ML20203C091
ML20203C091 | |
Person / Time | |
---|---|
Site: | 05000192, University of Texas at Austin |
Issue date: | 07/10/1986 |
From: | Bauer T TEXAS, UNIV. OF, AUSTIN, TX |
To: | Berkow H Office of Nuclear Reactor Regulation |
References | |
NUDOCS 8607180352 | |
Download: ML20203C091 (1) | |
Similar Documents at 05000192, University of Texas at Austin | |
---|---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20210Q7171999-08-0202 August 1999
[Table view]Provides Rept of Violation of Surveillance TS TS4.2.4, Reactor Instrumentation Sys. Calorimetric Calibr of Reactor Power Instrument Channels Was Not Done in Necessary Annual Period.No Immediate Corrective Actions Necessary ML20206K7271999-05-0606 May 1999 Informs That MG Krause Will Be Reactor Supervisor & Assume Daily Supervisory Duties Previously Performed by T Bauer. T Bauer Will Continue as Assistant Director Concentrating Efforts on Extended Time Activities ML20206B1071999-04-21021 April 1999 Informs That Activities at Nuclear Engineering Teaching Lab, Continuing to Improve.Nuclear & Radiation Engineering Program Continues to Have Support from All Levels of Univ Administration - Dept,College & Institutional ML20205J2571999-03-26026 March 1999 Forwards Copy of Results of Operator Initial Exam Conducted at Univ of Texas at Austin on 990315-16.Without Encl ML20207B4341999-03-0202 March 1999 Forwards Insp Rept 50-602/98-201 on 981207-11.No Violations Noted ML20198S3041999-01-0606 January 1999 Discusses Telcon Between W Eresian & T Bauer Re Exam at Univ of Texas.Exam Scheduled During Month of Feb 1999. Rules & Guidelines That Will Be in Effect During Administration of Written Exam Encl ML20248F4661998-05-22022 May 1998 Notifies NRC That Licensee Intend to Reconstitute Committee Immediately,Rather than Wait Until Next Academic Yr ML20217M2201998-04-28028 April 1998 Forwards Replacement Page 3-13 to Univ of Tx 1997 Annual Rept.Corrections to Page Consists of Several Transcription Errors Incorrectly Categorizing Several of Tabulated Doses IR 05000602/19972011998-01-0909 January 1998 Forwards Insp Rept 50-602/97-201 on 970929-1003.No Violations Noted.Previous Level IV Violation Was Closed ML20113A1021996-06-0606 June 1996 Notifies of Change of Name of Balcones Research Ctr to Pickle Research Campus & Addition of Two Annotations for Interlock Requirements of TS W/Rcs Interlocks,Section 3.2.2, Per Conversation W/Nrc.Amended TS Pages 14 & 24 Encl ML20107K5251996-04-16016 April 1996 Forwards Response to NRC 960325 Rai,Supplementing Response Made on 951111 & Original Amend Request to Correct Lanquage in Ts.Affected TS Page Also Encl ML20094G5401995-11-11011 November 1995 Submits Response to Request for Addl Info Re NRC Ltr & Original Amend Requested .No Change to Reactor Operating Conditions Being Proposed ML20085M4361995-06-21021 June 1995 Submits Info Re Control of Access to Radiation in Beams ML20084A9671995-05-24024 May 1995 Forwards Response to NRC Ltr Re Violations Noted in Insp Rept 50-602/95-01.Corrective Actions:Review of Reactor Committee Minutes Was Done by Facility Director for Period 1/92 to 4/95 ML20057F8301993-10-13013 October 1993 Forwards Order Terminating License R-92 for Triga Mark I Research Reactor,Per 850503 Application.Amend 15 to Indemnity Agreement E-25 Encl for Signature ML20056H4331993-07-21021 July 1993 Forwards Final Rept of Confirmatory Survey of Univ of Texas Triga Reactor.Informs That Minor Rev Made to Draft Rept Issued in June 1993 to Reflect Comments Communicated by Telephone ML20056C3161993-05-0404 May 1993 Forwards Proprietary Response to NRC Ltr Re Violations Noted in Insp Rept 50-602/93-01 on 930317-18.Encl Withheld,Per 10CFR2.790 ML20056C1471993-03-23023 March 1993 Confirms Arrangements Made on 930304 to Hold Meeting on 930429 to Discuss Performance Perspectives of Licensed Activities at