ML20199G030

From kanterella
Jump to navigation Jump to search
Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-454/97-16 & 50-455/97-16
ML20199G030
Person / Time
Site: Byron  Constellation icon.png
Issue date: 11/18/1997
From: Leach M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Graesser K
COMMONWEALTH EDISON CO.
References
50-454-97-16, 50-455-97-16, NUDOCS 9711250075
Download: ML20199G030 (2)


See also: IR 05000454/1997016

Text

.-

-

.

QtM

'

i

November 18 1997

Mr. K. Graesser

Site Vice President

Byron Nuclear Power Station

Commonwealth Edison Company

4450 North German Cnurch Road

Byron,IL 61010

'

SUBJECT:

NOTICE OF VIOLATION (NRC INSPECTION REPORTS 50-454/97016(DRS);

50-455/97016(DRS))

Dear Mr. Graesser:

This will acknowledge receipt of your letter dated October 29,1997, in response to our letter

dated September 30,1997, transmitting a Notice of Violation associated with the failure to notify

the NRC conceming proceduralinadequacies with Byron emergency operating procedure (EOP)

BEP-3," Steam Generator Tube Rupture," at the Byron Nuclear Power Station. We have reviewed

your corrective actions and have no further questions at this time. These corrective actions will be

examined during future inspections.

Sincerely,

Original Signed b.y Melv.vn Leach

Melvyn Leach, Chief

\\

Operator Licensing Branch

\\ \\

Docket Nos. 50-454; 50-456

License Nos. NPF-37; NPF 66

Enclosure:

Ltr dtd 10/29/97 K. L. Graesser

Byron to USNRC

See Attached Distribution

DOCUMENT NAME: G:DRS\\BYR11)]l,7.DRS

,.~s....n m e.c m .,en m

u.,c..cm m .w= =.=a.

r.cm.o. - ~ v.nem

OFFICE

Rlli

Ic Rlil

t

Rill

l

Rill

v

NAME

HPeterson:Jpt#*6AMJordan%4

- 3*^'-

N. 46

DATE

11A8/97

T 11//S/97

11/ /97

11/4/97

' 3 0 C .l 5) _

OFFICIAL RECORD COPY

Ao \\

ADOh h l54

Q

POR

__

.

I

,

K. Graesser

2

November 18, 1997

cc w/o encl:

O. Kingsley, Nuclear Generation Group

President & Chief Nuclear Officer

M. Wallace, Senior Vice President,

Corporate Services

H. G. Stanley, Vice President,

PWR Operations

Liaison Officer, NOC-BOD

D. A. Sager, Vice President,

Generation Support

D. Farrar, Nuclear Regulatory

Services Manager

1. Johnson, Licensing Operations Manager

Document Control Desk - Licensing

K. Kofron, Station Manager

D. Brindle, Regulatory Assurance

Supervisor

cc w/ encl:

Richard Hubbard

Nathan Schloss, Economist,

Office of the Attomey General

State Liaison Officer

State Liaison Officer, Wisconsin

Chairman, Illinois Commerco Commission

Dhkik.utiQD:

Docket File w/o enct

SRI, Byron w/o enci

. TSS w/o enci

PUBLIC IE 01 w/o encl

LPM, NRR w/o enct

CAA1 w/o enci

OCFO/LFARB w/o enci

A. B. Beach, Rlll w/o encI

DOCDESK w/o enci

DRP w/o enci

J. L. Caldwell, Rlli w/o encl

DRS w/o enct

Rlli Enf. Coordinator w/o enct

Rill PRR w/o enci

R. A. Capra, NRR w/o enci

_

.

..

-

,

i

Commonwealth Ihon Company

,

thwn Generating Station

4 441i Ninh t errnun C.hurch Ibud

l'i ti m 11 611818 6 '3*4 4

,

1 ri x i s .! * e 4 4 t t

October 29,1997

LTR:

BYRON 97-0242

FILE:

1.10.0101

U.S. Nuclear Regulator,

.nmission

Washington, DC 20555

Attention:

Document Control Desk

Subject:

Byron Nuclear Power Station Units 1 and 2

Response to Notice of Violation

Inspection Report No. 50-454/97016; 50-455/97016

NRC Docket Numbers 50-454, 50-455

l

Reference:

John A. Grobe letter to Mr. Graesser dated

September 30,1997, transmitting NRC Inspection

Report 50454/97016; 50-455/97016

Enclosed is Commonwealth Edison Company's response to the Notice of Violation (NOV)

which was transmitted with the referenced letter and Inspection Report. The NOV cited

one (1) Severity Level IV violation requiring a written response. Comed's response is

provided in the attachment.

