Forwards Final SALP Rept 50-354/85-99 for Nov 1984 - Oct 1985,per 860227 Meeting & Review of 860317 Comments.No Changes to Original 860219 Rept Required,Based on Overall Assessment of Performance & Response to NRC Concerns
ML20203D483
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 04/16/1986
From: Murley T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Corbin McNeil
Public Service Enterprise Group
Shared Package
ML20203D489 List:
References
NUDOCS 8604220121
Download: ML20203D483 (3)


See also: IR 05000354/1985099

Text

.

__

_ _ _ _ _ _

_

1

I

4

APR 161986

Docket Nos. 50-354

Public Service Electric & Gas Company

ATTN: Mr. C. A. McNeill, Jr.

Vice President - Nuclear

Post Office Box 236

Hancocks Bridge, New Jersey 08038

Gentlemen:

Subject: SYSTEMATIC ASSESSMENT OF LICENSEE PERFORMANCE (SALP);

REPORT NO. 50-354/85-99

This letter refers to the SALP of the Hope Creek Generzting Station for the

period of November 1, 1984 through October 31, 1985, initially forwarded to you

by our February 19, 1986 letter (Enclosure 1). This SALP evaluation was dis-

cussed with you and your staff at a meeting held on February 27, 1986 (see en-

closure 2 for attendees). We have reviewed your March 17, 1986 written comments

(enclosure 3) and herewith transmit the final report (enclosure 4).

Based on

review of your comments, no changes to the original February 19, 1986 report

were required.

Our overall assessment is that you and your staff have demonstrated competent

management, exercised good control of activities, maintained positive attitude,

and have been responsive to NRC concerns.

Your cooperation in the SALP program is appreciated.

Sincerely,

Origrnal 3fgnid Ey

Tho=as E. Murley

Thomas E. Murley

Regional Administrator

cc w/ encl:

P. R. H. Laudrieu, Vice President - Engineering (Newark)

R. S. Salvesen, General Manager, Hope Creek Operations

A. E. Giardino, Manager, Station Quality Assurance

R. L. Mitti, General Manager, Nuclear Assurance and Regulation

A. J. Pietrofitta, General Manager, Power Production Engineering, Atlantic

Electric

L. A. Reiter, General Manager - Licensing and Reliability

Rebecca A. Green, Bureau of Radiation Protection

Public Document Room (POR)

local Public Document Room (LPDR)

Nuclear Safety Information Center (NSIC)

NRC Resident Inspector

State of New Jersey

0FFICIAL RECORD COPY

251FUHRMEISTER4/7/86 - 0001.0.0

8604220121 860416

-

04/11/86.I E 40

PDR

ADOCK 05000354

G

PDR

g

g

i

-s

v

PSE&G Gas Company

2

cc w/ encl: (Continued)

Chairman Palladino

Commissioner Roberts

Commissioner Asselstine

Commissioner Bernthal

Commissioner Zech

bcc w/ encl:

Region I Docket Room (with concurrences)

Management Assistant, DRMA (w/o encl)

DRP Section Chief

PA0 (2)

J. Goldberg, OELD:HQ

J. Van Vliet, PM, NRR

D. Wagner, NRR

J. Taylor, IE

T. Murley, Regional Administrator

Director, DRS

Director, DRSS

H. Kister, RI

D. Holody

W. Bochardt

DRP SALP File

v 'fh

W

l

0(f

RhRA

.RA

/

l

'RI:DRP

I. RP

F

'

lStrosnider

Kister

I

mstecki

A14p/86

url y

4//o/86

4/// /86

4/g /86

4//Lf

4

/86

0FFICIAL RECORD COPY

251fUHRMEISTER4/7/86 - 0003.0.0

04/07/86IE40

<

.

.

.--

_

..

ENCLOSURE'l'"

/

UNITED STATES

~'

8

NUCLEAR REGULATORY COMMISSION

n

?,

't

REGION I

,

o,

g

631 PARK AVENUE

\\

% . . . . ,6

KING OF PRUSSIA, PENNSYLVANIA 19406

+

FEB 191986

Docket No. 50-354

Public Service Electric and Gas Company

ATTN: Mr. Corbin A. McNeill, Jr.

Vice President - Nuclear

Nuclear Administration Bu-ilding

P.O. Box 236

Hancock's Bridge, New Jersey 08038

Gentlemen:

Subject: Systematic Assessment of Licensee Performance (Inspection No.

50-354/85-99)

On January 16, 1986, as documented in the enclosed report, the NRC Region 1

SALP Board evaluated activities associated with the Hope Creek Generating

Station.

A' meeting has been scheduled at the Hope Creek site on February 27, 1986, at

1:30 p.m., to discuss the SALP.

This meeting is intended to provide a forum

for candid discussion, including your plans to improve performance and any

comments you have on the assessment. We would like you to be prepared to

discuss at the meeting the possible root causes and futura implications of

problems related to electrical and I&C construction activities as discussed

in Section IV B of the enclosed report. Also, following the SALP meeting we

would like to discuss with you and your staff the status and results of the

preoperational test program.

Finally, please respond to the assessment in writing within 20 days af ter the

SALP discussion meeting.

The SALP report (supplemented and modified as

appropriate) and your response will then be placed in the NRC Public Document

,

Room.

Your coopecation is appreciated.

Sincerely,

fLil

v

'

Thomas E. Murle b

Regional Administrator

Enclosure:

NRC Inspection Report No. 50-354/85-99

D

'us, 22T SW

/b.

-

__ _ _ _ _ _ _ _

ENCLOSURE 2

s

%

HOPE CREEK SALP MEETING

February 27,1986

List of Attendees

Public Service Electric and Gas Company

$

R.M.

Eckert

-Sr. Vice President - Nuclear and Engineering

1

C.A.

McNeill, Jr.

-Vice President - Nuclear

P.H.R.

Landrieu

-Vice President - Engineering and Construction

R.S.

Salvesen

-General Manager - Hope Creek Operations

J.M.

Zupko

-General Manager - Salem Operations

R.A.

Burricelli

-General Manager - Engin9ering and Plant

i

q

Better.,ent

A.K.

Thompson

-General Manager - Nuclear Services

!

C.P.

Johnson

-General Manager - Nuclear iluality Assurance

l

J.T.

Boettger

-Assistant Vice President - Nuclear Operations

Support

J.

MacKinnon

-General Manager - Safety Review

S.

LaBruna

-Assistant General Manager - Hope Creek

!

i

Operations

{

P.J.

Kudless

-Maintenance Manager - Hope Creek

G.C.

Connor

-Operations Manager - Hope Creek

l

J.A.

Nichols

-Technical Manager - Hope Creek

J.R.

Lovell

-Radiation Protection / Chemistry Manager

i

F.

Meyer

-Manager - Site Services

R.A.

Silveria

-Community Affairs Manager

i

C.W.

Churchman

-Assiscant General Manager - Engineering

R.

Drewnowski

-Manager - Nuclear Systems Engineering

'

A.E.

Giardino

-Manager - Station OA - Hope Creek

D.J.

Jagt

-Assistant General Manager - Project Engineering

1

United States Nuclear Reaulatory Commission

T.E.

Murley

-Regional Administrator - Region 1

R.W.

Starostecki

-Director - Division of Reactor Projects

E.G.

Adensam

-Director - BWR Projects Directorate #3

J.R.

Strosnider

-Chief - Reactor Projects Section IB

R.W.

Borchardt

-Senior Resident Inspector - Hope Creek

D.H.

Wagner

-Licensing Project Manager

J.J.

Lyash

-Reactor Engineer

D.K.

Allsopp

-Resident Inspector