Cindy L. Haag Ms. Lynn Connor Advanced Plant Safety & Licensing Doc-Search Associates Westinghouse Electric Corporation Post Office Box 34 l
Energy Systems Business Unit Cabin John, MD 20818 Box 355 Pittsburgh, PA 15230 Dr. Craig D. Sawyer, Manager Advanced Reactor Programs Mr. Sterling Franks GE Nuclear Energy U.S. Department of Energy 175 Curtner Avenue, MC 754 NE-50 San Jose, CA 95125 19901 Germantown Road Germantown, MD 20874 Mr. Robert H. Buchholz GE Nuclear Energy Mr. Frank A. Ross 175 Curtner Avenue, MC-781 U.S. Department of Energy, NE-42 San Jose, CA 95125 Office of LWR Safety and Technology 19901 Germantown Road Barton Z. Cowan, Esq.
Germantown, MD 20874 Eckert Seamans Cherin & Mellott 600 Grant Street 42nd Floor Mr. Charles Thompson, Nuclear Engineer Pittsburgh, PA 15219 AP600 Certification NE 50 Mr. Ed Rodwell, Manager 19901 Germantown Road PWR Design Certification Germantown, MD 20874 Electric Power Research institute 3412 Hillview Avenue Palo Alto, CA 94303
SER SECTION 19.3 OPEN ITEMS ASSOCIATED WITH THE AP600 SHUTDOWN RISK EVALUATION 440.763F The shutdown evaluation report, W^AP-14237, provides insights that can be utilized by the COL applicants to increase the availability of altemate decay heat removal capabilities during shutdown and refueling operations. Westinghouse should provide a COL action item in the AP600 SSAR to ensure that the COL applicant develops plant specific refueling plans that would make use of the insights fumished in WCAP-14837.
440.764F A!r entrained in the RNS piping may hinder the ability to provide adequate shutdown cooling during mid-loop operation. To address this concem,'Nestinghouse designed the RNS piping to each respective RNS pump suction in a continuously downwara sloping path from the RCS connection, thereby creating a self venting path with no high point areas and no loop seats. The RNS piping design feature which precludes loop seals should be included in the ITAAC program for design verification.
440.765F As part of design features that mitigite a!: binding of the RNS pump during mid-loop operation, the RNS employs a step-nozzle connection to the RCS hot leg. The step-nozzle connection has several advantages that substantially reduce the RCS hot leg level (critical water level) at which a vom can occur in the RNS pump suction line becat.se of lower fluid velocity in the hot leg nozzw. and limits the maximum air entrainment into the pump suction, should a vortex occur, to no greater than 5-percent while continuing to provide decay heat cooling. The RNS step nozzle connection should be included in the ITAAC program for design verification.
440.766F Freeze seals are used for repairing and replacing such components as valves, pipe fittings, pipe stops and pipe connections when it is impossible to isolate the area of repair any other way.
Industrial experience indicates that some freeze seats have failed in nuclear power plants and resulted in significant ever.s. To address the issue of freeze seal failure, the AP600 design reduced the potential applications of freeze seals by reducing the number of lines that connect to the RCS. Westinghouse should provide a COL action item in the SSAR which will ensure that the COL applic. ant develops plant specific guidelines that would reduce the potential loss of RCS boundary and inventory when employing freeze seals.
Enclosure
0' 2
'440.767F AP600 design includes two RCS safety-related hot leg wide-range thermowell-mounted resis,
- tance temperature detectors (RTDs) and incore thermocouples that are used to measure RCS temperature. The incore thermocouples are used to measure core exit temperature, which is the indicative of the RCS temperature, and are available when the reactor vessel head is in place.
This capability is not available when the reactor vessel head is detensioned and instruments are -
disconnected in preparation for refueling activities. In this condition, the ability to measure the --
RCS temperature is dependent on the RCS wide-range hot leg RTDs. The staff believed that the RTD detector's accuracy would be highly flow dependent and asked (RAI 440.6g0) that Westing-house address the ability of RTDs to accurately detect incremental changes in temperature at no flow conditions. Westinghouse indicated that the wide-range RTDs provide a backup indication i
of coolant temperature when the RNS are operating, and provide the primary indication in the -
event that the RNS pumps become inoperable. The RTDs are inserted into the bottom of the hot legs in the AP600 design and Westinghouse states that these RTDs do not require flow to provide an accurate temperature measurement of the stagnant water in the hot legs. This configuration will provide indication of the temperature of the water in the hot legs as long as
- there is water present in the loop piping. Some current plants require flow for an accurate temperature measurement due to the RTD flow bypass manifold arrangement employed to measure RCS temperature. The staff agrees that the AP600 RTDs would accurately measure temperature in the hot leg as long as there is water in the hot leg piping. However, the measured hot leg temperature is not necessarily indicative of the overall RCS temperature if there is a lack-of coolant circulation in the RCS loop. Also, the staff considers the ability of the RTDs to relatively quickly measure incremental changes in the RCS temperature an important indication
- ~
of an approach to RCS boiling and a loss of RNS cooling. The staff could not verify the response time of the wide range RTDs as indicated by Westinghouse. Westinghouse indicated that an analysis was performed to determine the accuracy of the wide range RTDs for the stagnant 4
conditions. The staff has not received results indicating the ability of the RTDs to respond to incremental changes in RCS loop temperature under a stagnant condition. The staff, l..erefore, considers this an open item.
440.768F The staff considers the NPSH requirement an important design parameter of the RNS pump's design, and therefore, concludes that this information should be captured in the ITAAC program i
and the Initial Test Program.