Nuclear Engineering Teaching Lab.Proposed Meeting Agenda Encl ML20127M9821993-01-21021 January 1993 Forwards Correction to License R-129,changing Wording on Page 7-12 ML20126L0801993-01-0505 January 1993 Forwards Insp Repts 50-192/92-02 & 50-602/92-02 on 921207-11.No Violations or Deviations Noted ML20095L8181992-04-15015 April 1992 Advises That Assembly Error Made at Triga Fabrication Facility in That Two Wires on Potentiometer on CRD Mechanisms Reversed,Per 920311 Telcon ML20091Q3981992-01-23023 January 1992 Forwards Executed Amendment to Indemnity Agreement E-25 & 14 ML20085D1821991-10-0404 October 1991 Forwards Univ SAR Amend Pages for Rev 1.01 Dtd May 1991 ML20083D3691991-09-24024 September 1991 Submits Info Re Availability of Funds for Future Decommissioning of Reactor,Per 10CFR50.33 & 10CFR50.75 ML20073R0131991-05-24024 May 1991 Requests Extension of CP CPRR-123 for Four Addl Months to Provide Time for Review of NRC Questions.Current Expiration 910630.Final Response & Amended SAR Being Sent by Separate Ltr ML20073R1061991-05-24024 May 1991 Forwards Rev 1.01 to Sar,Response to NRC Questions,Per 910222 Request for Addl Info & List of Matl Subj to License Request ML20073E6891991-04-15015 April 1991 Forwards Rev 1 to PLAN-O, Call & Notification & PLAN-E, Emergency Response, QA Plan & Pages 12,20 & 21 of Emergency Response Plan ML20066J3141991-02-12012 February 1991 Forwards Rev 1 to Tech Specs.Changes Made by Discussion & Concurrence W/Nrc ML20066E2641991-01-11011 January 1991 Forwards Rev 1 to Emergency Response Plan. Annotated Copy Also Encl to Assist Review Process Due to Editorial Changes Made to Reword Sentences ML20065Q3231990-12-11011 December 1990 Informs That Extension Date Incorrectly Stated as 900630 in .Correct Extension Date Should Read 910630 ML20062H0371990-11-26026 November 1990 Submits List of Matl Required to Complete Evaluation for Issuance of OL Including Updated Emergency & Operator Requalification Plans & Final Tech Specs & Bases.Three Open Items identifed,602/8904-05,602/8904-06 & 602/9003-01 ML20065S1391990-11-21021 November 1990 Forwards Rev 0 to QA Plan IR 05000192/19900011990-10-0101 October 1990 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-192/90-01 ML20065D0071990-09-10010 September 1990 Responds to Violations Noted in Insp Rept 50-192/90-01 on 900806.Corrective Actions:Personnel Access to Area Limited to Personnel W/Direct Knowledge of Status of Facility & Routine Work W/Radioactive Matl Removed from Area ML20056B2541990-08-13013 August 1990 Forwards Rev 1 to Physical Security Plan.Encl Withheld ML20056A8701990-08-0606 August 1990 Forwards Insp Rept 50-192/90-01 on 900625-28 & Notice of Violation.Encls Withheld (Ref 10CFR2.790(d)) ML20055D0401990-06-18018 June 1990 Updates Status of Items from Past Insps for Cp.Efforts to Reasonably Complete Items within Constraints of No Matl License Complete ML20043G6341990-06-0606 June 1990 Forwards Physical Security Plan.Plan Withheld ML20006E2981990-02-0909 February 1990 Forwards J Cox 891218 Ltr for Consideration & Compliance,If Possible ML20245G8181989-06-19019 June 1989 Informs of Bw Wehring Appointment as Director of Nuclear Engineering Teaching Lab at Univ of Texas,At Austin,Per License R-92,Tech Spec 6.2c3 & 6.2.2a.Curriculum Vitae of Wehring Encl ML20245J5851989-04-24024 April 1989 Forwards Addendum to 1988 Annual Rept ML20245D3281989-04-21021 April 1989 Forwards Amend 11 to License R-92 & Safety Evaluation. Amend Allows Postponing Certain Surveillance Requirements If Reactor Not Operable & Changes Definition of Reactor Secure ML20236C4461989-03-0808 March 1989 Responds to NRC Re 880801 Application for Amend to License R-92.Licensee Does Not Plan to Complete Postponed Surveillances to Make Facility Operable Prior to Movement of Fuel ML20235Y3541989-02-24024 February 1989 Forwards Order Extending