O SALEM GENERATING STATION MONTHLY OPERATING
SUMMARY
- UNIT 1 MARCH 1986 The Unit began the period operating at 97% power.
Between March 15, 1986 and March 17, 1986, river grasses and debris caused a series of circulating water problems.
Load reductions were performed as necessary to maintain condenser vacuum. On March 21, 1986 at 2158 l
hours, the Unit was removed from service and commenced the sixth refueling outage.
Major work to be done this outage includes refueling, leak rate test of the Type "C" Containment Isolation Valves, llE, 12E, and 13W MSR HP tube bundle replacement, valve replacements, valve repackings (as required), upgrade of the connectors on the Control Rod Drive mechanisms, and other miscellaneous maintenance and inspection work.
The Unit remained in Mode V (Cold Shutdown), until 0715 hours0.00828 days <br />0.199 hours <br />0.00118 weeks <br />2.720575e-4 months <br />, on March 28, 1986, when the reactor vessel head studs were detensioned and Mode VI (Refueling),
was entered.
The reactor vessel head was lifted on March 30, 1986.
As of this report, the Unit remains in Mode VI with outage work continuing and on schedule.