440.769F Inadvertent actuation or malfunction of the CMTs can cause an increase in RCS inventory, The -
events may lead to an overfill of the pressurizer and possible loss of reactor coolant.' The analysis of the inadvertent actuation of the CMTs is performed with the plant initially in Mode 1, full-power condition and is discussed in SSAR 15.5.1. The reactor trip and the PRHR HX actuation are actuated on the Hi 3 pressurizer level trip setpoint. During the event, the CMTs inject cold and borated fluid into the RCS. The injected fluid expands as it is heated in the RCS by the decay heat. The expansion is counteracted by the heat removal from the PRHR HX.
Westinghouse stated that the severity of the fluid expansion increases with higher decay heat levels and claimed that the case at full-power (producing a maximum decay heat) bounds the results initiated from conditions below Mode 1. The fluid expansion is controlled by the injectioa-4 Z.
1. i.
3 i
rate, the core decay heat level and the heat removal rate. At shutdown operations, while decay -
heat levels are lower, heat removal from the PRHR HX is also lower. The staff notes that in the absence of analyses to quantify the total effect of the injection rate, decay heat levels and the heat removal rate from the PRHR HX on the fluid expansion, it is not clear that the full-power case bounds conditions below Mode 1. Westinghouse is requested to analyze the CMT malfunction events at shutdown modes and show that the results are acceptable.
440.770F Similar to the concem identified in 440.769F. the analysis of CVS malfunction is performed with the plant initially in Mode 1, full-power conditions and is discussed in SSAR 15.5.2. The severity of the event depends on ths fluid expansion, which, in tum, is controlled by the integral flow from the CVS, decay heat levels, and heat removal from the PRHR HX. The staff notes that in the absence of analyses to quantify the total effect of these parameters on fluid expansion, it is not clear that the full-power case discussed in SSAR 15.5.2 bounds events initiated from operations below Mode 1. Westinghouse is requestad to analyze the CVS malfunction events at shutdown modes and show that the results are acceptable. This is an Open item.
440.771F Westinghouse asserted in Section 4.7.3 of the shutdown evaluation report, WCAP-14837, that margin to the SG overfill would be maintained for SGTR events initiated at lower power levels even with a higher initial SG inventory corresponding to the lower initial power level. The staff notes that margin to SG overfill depend on parameters such as initial SG water inventory time to actuate the PRHR HX and termination of the CVS flow. In the absence of a quantitative analysis for SG overfill, it is not clear that the margin to SG overfill can be maintained for SGTR avents initiated at lower power levels and shutdown modes. Westinghouse is requested to perform SG overfill analyses initiated from lower mode conditions and show that the analytical results are acceptable. This is an Open item.
440.772F Technical Specifications allow isolation of one CMT for Mode 5 with the RCS intact. Prior to RNS operation, the initial RCS pressure may maintain at pressures corresponding to full-power pressures. Even though the decay power is less than the value assumed in the Mode-3 LOCA analyses, the availability of safety-related systems (one CMT vs. two CMTs available) is reduced.
Westinghouse is requested to perform LOCA analyses for Mode 5 with the RCS intact and at high RCS pressures and show that the results are acceptable. This is an Open item.
440.773F Westinghouse stated in its response to RAI 440.713 that the analysis of a loss of the RNS performed in Mode 5 bounds events that may occur during Mode 6 because of the higher decay heat levels, in Mode 6, the water in the refueling cavity provides a large heat sink. Following a loss of the RNS, the waterin the refueling cavity can heat up and begin to boilin several hours.
Westinghouse rtated that, before boiling occurs, the operators are required to close containment.
If no operator actions are taken, the water in the refueling cavity can fall to the lewl of the top of the core in several day.. Westinghouse stated that, prior to this time, the operators are required to align IRWST injection and eventually establish containment recirculation to provide long-term cooling. Westinghouse should include a COL action item in the AP600 SSAR for the COL
4 applicant to provide information (procedures or controls) and show that the required operator actions to close containment, align IRWST injection, and establish containment recirculation will be in place for removal of decay heat.
440.774F in NUREG/CR-5820 " Consequences of the Loss of the Residual Heat Removal System in Pressurized Water Reactors," dated May 1992, the staff and its contractor analyzed the assumed loss of residual heat removal with the vessel upper intomals in place to determine the possible core uncovery from a lack of coolant circulation flow. Such conditions could occur during the flooding of the refueling pool avity while preparing for fuel shuffling operations. Under these conditions, the vessel upper intemals may provide sufficient hydraulic resistance to natural circulation flow betwnn the refueling pool and the reactor, and may prevent the refuoling water from cooling the core if the residual heat removal cooling is lost. Westinghouse is requested to address this issue for the AP600 design. This is an Open item.
440.775F The ultimate responsibility for outage planning and controlis within the scope of the plant owners. The staff will review and ensure that the COL applicant has appropriately addressed the outage and planning program to improve low-power and shutdown operations, which, as a minimum would include the following important elements:
an outage philosophy which includes safety as a primary consideration in outage planning e
and implementation.
organizations responsible for scheduling and oversee!ng outages and provisions for an e
independent safety review team that would be assigned to perform final review and grant approval.
e control procedures which address both the initial outage plan and all safety-aignificant changes to schedule, provisions to ensure that all activities receive adequete resources, e
provisions to ensure defense in depth during shutdown and ensure that margins are not e
reduced. In addition, an altemate or backup system must be available if a safety system or l
a defense-in-depth system is removed from service.
provisions to ensure that all personnel involved in outage activities are adequately trained; e
this should include operator simulator training to the extent practicable; other plant personnel, including temporary personnel, should receive training commensurate with the outage tasks they will be performing.
Westinghouse should provide a COL action item in the AP600 SSAR to provide this information, l