This letter contains the following commitments:

1)

An LER will >e written in accordance with 10CFR50.73(a)(2)(v) & (vi)

documenting the concern

2)

The Reportability Manual will be revised to clarify the requirements for

reporting ofprocedural problems.

J[4+

(p $7b>hrr970242 doc)

. . s i e :' ' %!

' . em i e t 4 itup.mg

.

, - 4

'

.

Byron Ltr. 97-0242

October 29,1997

Page 2

Ifyour staff has any questions or comments concerning this letter, please refer t

Don Brindle, Regulatory Assurance Supervisor, at (815) 234-5441 ext. 2280.

Respectfully,

>/'sd

,

v

.

.

K. L. Grae

Site Vice President

Byron Nuclear Power Station

KLG/DB/rp

Attachment (s)

A. B. Beach, NRC Regional Administrator - RIII

cc:

G. F. Dick Jr., Byron Project Manager - NRR

Senior Resident inspector, Byron

R. D. Lanksbury, Reactor Projects Chief- RIII

,

'

F. Niziolek, Division of Engineering - IDNS

'

.

t

,

'

5

l

,

g-

g

4

g

n.

,.

._ ,,. , ,..

e

w

..-- .

, ,.,,,', , ,,,.

-., ,

'

,

--

. -.

.

,

.

ATTACilMENT 1

VIOLATION (454/455 97016-01)

Code of Federal Regulations Title 10 Part 50.72(b)(2)(iii) states, in part, that licensees

shall notify the NRC when practical and in all cases, within four hours of the occurrence,

"Any event or condition that alone could have prevented the fulfillment of the safety

function of structures or systems needed to: (D) httigate the consequences of an

accident."

l

'

Code of Federal Regulations Title 10 Part 50.73(a)(2)(v) states, in part, that licensees shall

report, "Any event or condition that alone could have prevented the fulfillment of the

safety function of structures or systems that are needed to: (D) Mitigate the consequences

of an accident."

Code of Federal Regulations Title 10 Part 50.73(a)(2)(vi) states that, " Events covered in

paragraph (a)(2)(v) of this section may include one or more personnel errors, equipment

failures, and/or discovery of design, analysis, fabrication, construction, and/or procedural

inadequacies "

Contrary to the above, the inspector identified that the licensee on February 19,1996, had

failed to notify the NRC concerning procedural inadequacies with Byron emergency

operating procedure (EOP) BEP-3, " Steam Generator Tube Rupture," and functional

restoration procedure BFR P.1, " Response to Imminent Pressurized Thermal Shock

Condition," which could limit operator response such that the EOP operator response time

limits documented in the Updated Final Safety Analysis Report may not be met.

This is a Severity Level IV violation (Supplement I).

(p 97byttir970242 dx)

-

. - -

- . . - - - . - - - -

. - . -

_ - . - - - - . . -- .-

.

,

'

w

REASON FOR THE VIOLATION

,.r

The original concern with the EOPs was identified on Feb. 19,1996 in Problem

Identification Form (PIF) 454 201 96-0298 written by the EOP Procedure Writer. The

concern was based on an Emergency Response Guideline (ERG) Direct Work Request

(DW) DW 89-077 that had been submitted to the Westinghouse Owners Group (WOG)

on November 10,1989 by Turkey Point. The EOP Procedure Writer had been reviewing

the WOG response to the DW and felt that the response was inadequate. He also felt that

the issue perteined to Byron Station, and therefore wrote the PIF. The DW postulated

that under some Steam Generator Tube Rupture (SGTR) scenarios it was possible that

j

i

cold Safety Irsection (SI) flow cor'd flow backwards through the Reactor Coolant System

(RCS) loop and out the SG break if the Reactor Coolant Pumps (RCPs) were not running.;

If this were to occur, it was further postulated that the cold SI flow might be such that the

wide range RCS loop thermocouples would indicate a temperature lower than that used as

,

. criteria for entry into Byron Functional Response procedure BFR-P.1, Response to-

{

~ Imminent Pressurized Thermal Shock Condition. Byron Emergency.*Nocedure BEP 3,

'

Steam Generator Tube Rupture, did not provide any guidance to the opomors that the

indication oflow temperature in the ruptured RCS loop was expected and that Pressurized

Thermal Shock (PTS) was not a concern Thus, if the operators exited BEP-3 in order to

follow BRP P.1, it was then postulated that they might use up so much time responding t

BFR P,1 that by the time they came back to BEP 3, the SG would have overfilled before

they had equalized RCS and SG pressurcs. Byron's Design Basis does not include overfill

,

i

of the SG's. Therefore, the issue was one of muting the operator response time to SGTR

assumed in the UFSAR. The DW response stated that "For most plants, it is expected

t

that for a SGTR with RCP: tripped, the operator will remain in E 3 to properly respond to

the SGTR."

f

The original PIF was reviewed for reportability by the Shift Manager. The Shift Manager

wrote that the PIF was "Not an operability issue at this time pending further review.

