ML20199H806

From kanterella
Jump to navigation Jump to search
Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-382/97-21 Issued on 971202.Corrective Actions Will Be Examined During Future Inspections
ML20199H806
Person / Time
Site: Waterford Entergy icon.png
Issue date: 01/30/1998
From: Stetka T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Dugger C
ENTERGY OPERATIONS, INC.
References
50-382-97-21, NUDOCS 9802050127
Download: ML20199H806 (5)


See also: IR 05000382/1997021

Text

_

_

-.

_ . _ . _ _ __ . _

_

_._._.. _ _. _..

_. _ .. _

___._ _ _

_

_

.

.

t

,t ** "8 0

UNitt D St Att$

/

W,$*t

NUCLEAR REGULATORY COMMISSION

.

$

f$

'

nacioN iv

' k4k;,/

t

!

$11 RYAN PLAZA DRIVE, SUlt E 400

%,,'-

ARuNotow. te xAs n,oit soes

,

January 30, 1998

Charles M. Dugger, Vice President

Operations . Waterford 3

Entergy Operations, Inc.

P.O. Box B

Killona, Louisiana 70066

SUBJECT: RESPONSE TO NRC INSPECTION REPORT 50-382!97-21

Dear Mr. Dugger:

Thank you for your letter of January 22,1998, in response to our December 2,1997,

letter and Notice of Violation concerning two examples of a failure to follow procedures. We

have reviewed your reply and find it responsive to the concerns raised in our Notice of Violation.

We will review the implementation of your corrective actions during a future inspection to

determine that full cor,pliance has been achieved and will be maintained.

Sincerely,

A

- I Z w ~v' W. M L < A -

a

Thomas F. Stetka, Acting Chief'

Engineering Branch

Division of Reactor Safety

Docket No.: 50-382

License No.: NPF 38

cc:

Executive Vice President and

Chief Operating Officer

Entergy Operations, Inc.

P.O. Box 31995

Jackson, Mississippi 39286-1995

Vice President, Operations Support

Entergy Operations, Inc.

P.O. Box 31995

Jackson, Mississippi 39286-1995

'

lllllllll.1.llll1.1

/

....

. .

9902050127 980130

PDR

ADOCK 05000382

0

PDR

-- -

-

.

.

--

l

o

.

Entergy Operations, Inc.

2

l

- i

Wise, Carter, Child & Caraway

i

P.O. Box 651

Jackson, Mississippi 39205

f

General Manager, Plant Operations

Waterford 3 SES

Entergy Operations,Inc.

P.O. Box B

Killona, Louisiana 70066

'

,

!

!

Manager Lloonsing Manager

!

Waterford 3 SES

,.

'

Entergy Operations, Inc.

,

'

P.O. Box B

'

.

Killona, Louisiana 70066

,

Chairman-

Louisiana Public Service Commission

One American Place, Suite 1630

Baton Rouge, Louisiana 70825-1697

+

Director, Nuclear Safety &

Regulatory Affairs

.

- Waterford 3 SES

!

Entergy Operations, Inc.

P.O. Box B

Killona, Louisiana 70066

~

William H. Spell, Administrator

Louisiana Radiation Protection Division

P.O. Box 82135

Baton Rouge, Louisiana 70884 2135

'

Parish President

St. Charles Parish

P.O. Box 302

Hahnville, Louisiana 70057

,

Mr. William A. Cross

>

Bethesda Licensing Office

3 Metro Center

Suite 610

Bethesda, Maryland 20814

<

  • m'-

r

4p,

--

-cn-,nu ew -, -,

,, , ,

,n.-

c - - , , , . . ,m.

v-i,

--n

n

.r,---

-r-m.%

.e,--

r--

.e---.

~ . , . . + - . - .

'

.. . .-

- ,-. - ..

.. ._._- - ..- -.

.- -.......- -.

- _..-.-... -.. _-.--,.._. .

. .

o

!