Const Completion Date of Triga Mark II Reactor to 891231,safety Evaluation & Environ Assessment & Finding of No Significant Impact,Per 881017 Request ML20206E5261988-10-17017 October 1988 Requests Extension of Final Completion Date by 4 Months to 890430 for CP CPRR-123.Termination of General Contractor of Record Effective 881013 Requires Assumption of Project Responsibility by Continental Insurance Co ML20204G2111988-10-17017 October 1988 Forwards Insp Rept 50-602/88-05 on 880922-23.No Violations or Deviations Noted ML20206F0661988-09-13013 September 1988 Forwards Info to Suppl 880801 Amend Request for Change to License R-92 Tech Specs IR 05000192/19880021988-09-0202 September 1988 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-192/88-02 & 50-602/88-02 ML20151U6211988-08-15015 August 1988 Forwards Request for Addl Info Re 880801 Application for Amend to License R-92.Detailed Discussion of Which Tech Specs Should Be Amended & Wording of Tech Specs Requested ML20195D4921988-06-17017 June 1988 Confirms Telcon Arrangements for Administration of Operator Licensing Exams at Facility During Wk of 880912.Mtg Requested to Furnish Approved Ref Matl Listed in Encl Before 880711 Deadline 1999-08-02 Category:EDUCATIONAL INSTITUTION TO NRC MONTHYEARML20065D0071990-09-10010 September 1990
[Table view]Responds to Violations Noted in Insp Rept 50-192/90-01 on 900806.Corrective Actions:Personnel Access to Area Limited to Personnel W/Direct Knowledge of Status of Facility & Routine Work W/Radioactive Matl Removed from Area ML20056B2541990-08-13013 August 1990 Forwards Rev 1 to Physical Security Plan.Encl Withheld ML20055D0401990-06-18018 June 1990 Updates Status of Items from Past Insps for Cp.Efforts to Reasonably Complete Items within Constraints of No Matl License Complete ML20043G6341990-06-0606 June 1990 Forwards Physical Security Plan.Plan Withheld ML20245G8181989-06-19019 June 1989 Informs of Bw Wehring Appointment as Director of Nuclear Engineering Teaching Lab at Univ of Texas,At Austin,Per License R-92,Tech Spec 6.2c3 & 6.2.2a.Curriculum Vitae of Wehring Encl ML20245J5851989-04-24024 April 1989 Forwards Addendum to 1988 Annual Rept ML20236C4461989-03-0808 March 1989 Responds to NRC Re 880801 Application for Amend to License R-92.Licensee Does Not Plan to Complete Postponed Surveillances to Make Facility Operable Prior to Movement of Fuel ML20206E5261988-10-17017 October 1988 Requests Extension of Final Completion Date by 4 Months to 890430 for CP CPRR-123.Termination of General Contractor of Record Effective 881013 Requires Assumption of Project Responsibility by Continental Insurance Co ML20206F0661988-09-13013 September 1988 Forwards Info to Suppl 880801 Amend Request for Change to License R-92 Tech Specs ML20150F3181988-04-22022 April 1988 Responds to NRC Re Violations Noted in Insp Rept on 880324.Corrective Actions:Immediate Check of Review Dates on All Procedures & List Made of All Mods of Any Type ML20236Q9571987-11-0606 November 1987 Advises That NETL Project Progress Continues W/Projected Completion Date of 880610.Present Figures Indicate 46% Completion by mid-Oct.Key Items & Date Estimates Listed ML20212E3451987-02-20020 February 1987 Advises of Correction to Project Completion Date Noted in .Completion Date in Sentence Two Corrected to June 1988 ML20211B3191987-02-0606 February 1987 Informs That Bids for Docket 50-602 Project Opened on 861021 W/Award of General Contract on 861204.Dismantling Activities of Docket 50-192 License Projected to Commense in Aug or Sept 1988.Submits Info to Suppl 850503 Decommissioning Plan ML20207N0351986-12-0808 December 1986 Forwards Notice of 861215 Preconstruction Conference in Austin,Tx to Discuss Const Schedule Available from Cit,Inc of Texas.Set of Plans & Specs Should Be Sent by 851208 from Ws Martin ML20203C0911986-07-10010 July 1986 