ML20199F036

From kanterella
Jump to navigation Jump to search
Insp Rept 50-344/97-05 on 971201-03.Violations Noted.Major Areas Inspected:Status of Dismantlement Activities,Changes to Util Emergency Exercise Plan Implementing Procedures & Decommissioning
ML20199F036
Person / Time
Site: Trojan File:Portland General Electric icon.png
Issue date: 01/23/1998
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20199F007 List:
References
50-344-97-05, 50-344-97-5, NUDOCS 9802030039
Download: ML20199F036 (13)


See also: IR 05000344/1997005

Text

_

_

_

. . . _

.

. . . . . .

_ _ _ _ _ _ _ _ _ _

.

ENCLOSURE 2

U.S. NUCLEAR REGULATORY COMMISSION

.

REGION IV

Docket No.:

50-344

License No.:

NPF 1

Report No.:

50 344/97-05

Licensee:

Portland General Electric Company

Facility:

Trojan Nuclear Plant

Location:

121 S, W. Salmon Street, TB-17

Portland, Oregon

Dates:

December 1-3,1997

Inspector:

J. V. Everett, Health Physics inspector

,

Approved By:

D. Blair Spitzberg, Ph.D., Chief

Nuclear Materials inspection and Fuel Cycle / Decommissioning

Attachment-

SupplementalInformation

9802030039 900123

PDR

ADOCK 05000344

G

PDR

- _ - - _ _ _ _ -

_ _ _ _ _ _ _ _ _ _

.

..

.

..

-2-

EXECUTIVE SUMMARY

Trojan Nuclear Plant

,

NRC Inspection Report 50-344/97-05

The Trojan facility had been undergoing active decommissioning and dismantlement for several

years. Estimated completion of the decommissioning was 2001. _ Structural components, tanks,

and piping were being removed from containment and the fuel / auxiliary building. Material that

was contaminated had been shipped for burial at Hanford. Material expected to be clean was

initially surveyed at the work area, then sent to a second area for final survey and eventual

release for sale as scrap metal. Workers observed during plant tours by the NRC inspector

were complying with radiological controls and restrictions. Housekeeping and fire loading was

acceptable and overall good safety practices were being implemented by tne workers. The

)

water clarity and condition of the spent fuel pool was good. No potential freezing problems due

to cold weather were identified.

Problems continued to occur with surveys of potentially contaminated matenals. Previous

problems associated with the adequacy of surveys for shipping containers destined for burial at

Hanford appeared to have been corrected. However, certain surveys of materials removed from

the radiologically controlled area had been identified as inadequate in 1997. The, resulted in the

release of some materials outside the radiologically controlled area that exceeded free release

limits. The licensee's review of the problem identified that similar inadequacies occurred with

certain materials released during earlier years. The licensee was being aggressive in identifying

the extent of the problem and had shown considerable commitment to co rect the problem.

Corrective actions recently initiated for future surveys should be effective in reducing

unintentional releases of contaminated material from the radiologically controll.*d area.

Sagot Fuel Pool Safetv

Spent fuel pool water level and temperature were conbrmed to be within the required

-

limits of the Trojan Technical Specifications. Water clarity was good. Dismantlement

work within the facility had not affected the spent fuel pool or associated systems

(Section 1).

Cold Weather Preoarations

A significant number of tanks and systems which contained water had been removed

from the Trojan facility. The few tanks that were operational did not appear to be

vulnerable to freezing damage considering the typical temperature rangts for the Trojan

area and the location of the tanks. Systems used to maintain the spent fuel pool were

located within the building and were not susceptible to freezing (Section 2).

_ - _ _ _ _ _ _

_ _ _ . . .

..

-,

,

f

p ..;

l

>

l

-3-

.

I

~ Decommisalonina Performance and Statum Review

- Disbiantlement activities were proceeding, and a large number of tanks had been -

.'

removed since the last inspection.-_ A tour of work areas indicated general conditions

_

were safe, housekeeping was acceptable, and fire hazards were low (Section 3).

- Control of Raeliaar+!ve haial and Contamina*ian

Accountability for sealed sources was being maintained by the licensee through an

.

annual inventory. The sources were being stored in locked cabinets (Section 4).

One violation concerning the discovery by the licensee of contaminated tools and

-

scaffolding outside the radiologically controlled area in excess of the release limits

specdied in the Trojan Decommissioning Plan was identified. The NRC has requested

that in response to the violation, the licensee is to take appropriate actions to locate and

resurvey tools and scaffolding that were removed from the radiologically controlled area.

-(Section 4).

Qf93rization. Manacement. and Cost Controls -

- Changes to the licensee's emergency plan implementing procedures submitted .

-

-

August 14,1997, were reviewed with the emergency preparedness engineer and found

.

- acceptable (Section 5).

Tbe site emergency exercise was conducted September 30,1997. The exercise

.

- involved a fire in containment and a medical emergency involving a potentially ,

contaminated individual. The licensee's evaluation found that all exercise objectives had -

been_successfully met (Section 5);

The year 2000 computer system prublem was being evaluated by a consultant to the

+=

- licensee. A number of tracking and scheduling systems were being evaluated to .

determine the magnitude of the problem for software used at Trojan (Section 5).

!

_ . .

..

.

.

,*

4

honort Detans

S1HDFnry of Plant Status

Dismantlement and decommissioning activines were in progress ut ue Trojan facility.

Noticeable dismantlement had occurred since the last inspection, especially in the area of tank

removal. Work had expanded into new rooms and new radiological controls wore observed at

severallocations.