6

Entergy Operations, Inc.

3

!

.

&

1

Winston & Strewn '

>

1400 L Street, N.W.

Washington, D.C.- 20005-3502

i

,

_

.

I

f

f

a

b

4

F

f

'I

. s

..

...>

9

-

,k

.

h

-

-

. - - - , .

y

-

h

n

s

, . _ , , , , .

r w

-v = c = -- rr

w r gw 's - i -g o

w

a-,v-

i-3

7

y-

f

_ _ _ _ _ _ _ _ _ _ _ . _ _ _ _

.

D

Entergy Operations, Inc.

-4

E Mail report to T. Frye (TJF)

E-Mail report to T. Hiltz (TGH)

E Mail report to NRR Event Tracking System (IPAS)

y

E Mail report to Document Control Desk (DOCDESK)

'

bec to DCD (IE01)

bec distrib. by RIV:

Regional Administrator

Resident inspector

DRP Director

DRS-PSB

l

Branch Chief (DRP/D)

MIS System

!

Project Engineer (DRP/D)

RIV File

Granch Chief (DRP/TSS)

DRS Al 97-G-0137

DOCUMENT NAME: R:\\_WAT\\WT721AK.MFR

To receive copy of document. Indicate in box: "C" = Copy without enclosures "E" = Copy with enclosures *N" = No copy

RIV: SRI:EB

AC:EB

o

MFRunyan/imb p

TFStetka @

0)#%98

01/9/98

OFFICIAL RECORD COPY

>

l

_ _ _ _ _ _ _ _ _ _ - _ _ _ - _ _ _ __ _ - _ _ _ _ _ _ _ _ _ _ _ - _ _ -

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

i

..

i

!

f

Entergy Operations, Inc.

-4

!

f

E-Mail report to T. Frye (TJF)

i

E Mail report to T. Hiltz (TGH)

l

E Mail report to NRR Event Tracking System (IPAS)

E Mail report to Document Control Desk (DOCDESK) -

,

i boo to DCD (IE01)'

!

"d -

bec distrib. by RIV:

'

Regional Administrator

Resident inspector

DRP Director

DRS PSB

Branch Chief (DRP/D)

MIS SyMem

Project Engineer (DRP/D)

_ RIV File -

Branch Chief (DRP/TSS)

!

DRS Al 97-G-0137

!

!-

,

1

DOCUMENT NAME: R:\\_WABWT721AK.MFR

To receive copy of document. Indicate in box:"C" = Copy wdhout enclosures "E" = Copy with enclosures "N" = No copy

'

RIV:SRl:EB

AC:EB

m

MFRunyan/imb #

TFStetka dM

0)4%98-

01 Af/98

OFFICIAL RECORD COPY

050021

,

,

. , ,

.n.

,

e

,-

.g

%;;'d

Ente gy operations,Inc.

v/

h@ma L A ?ODC4

Tel 504 ?39 0242

Earl C. Ewing. ill

og,.3.,s s n,. san

u.s,

,

W3F 197-0276

(A05

PR

January 22,1998

U.S. Nuclear Regulatory Commission

y

o

ATTN: Document Control Desk

. .l.d J l Ip

'

Washington, D.C. 20555

ih

y1

O

M 26' ' N

Subject:

Waterford 3 SES

2)

.

.!,

.

L

2 eh FI'..d , _ ' .

Docket No. 50 382

-

License No. NPF-38

~'

NRC Inspection Report 97 21

Reply to Notice of Violation

Gentlemen:

In accordance with 10CFR2.201, Entergy Operations, Inc. hereby submits in

Attachment 1 the response to the violation identified in Enclosure _1 of the subject

Inspection Report.

',

On December 31,1997, Waterford 3 receivea permission to extend the due date for

this reply from January 2,1998, to January 15,1998. On January 15,1998,

permission was granted to extend the due date from January 15,1998, to January

22,1998. NRC personnel contacted for those extensions include the Region IV

Director, Division of Reactor Safety, and the Region IV Deputy Director, Division of

Reactor Safety.