Informs That Bid Advertisement for Completion of Docket 50-602 & Dismantling of Docket 50-192 Scheduled for 860817 W/Bid Openings Planned for 860916 ML20199J9141986-03-26026 March 1986 Forwards 1985 Annual Rept of Univ of Texas at Austin, Nuclear Engineering Teaching Lab ML20137X1881985-12-0202 December 1985 Forwards Response to 850503 & 0809 Requests for Info Re Dismantling & Decommissioning Plan ML20133G8491985-10-0909 October 1985 Forwards Revised Tech Specs for License Submittal.Revs Include Changes in Form,Per NRC Request ML20133H1471985-08-14014 August 1985 Forwards Revised Security Plan,Per 850313 & 29 Telcons. Plan Withheld (Ref 10CFR73.21 & 2.790) ML20134E3431985-08-14014 August 1985 Forwards Revised Tech Specs to Suppl 841109 License Application.Revs Include Most Recent Info Available & Changes Per Telcons W/Nrc ML20132D2421985-07-0101 July 1985 Requests Application for CP Operating Permit & Environ Assessment for Research Reactor Be Forwarded to Author at Listed Address ML20117P1741985-05-14014 May 1985 Advises That Should Be Amended to Request Latest Facility Completion Date of 881231.Previous Date of 871231 Should Be Supplemented by Encl Latest Date,Per Telcon W/Nrc ML20117C0701985-05-0303 May 1985 Forwards Decommissioning Plan for Univ of Texas Triga Reactor. Project Schedule Estimates Completion in mid- to Late 1987.Implementation of Plan Not Anticipated Until Jul 1987 or Shortly After ML20116N7891985-05-0303 May 1985 Forwards Amended Application for Cp,Relocating Site 130 Meters from Original Location ML20116D4761985-04-22022 April 1985 Forwards Revised Tech Specs,Incorporating Changes in Response to Discussions During 850122 Site Visit & Telcons W/Nrc ML20115J1821985-04-15015 April 1985 Provides Financial Info as Amend to Paragraph (F) of General Info Submitted in 831109 License Application & Subsequent Submittals.Funding Approval for Major Changes in Physical Plant Is Responsibility of Board of Regents ML20113C7311985-04-0404 April 1985 Forwards Responses to NRC Questions Generated by Review of QA Program Submitted by 841109 ltr.Q-list for Structures,Sys & Components Encl ML20115C5981985-03-29029 March 1985 Forwards Annual Rept for CY84 ML20099H4271985-03-14014 March 1985 Forwards Supplemental Info in Support of 841109 Application & Subsequent 850227 Amend.Info Concerns Control Rods,Hvac Sys,Control Room Annunciator & Scram Channels ML20099H7501985-03-14014 March 1985 Forwards Response to Questions Re Reactor Operator Requalification Program Based on NRC Review of 841109 Application for License ML20099A2011985-02-28028 February 1985 Requests Extension Until 850315 to Respond to Request for Addl Info Re Operator Qualification & Requalification Portion of 841109 License Submittal ML20107M6161985-02-27027 February 1985 Forwards Response & Supplemental Response to Final Questions Re Initial Review & Site Visit to Proposed Reactor Facility, Per 841109 Application for License ML20107M6271985-02-27027 February 1985 Forwards Figure 1.0, Organizational Block Diagram & List of Titles of Emergency Procedures & Guidance Documents to Be Written in Support of Maintaining Emergency Preparedness,Per NRC 841109 Request ML20113E2821985-01-14014 January 1985 Certifies That Application for Cp/Ol Delivered to Governor M White,County Judge,M Renfro & Mayor R Mullen on 850114 ML20101F3301984-12-17017 December 1984 Forwards Physical Security Plan for Facility.Encl Withheld (Ref 10CFR2.790) ML20100J3011984-11-30030 November 1984 Notifies That All Correspondence Re License Application Should Be Sent to Director of Facility.Current Director & Appropriate Address Listed ML20108B3601984-11-0202 November 1984 Advises That Emergency Plan for Univ of Texas Triga Reactor Facility Fully Implemented ML20084H9661984-03-29029 March 1984 Submits Info Re Taylor Hall Renovation Plans.Illustration of