' COLLEGE OF ENGINEERING g'A,e THE UNIVERSITY OF TEXAS AT AUSTIN w
.I g/
DepartmentofMechanicalEngineering NuclearEngineeringProgram,fustin, Texas 18712 ($12)471-3136 e
July 10, 1986 Mr. Herb Berkow Special and Standardization Project Branch Nuclear Regulatory Commission Washington, D.C.
20555
Dear Mr. Berkow:
The University of Texas at Austin project (docket 50-602),
CPRR-123, received approval of final p1:ns by the UT Board of Regents on April 10, 1986.
Bid advo
.sement has been scheduled for August 17, 1986 with bid openings planned for September 16, 1986.
Following award of bids, construc'~)n would start in about 45 days with 16 months projected for completion.
This schedule projects completion of docket 50-602 facility in March 1988, and initiation of the dismantling activities of docket 50-192 at about the same time (approximately 30-60 days later).
Other schedule information or changes to the schedule will be provided when available.
Sincerely,
$$ 8-Dr. T.L.
Bauer Assistant Director Nuclear Engineering Teaching Laboratory TLB:bja j