-

_

,

_

_- -

_

.

.

'.

NRC Inspection Report 97 21

Reply to Notice of Violation

W3F197 0276

Page 2

January 22,1998

If you have any questions concerning this response, please contact me at (504) 739

6242 or Tim Gaudet at (504) 739 6666.

Very truly yours,

n

!

E.C. Ewing

-

Director,

Nuclear Safety & Regulatory Affairs

ECE/WDM/ssi

Attachment

oc:

E.W. Merschoff (NRC Region IV)'

J. 8.leberman (NRC-NRR)

C.P. Patel(NRC NRR)

J. Smith

N.S. Reynolds

NRC Resident inspectors Office

_

A

=.

=_

=_

__

,

4

Att:chment to

'.

V/3F197-0276

Page 1 of 6

ATTACHMENT 1

ENTERGY OPERATIONS. INC. RESPONSE TO THE VIOLATION IDENTIFIED IN

ENCLOSURE 1 OF INSPECTION REPORT 50-382/97-2_1,

VIOLATION NO,9721-02

10 CFR Part 50, Appendix B, Criterion V, * Instructions, Procedures, and Drawings,"

states that activities affecting quality shall be prescribed by documented instructions,

procedures, or drawingt,, of a type appropriate to the circumstances and shall be

accomplished in accordance with these instructions, procedures, and drawings.

.

Site Procedure W4.503, " Changes to the Technical Specifications, Technical

Requirements Manual, or Core Operating Limits Report," Revision 4.1, required that

desired changes to the technical requirements manual be evaluated under the

10CFR50.59 process in accordance with Procedure W2.302, *10CFR50.59 Safety

and Environmental Screenings," and reviewed by the plant operating review

committee.

Procedure W2.501, " Corrective Action," Revision 6, states that an individual who

identifies a condition adverse to quality shall initiate a condition report.

1. Contrary to the above, on April 8,1996, desired changes were identified for

entries in Table 3.8-1 of the technical requirements manual and as of October 10,

1997, had not been evaluated under the 10CFR50.59 process,

2. Contrary to the above, the licensee failed to initiate a condition report following

the discovery in 1997 of a condition adverse to quality involving Calculation EC-

191-027, Revision 0, dated December 30,1991, which analyzed the error

associated with the conta;nment spray riser level gauges. The calculation, which

did not account for density changes in the water column being measured,

affected the calculation of peak containment pressure for a loss of-coolant

accident.

This is a Severity Level IV violation (Supplement 1). (50-382/9721-02)

1

'

.

'-

!

a

>

Attachment to

!

~,

W3F197-0276

'{

[

Page 2 of 6

t

f

RESPONSE

{

I

For the sake of clarity, each example of Violation 9721-02 is addressed separately

'

below,

,

,

(1)

Reason for the VinjaEQD (Example 1)

._

i

Waterford 3 acknowledges that desired changes to Table 3.8-1 of the

!'

i

Technical Requirements Manual (TRM) were not evaluated under the

i

. 10CFR50.59 process from April 8,1996 to October 10,1997. The apparent

'

cause of that cor.dition is inappropriate action.

-l

!

!

p

Licensee Event Report (LER)95-006 dated January 8,1996, reporied a

condition wherein two electrical alternating current circuits which use

,

containment electrical penetrations did not have backup overcurrent .

!

protection as required by the Technical Specifications Corrective actions for .

i

that condition included, among other things, a revision to the TRM (evaluated

i

,

!

under the provis!ons of 10CFR50,59) to reflect installation of backup

overcurrent protection and a review of the TRM against the computerized

"

electrical penetrations list and associated electrical design drawings to ensure

>

,

L

all electrical penetrations were adequately protected Both actions were_

-

tracked under LER 95-006 and Condition Report (CR) 95-1282 to ensure

'

l

completion.

l

V

i

..