Affected Areas Encl.No Changes Will Directly Impact Operation of Facility ML20076M2781983-07-21021 July 1983 Forwards Public Version of Revised Emergency Plan & Emergency Procedures,Including Procedures 2.0 Re Emergency Classification procedures,S1 Re Emergency Call List & S2 Re Emergency Equipment ML20024D5541983-07-0606 July 1983 Submits Public Version of Request for 30-day Extension to File Emergency Plan.Delays Unavoidable ML20085A1371983-06-30030 June 1983 Forwards Revised Physical Security Plan.Rev Withheld ML20073S6571983-05-0202 May 1983 Forwards Responses to License Renewal Questions in NRC .Responses to Questions 4,5,6 & 16 Provided in Encl Updated SAR Pages ML20069K5491983-04-0101 April 1983 Forwards Annual Operating Rept 1982 ML20069H6131983-04-0101 April 1983 Forwards Annual Rept for Univ of Texas at Austin Nuclear Engineering Teaching Lab,1982 ML20069A7981983-03-11011 March 1983 Forwards Revised Tech Specs Re Potential Channel Failure Per 830301-04 Discussions Re Ser.Info Resolves Questions Re License R-92 Renewal ML20070U5861983-02-0707 February 1983 Forwards Pages to Be Appended to Chapter 5 of SAR Re Two Experimental facilities.Co-60 Irradiator Maintained in Reactor Tank.Subcritical Assembly,Separately Licensed from Reactor,Included for Completeness ML20070U4621983-02-0707 February 1983 Forwards Eight Oversize Blueprints Showing Const & Renovation Plans for Areas Encompassing Nuclear Engineering Teaching Lab.Aperture Cards Are Available in PDR ML20064J7221983-01-14014 January 1983 Discusses Renovation,Demolition & Const Plans for Areas Containing Triga Reactor Facility ML20027E2661982-10-28028 October 1982 Forwards Public Version of Emergency Plan ML20063K1801982-08-11011 August 1982 Forwards Maps & Sketches Detailing Currently Proposed Const & Impact on Facility.Const Expected to Consist of Bldg of multi-story Structure 15 Ft from Reactor Tank 1990-09-10 Category:INCOMING CORRESPONDENCE MONTHYEARML20210Q7171999-08-0202 August 1999
[Table view]Provides Rept of Violation of Surveillance TS TS4.2.4, Reactor Instrumentation Sys. Calorimetric Calibr of Reactor Power Instrument Channels Was Not Done in Necessary Annual Period.No Immediate Corrective Actions Necessary ML20206K7271999-05-0606 May 1999 Informs That MG Krause Will Be Reactor Supervisor & Assume Daily Supervisory Duties Previously Performed by T Bauer. T Bauer Will Continue as Assistant Director Concentrating Efforts on Extended Time Activities ML20206B1071999-04-21021 April 1999 Informs That Activities at Nuclear Engineering Teaching Lab, Continuing to Improve.Nuclear & Radiation Engineering Program Continues to Have Support from All Levels of Univ Administration - Dept,College & Institutional ML20248F4661998-05-22022 May 1998 Notifies NRC That Licensee Intend to Reconstitute Committee Immediately,Rather than Wait Until Next Academic Yr ML20217M2201998-04-28028 April 1998 Forwards Replacement Page 3-13 to Univ of Tx 1997 Annual Rept.Corrections to Page Consists of Several Transcription Errors Incorrectly Categorizing Several of Tabulated Doses ML20113A1021996-06-0606 June 1996 Notifies of Change of Name of Balcones Research Ctr to Pickle Research Campus & Addition of Two Annotations for Interlock Requirements of TS W/Rcs Interlocks,Section 3.2.2, Per Conversation W/Nrc.Amended TS Pages 14 & 24 Encl ML20107K5251996-04-16016 April 1996 Forwards Response to NRC 960325 Rai,Supplementing Response Made on 951111 & Original Amend Request to Correct Lanquage in Ts.Affected TS Page Also Encl ML20094G5401995-11-11011 November 1995 Submits Response to Request for Addl Info Re NRC Ltr & Original Amend Requested .No Change to Reactor Operating Conditions Being Proposed ML20085M4361995-06-21021 June 1995 Submits Info Re Control of Access to Radiation in Beams ML20084A9671995-05-24024 May 1995 Forwards Response to NRC