Notice of Violation from Insp on 860224-0303
ML20199K775
Person / Time
Site: Hatch Southern Nuclear icon.png
Issue date: 04/04/1986
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20199K763 List:
References
50-321-86-08, 50-321-86-8, NUDOCS 8604100225
Download: ML20199K775 (1)


Text

_ _ _ _

ENCLOSURE 1 NOTICE OF VIOLATION Georgia Power Company Docket Nos. 50-321 Hatch I License Nos. DPR-57 The following violation was identified during an inspection conducted on February 24 - March 3,1986. The Severity Level was assigned in accordance with the NRC Enforcement Policy (10 CFR Part 2, Appendix C).

Technical Specification 6.8.1 requires the licensee to implement approved ,

written procedures covering the areas recommended in Appendix A of Regula-tory Guide 1.33, Revision 2, February 1978, which includes maintenance and surveillance activities of safety-related equipment.

Contrary to the above,

1. Procedure 50AC-MNT-001-0S, Maintenance Program, was not properly

, implemented in that the thermal relief valve on the RHR service water side of the "B" RHR Heat Exchanger was removed, repaired and rein-stallad when the Maintenance Work Order specified the thermal relief valve on the RHR side of the heat exchanger was to be worked.

2. Procedure 52GM-MEL-022-0S, Limitorque Valve Operator Electrical Maintenance, was not properly implemented for Maintenance Work Order 1-84-5742 in that step' 7.9.13.7 through 7.9.13.17.1 were omitted when per the procedure they were required to be performed.

This is a Severity Level IV violation (Supplement I).

Pursuant to 10 CFR 2.201, you are required to submit to this office within

, 30 days of the date of this Notice, a written statement or explanation in reply, including: (1) admission or denial of the alleged violation; (2) the reasons for the violation if admitted; (3) the corrective steps which have been taken and the results achieved; (4) corrective steps which will be taken to avoid further violations; and (5) the date when full compliance will be achieved.