' As a result of the latter corrective action (i e TRM review) minor.

. . ,

,

inconsistencies were identified in the TRM, Those inconsistencies did not

,

impact the primary and backup electrical protection for the containment

1

L

penetrations, On April 8,' 1996, an inter-office memo from Design Engineering

to Licensing personnel identified the discrepancies and committed to submit'

'

the changes impacting the TRM to Electrical Maintenance for incorporation

i

>

F

into the manual, in addition, the inter-office memo was submitted to Electrical

,

L

Maintenance (to process the TRM change) and in-House Events Analysis (to-

?i

close the action identified in CR 95-1282),

l

Site procedures W2,302, "10CFR50,59 Safety and Environmental impact

Evaluations," and W4,503, " Changes to the Technical Specification,

,

Technical Requirements Manual or Core Operating Limits Report," require all

'

- proposed TRM changes to be evaluated under the 50,59 process prior to

implementation Although TRM discrepancies were identified, personnel did

.

not promptly process a TRM change per site procedures nor did they utilize a:

tracking tool to ensure a TRM change was implemented.

_

_

,

.

-

I

'

t

(

!

- . ; # ,_ ._,-..._ ,- .. __

.m

,-,_-_. _.

.

,,

, _ . - , . , . _ . _ _ _ . _ . . _ . . _ . , . . , _

. -

.

-

,

.

Att:chment to

W3F1974276

,

Page 3 of 6

(2)-

Corrective Stoos That Have Been Taken and the Result 1 Achieved

TRM Change Request 98-001 has been initiated. That request has been

assigned to Electrical Maintenance and will provide a tracking mechanism to

ensure proposed changes to correct the TRM discrepancies are evaluated

under the 10CFR50.59 process.

Design Engineering / Electrical reviewed this condition during a staff meeting to

ensure department personnel understena expectatiens of the corrective

action process in relaying information to other departinents and the

importance of appropriately following up on the completion of corrective

actions.

The Licensing and lHEA departments have discussed this condition in

departmental staff meetings to accentuate the importance of action item

l

tracking and completion.

.

(3)

Corrective Stoos Which Will Be Taken to Avoid Further Violations

The desired changes to the TRM are being evaluated under the 10CFR50.59

process. Once that process is complete, the appropriate changes will be

incorporated.

(4)

Date When Full Comoliance Will Be Achieved

The appropriate TRM changes will be completed by March 2,1998.

'

,

Att: chm:nt to

'

VV3F197-0276

.

Page 4 of 6

(1)

Reason for the Violation (Example 2)

Waterford 3 acknowledges that a condition report was not initiated following

the discovery of a condition adverse to quality associated with Calculation EC- 101027. Revision 0. The apparent cause of that condition is inappropriate

action in that site procedure W2.501, " Corrective Action," Revision 6 (R6), was

not usod appropriately in deciding whether or not a condition repor1 should

have been written.

~

On March 21,1997, Design Engineering discovered a deficiency associated

with calculation EC 191027, Revision 0. The calculation failed to include

uncertainty allowances for the Containment Spray (CS) riser level instruments.

An evaluation of that enor determined CS riser indicated level could be a

much as 10 feet higher than actuallevel. Because the error could prohibit or

detract from the safe operation of Waterford 3, a condition report (CR 97-

0682) was, generated.

-

On April 21,1997, Licensee Event Report 97-011-00 reported that, due to the

uncertainty error, CS Riser level may have been less than required by

Technical Specifications (TS). However, the condition would not have

prevented the CS or Containment Cooling System or any other auxiliary

system required to ensure operability of those systems from performing their

specified safety functions.

During Refuel Outage 8 (RF08), the CS riser level instruments were replaced

with more accurate devices to reduce the calculated uncertainty The B Train

instrument was replaced on May 5,1997, under work Authorization (WA)

01159013 and the A Train instrument was replaced on May 12,1997, under

WA 01159014. The plant was in Mcde 6 (Refueling) at the time.