Ltr Re Violations Noted in Insp Rept 50-602/95-01.Corrective Actions:Review of Reactor Committee Minutes Was Done by Facility Director for Period 1/92 to 4/95 ML20056H4331993-07-21021 July 1993 Forwards Final Rept of Confirmatory Survey of Univ of Texas Triga Reactor.Informs That Minor Rev Made to Draft Rept Issued in June 1993 to Reflect Comments Communicated by Telephone ML20056C3161993-05-0404 May 1993 Forwards Proprietary Response to NRC Ltr Re Violations Noted in Insp Rept 50-602/93-01 on 930317-18.Encl Withheld,Per 10CFR2.790 ML20095L8181992-04-15015 April 1992 Advises That Assembly Error Made at Triga Fabrication Facility in That Two Wires on Potentiometer on CRD Mechanisms Reversed,Per 920311 Telcon ML20091Q3981992-01-23023 January 1992 Forwards Executed Amendment to Indemnity Agreement E-25 & 14 ML20085D1821991-10-0404 October 1991 Forwards Univ SAR Amend Pages for Rev 1.01 Dtd May 1991 ML20083D3691991-09-24024 September 1991 Submits Info Re Availability of Funds for Future Decommissioning of Reactor,Per 10CFR50.33 & 10CFR50.75 ML20073R0131991-05-24024 May 1991 Requests Extension of CP CPRR-123 for Four Addl Months to Provide Time for Review of NRC Questions.Current Expiration 910630.Final Response & Amended SAR Being Sent by Separate Ltr ML20073R1061991-05-24024 May 1991 Forwards Rev 1.01 to Sar,Response to NRC Questions,Per 910222 Request for Addl Info & List of Matl Subj to License Request ML20073E6891991-04-15015 April 1991 Forwards Rev 1 to PLAN-O, Call & Notification & PLAN-E, Emergency Response, QA Plan & Pages 12,20 & 21 of Emergency Response Plan ML20066J3141991-02-12012 February 1991 Forwards Rev 1 to Tech Specs.Changes Made by Discussion & Concurrence W/Nrc ML20066E2641991-01-11011 January 1991 Forwards Rev 1 to Emergency Response Plan. Annotated Copy Also Encl to Assist Review Process Due to Editorial Changes Made to Reword Sentences ML20065Q3231990-12-11011 December 1990 Informs That Extension Date Incorrectly Stated as 900630 in .Correct Extension Date Should Read 910630 ML20065S1391990-11-21021 November 1990 Forwards Rev 0 to QA Plan ML20065D0071990-09-10010 September 1990 Responds to Violations Noted in Insp Rept 50-192/90-01 on 900806.Corrective Actions:Personnel Access to Area Limited to Personnel W/Direct Knowledge of Status of Facility & Routine Work W/Radioactive Matl Removed from Area ML20056B2541990-08-13013 August 1990 Forwards Rev 1 to Physical Security Plan.Encl Withheld ML20055D0401990-06-18018 June 1990 Updates Status of Items from Past Insps for Cp.Efforts to Reasonably Complete Items within Constraints of No Matl License Complete ML20043G6341990-06-0606 June 1990 Forwards Physical Security Plan.Plan Withheld ML20006E2981990-02-0909 February 1990 Forwards J Cox 891218 Ltr for Consideration & Compliance,If Possible ML20245G8181989-06-19019 June 1989 Informs of Bw Wehring Appointment as Director of Nuclear Engineering Teaching Lab at Univ of Texas,At Austin,Per License R-92,Tech Spec 6.2c3 & 6.2.2a.Curriculum Vitae of Wehring Encl ML20245J5851989-04-24024 April 1989 Forwards Addendum to 1988 Annual Rept ML20236C4461989-03-0808 March 1989 Responds to NRC Re 880801 Application for Amend to License R-92.Licensee Does Not Plan to Complete Postponed Surveillances to Make Facility Operable Prior to Movement of Fuel ML20206E5261988-10-17017 October 1988 Requests Extension of Final Completion Date by 4 Months to 890430 for CP CPRR-123.Termination of General Contractor of Record Effective 881013 Requires Assumption of Project Responsibility by Continental Insurance Co ML20206F0661988-09-13013 September 1988 Forwards Info to Suppl 880801 Amend Request for Change to License R-92 Tech Specs ML20150F3181988-04-22022 April 1988 Responds to NRC Re Violations Noted in Insp Rept on 880324.Corrective Actions:Immediate Check of Review Dates on All Procedures & List