Concern involves response in the emergency procedures and should be addressed by

,

WOG." The Event Screening Committee also believed it was a generic WOG issue and

assigned the PlF to the Emergency Procedure writer for resolution as a Level 4 (Apparent

?

Cause Evaluation) PIF. The RA Supervisor consulted the Comed Reportability Manual.

Section SAF 1.17 of the manual addresses 10CFR50.72(b)(2)(iii) and

10CFRSO.73(a)(2)(v) & (vi). Procedure problems are covered by the following

paragraph:

. i

A plant procedure, approved but not yet used, that' has an

error which would cause a safety system to become

inoperable would be reportable. -If the error was

-

discovered before the procedure was approved, it would

not be reportable.

4

r

'. hl DhN242.400C)

?

._,

i

'

'

.--, - - , , . - , - - . - , , . - . , .

.-..--....,,,...._.m_..-,.,as-

L ...-... .

..-,_..,_,-~.._._.~s

--.

m.-..,,

-

____ ___ - -

.

.

.

The root cause of the violation was the inappropriate decision made by the Regulatory

Assurance Supervisor. The procedure problem did not "cause a safety system to become

inoperable " It appeared that several circumstances would have had to occur in order to

not meet the desy basis. but none of them included making a system inoperable. The

issue was also discussed with the RA Supenisor at Braidwood, who concurred with the

Byron RA Supenisors position. On 3/15/96, based on another review of the significance

level, the PlFs significance level was raised to Level 3 (Root Cause Repon), however it

was still believed that the event was not reportable.

At that time, Byron Station was not aware of any other utilities that had made an NRC

notification of the concem. Therefore, the Byron RA Supenisor made the decision that

the issue was not reportable.

The Byron Emergency Procedure Writer was not satisfied with the WOG response to

DW 89-077. On May 2,1996, he attended the WOG Operations Subcommittee meeting

and again raised the concem with the DFR P.1 issue. The WOG Ops Subcommittee

requested that he write another DW, which he did (DW 96-028). The DW was issued as

Category 4 (Feedback to provide clarification or improve guidance (NOT to correct an

error)). In early 1997 the WOG authorized a program to investigate operator action

times. On Feb. 28,1997, the WOG Ops Subcommittee issued a letter (OG 97-021) to

applicable utilities asking them to run selected time critical scenarios on the simulator,

video taping them if possible, and to provide the results of the operator response back to

the WOG. Byron and Braidwood both responded to the request. The WOG is reviewing

the various responses and expects to issue a fmal report by the end of 1997. The second

'

DW is still open.

CORRECTIVE STEPS TAKEN AND RESULTS ACHIEVED

in response to the originalissue with the BEP 3 and DFR P.1 procedures, it was realized

that there might be other operator response times assumed in the UFSAR that had not

been validated. Therefore, a Task Force was chartered to review those operator response

times that were known at that time. The Task Force has reviewed 18 items since, with 16

items being closed out. Most of them have not been determined to be of concern.

liowever, several of them will be periodically validated to ensure that operators continue

to meet the UFSAR assumed times.

n

As pan of the Task Force response to the issue of DEP 3 and BFR P.1, a procciute

change was made to BEP-3 that informed the operators that a low temperature condition

was expected on the ruptured loop, and that ifit occurred, to NOT go to BFR P.I. If the

operators do not go to BFR P.1, they have time to equalize RCS and 50 pressures prior

to SG overfill.

(p \\97hlus\\970242 dx)

.

..

. _ ___

_ _ _ _ _ - _ _ - - -

I

-

.,

.

o

'

The RA Supenisor has been counseled on conservative decision making with respect to

ENS notifications.

The Byron PA Supenisor has discussed this issue with the Braidwood RA Supervisor.

CORRECTIVE STEPS THAT WILL BE TAKEN 10 AVOID FURTHER VIOLATION

An LER will be written in accordance with 10CFR50.73(a)(2)(v) & (vi) documenting the

concern This is tracked by NTS item # 454 100-97-01601-01.

The Rep artability Manual will be revised to clarify the requirements for reporting of

procedural problems. This is tracked by NTS itera# 454 100 97-01601 02.

DATE WHEN FULL COMPLIANCE WILL BE ACHIEVED

Full compliance will be achieved 30 days from the date of this letter when the LER will be

submitted to the NRC.

.

'

__

. . _ .

,_

_....

- . - - . -

- - - - -

-