On May 20,1997, EC-191-027, Revision 1, was implemented in consequence

of the aforementioned instrument leplacements. Revision 1 included an

uncertainty factor to account for density changes in the water column being

measured in accordance with standard fluid calculation practices. On July 17,

1997, EC-191-027, Revision 2 was implemented to account for a change in the

TS allowed boron concentration in the Refueling Water Storage Pool.

While conducting IR 97-21, NRC inspectors noted the additional term for

density effects applied a biased effect that, absent any other considerations,

could cause the indicated CS riser level to be as mtah as 11.6 feet higher

than actuallevel. The inspectors questioned if the additional bias invalidated

previous conclusion : regarding safety significance.

In response to NRC questions, Waterford 3 personnel stated that, in their

judgment, changes to other assumptions in the oiiginal calculation would

.

>

.

.

Att: chm:nt to

'.

W3F197 0276

Page 5 of 6

offset the increase in uncertainty added by the density affects, but had not

confirmed that judgment. Furthermore, the application of density effects is a

standard practice and it is unlikely that effect would be missed on a broad

scale. IR 97-21 states the Inspectors considered the lack of consideration of

density effects in the original calculation to constitute a condition adverse to

quality, in that it was a source of error that should have been considered, and

for which its exclusion in this one instance, could imply its possible exclusion

from other level Instrument calculations.

W2.501 R6 defines a condition adverse to quality as a condition (or

deficiency) that could result in a degradation or challenge to nuclear safety.

At the time of discovery, personnel knew EC 191-027, Revision 0, affected

level instruments no longer installed in the plant. In addition, they believed

that changes to other assumptions in the original calculation would offset the

increase in uncertainty added by the density effect. That offset was later

confirmed and was all that was necessary to disposition the error in EC 191-

027, Revision 0. W2.501 does not require personnel to initiate a condition

report following the discovery of non significant issues that question past

operability.

Although personnel considered it unlikely for the density effect to be missed

on a broad scale and that belief was later confirmed, neither a confirmatory

review or a condition report was promptly initiated. In addition, an appropriate

level of supervisory review was not included in the decision making process.

The failure to promptly initiate a confirmatory review or a condition report for a

potential recurring deficiency constitutes a failure to comply with W2.501.

Pursuant to W2.501 and our commitment to ANSI N45.2.11, corrective actions

for significant or recurring calculation deficiencies require the initiation of a

condition report.

(2)

Corrective Steps That Have Been Taken and the Results Achieved

A condition report was generated.

On May 20,1997, EC-191-027, Revision 1, was implemented. Revision 1

included an uncertainty factor to account for density changes in the water

column being measured.

Design Engineering performed a review that confirmed the lack of

consideration of density effects in EC-191-0:!7, Revision 0, was offset by other

assumptions in the calculation.

A review of level calculations and selected pressure calculations was

performed. No other calculations were identified that failed to include the

water density factor.

l

!

_ _

_

_

_

.

___ _ ___ _ ___ _ _ _

.

.

.'

s

Attachm:nt to

'e

W3F197-0276

Page 6 of 6

in response to IR 97-16 dated November 24,1997, Waterford 3 identified the

need to emphasize the importance of communicating new information that

involves a potentially degraded or nonconforming condition, in consequence,

. on December 17,1997, the Director, Design Engineering, issued a

memorandum to all Design Engineering personnel providing expectations on

,

'

when to write a condition report and when to involve others in the decision

making process.

(3)

Corrective Steps Which Will Be Taken to Avoid Further Violations

This condition will be discussed during the next cycle of Engineering Support

Personnel (ESP) Continuing Training. Also, that training will include additional

examples of when to write a condition report and when to involve others in the

decision making process.

,

(4)

Date When Full Compliance Will Be Achieved

Full compliance has been achieved. The next cycle of ESP Continuing

L

Training is scheduled for Mwch,1998.

I