Made of All Mods of Any Type ML20236Q9571987-11-0606 November 1987 Advises That NETL Project Progress Continues W/Projected Completion Date of 880610.Present Figures Indicate 46% Completion by mid-Oct.Key Items & Date Estimates Listed ML20212E3451987-02-20020 February 1987 Advises of Correction to Project Completion Date Noted in .Completion Date in Sentence Two Corrected to June 1988 ML20211B3191987-02-0606 February 1987 Informs That Bids for Docket 50-602 Project Opened on 861021 W/Award of General Contract on 861204.Dismantling Activities of Docket 50-192 License Projected to Commense in Aug or Sept 1988.Submits Info to Suppl 850503 Decommissioning Plan ML20207N0351986-12-0808 December 1986 Forwards Notice of 861215 Preconstruction Conference in Austin,Tx to Discuss Const Schedule Available from Cit,Inc of Texas.Set of Plans & Specs Should Be Sent by 851208 from Ws Martin ML20203C0911986-07-10010 July 1986 Informs That Bid Advertisement for Completion of Docket 50-602 & Dismantling of Docket 50-192 Scheduled for 860817 W/Bid Openings Planned for 860916 ML20199J9141986-03-26026 March 1986 Forwards 1985 Annual Rept of Univ of Texas at Austin, Nuclear Engineering Teaching Lab ML20137X1881985-12-0202 December 1985 Forwards Response to 850503 & 0809 Requests for Info Re Dismantling & Decommissioning Plan ML20133G8491985-10-0909 October 1985 Forwards Revised Tech Specs for License Submittal.Revs Include Changes in Form,Per NRC Request ML20133H1471985-08-14014 August 1985 Forwards Revised Security Plan,Per 850313 & 29 Telcons. Plan Withheld (Ref 10CFR73.21 & 2.790) ML20134E3431985-08-14014 August 1985 Forwards Revised Tech Specs to Suppl 841109 License Application.Revs Include Most Recent Info Available & Changes Per Telcons W/Nrc ML20128N6691985-07-0909 July 1985 Requests Univ of Texas 841109 Application for CP & OL & Environ Assessment ML20132D2421985-07-0101 July 1985 Requests Application for CP Operating Permit & Environ Assessment for Research Reactor Be Forwarded to Author at Listed Address ML20117P1741985-05-14014 May 1985 Advises That Should Be Amended to Request Latest Facility Completion Date of 881231.Previous Date of 871231 Should Be Supplemented by Encl Latest Date,Per Telcon W/Nrc ML20117C0701985-05-0303 May 1985 Forwards Decommissioning Plan for Univ of Texas Triga Reactor. Project Schedule Estimates Completion in mid- to Late 1987.Implementation of Plan Not Anticipated Until Jul 1987 or Shortly After ML20116N7891985-05-0303 May 1985 Forwards Amended Application for Cp,Relocating Site 130 Meters from Original Location ML20116D4761985-04-22022 April 1985 Forwards Revised Tech Specs,Incorporating Changes in Response to Discussions During 850122 Site Visit & Telcons W/Nrc 1999-08-02 |
Text
.
' COLLEGE OF ENGINEERING g'A ,e THEw UNIVERSITY OF TEXAS AT AUSTIN
. .I e g/ DepartmentofMechanicalEngineering NuclearEngineeringProgram ,fustin, Texas 18712 ($12)471-3136 July 10, 1986 Mr. Herb Berkow Special and Standardization Project Branch Nuclear Regulatory Commission Washington, D.C. 20555
Dear Mr. Berkow:
The University of Texas at Austin project (docket 50-602),
CPRR-123, received approval of final p1:ns by the UT Board of Regents on April 10, 1986. Bid advo .sement has been scheduled for August 17, 1986 with bid openings planned for September 16, 1986. Following award of bids, construc'~)n would start in about 45 days with 16 months projected for completion. This schedule projects completion of docket 50-602 facility in March 1988, and initiation of the dismantling activities of docket 50-192 at about the same time (approximately 30-60 days later).
Other schedule information or changes to the schedule will be provided when available.
Sincerely,
$$ 8- '
Dr. T.L. Bauer Assistant Director Nuclear Engineering Teaching Laboratory I
1 TLB:bja j cc: Mr. John Dosa Mr. Hal Bernard