Free release of radioactive material had received considerable attentien by the licensee over th3

past several months. Changes to the program had been made to strengthen controls to prevent

contaminated material from being released from the radiologically controlled area. A significant

effort had been initiated by the licensee to survey all areas of the site to locate contaminated

mateNs improperly released from the radiologically controlled area during past activities.

1

>ent Fuel Pool fiafety (60801,86700)

1.1

inspection Scooe

Technical Specifications for the spent fuel pool spacified water level and water

temperature limits. These limits were verified during this inspection. In addition, a tour of

the general area of the spent fuel pool was conductod to evaluate the structural condition

of the spent fuel pool walls and piping and verify that no dismantlement work was

underway that posed a threat to the structuralintegrity of the pool.

1.2

QbiciYahpn and Findinas

Trojan Technical Specification 3.1.1 required the spent fust pool water level to be

maintained at or above 22 feet ov9r the top of the spent fuel assemblies. The records for

the spent fuel pool water level for 1997 were reviewel. Water level was maintained

above 24 feet throughout the year with the lowest level recorded on November 11,1997,

at 24 feet 3 inches.

Trojan Technical Specification 3.1.3 required the spent fuel pool water temperature to be

maintained below 140' F. For 1997, the : vater temperature was typically maintained

between 50' F to 80' F. During December, a maximum temperature was recorded at

102' F. The licensee had allowed the temperature to increase in orde: to increase

,"

evaporation to make room for the transfer of water hcm the cask loading pit into the

spent fuel pool.

The steam reformer project was still underway and sorting of materialin the spent fuel

pool was observed. Some w1ter clouding around the work area in the fuel transfer canal

was observed; however, the water clarity around the spent fuel was good. A tour was

conducted of the various floors around the spent fuel pool. Work undeNvay to dismantle

_

.

. .

. - .

- . _ .

__

- _ - - - _ - _ _ _ - _ _

-

..

,

.-

i

.s.

tanks, pipes and systems did not appear to affect the systems associated with the spent

fuel pool. The licensee had implemented a program to ers .re that critical systems were

not deactivated. Prior to any dismantlemnt work in on area, a survy was completed by

engineering. Piping and cables that were not to be removed were marked with red tape.

A tour of several areas where dismantlement had been completed near the spent fuel

pool revealed several pipes that wera taped and had not been affected by the work

completed in the room.

1.3

Conclusion

Spent fuel pool water level and temperature were confirmed to be within the required

limits of the Trojan Technical Specifications. Water clarity was good. Dismantlement

work within the facility had not affected the spent fuel pool or associated systems.

2

Cold Weather Preparations (71714)

2.1

Insoection Scooe

A general review of the licensee's prosisions for cold weather protection was conducted.

Primary emphasis was placed on systems related to the spent fuel pool and tanks that

could leak contaminated water.

2.2

Observation and Findinos

A significant portion of the dismantlement effort at Trojan in 1997 was directed toward

removal of tanks. This eliminated much of the potential water inventory in the building.

Tanks inside the building that still had water included the dirty waste tank, clean waste

tank, trested waste tank, spent resin storaga tank and several s, umps. Outside the

building, water was still stored in the primary sater storage tank. This water contained

tntium. The Trojan facility was kept heated in most areas, with automatic switches to

activate heaters in selected areas. Weather conditions at Trojan are relatively mild with

few periods of hard freezing temperatures. Freezing of pipes had not been a problem in

the past.

Three systems with water were connected to the spent fuel pool. These were the cooling

system, the skimmer system, and the make-up water system. The demineralizer system

was connected to the coohng system. All three systems were within the heated

structure. The freezing potential for these systems appeared to be minimal.

,

An auxiliary operator had conducted routine plant tours each sh:9. Shifts were 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />

in length. Frocedure OG 13,100 entitled " Auxiliary Operator Rounds," Revision 18, was

1

used by the auxiliary operator. Step 4.4.1(r) directed the auxiliary operator to check

room temper:tures during the routine tours to detem1ine if temperatures were

appropriate for the time of year and to check heaters and coolers for proper operatior A

checklist was attached to the procedure to document the completed activities. The

I

l

..-

.

.

..

-6-

2

procedure also established a specific minimum temperature of 40'F for the diesel fire

pump room, otherwise the system was declared inoperable. Procedure POT 24 6," Shift

Operating Routines for Permanently Defueled Conditions," Revision 3, specified that if

i

temperatures were below 32'F, special attention should be directed toward equipment

supporting the spent fuel pool, fuel transfer tube which passes ti .mugh the auxiliary

building facade, demineralizer water line in containment and cond . ment heaters.

On June 30,1994, the licensee submitted to the NRC a response to NRC Bulletin 94-01,

  • Potential Fuel Pool Draindown Caused by inadequate Maintenance Practices at

Dresden Unit 1." A comparison of the 1994 response with the current procedures found

that procedural commitments were still in place for systems related to the spent fuel pool.

2.3

Conclusion

A significant number of tanks and systems which contained water had been removed

from the Trojan facility. The few tanks that were operational did not appear to be

vulnerable to freezing damage considering the typical temperature ranges for the Trojan

area and the location of the tanks. Systems used to maintain the spent fuel pool were

located within the building and were not susceptible to freezing.

3

Decommissioning Performance and Status Review (71801)

3.1

-Inspection Scope

The status of dismantlement activities was observed during a plant tour to evaluate work

conditions, housekeeping, and fire protection.

3.2 -

Observation and Findinos

The dismantlement work at Trojan was proceeding and significant work had been

completed since the last inspection. A larga number of tanks had been removed and

segmented for burial. Several tanks remaineo .. ,,ervice. A tour of tanks used to collect

water from the sumps was performed with the licensee.- This included observing the

control panel which indicated the status of active tanks and touring the area where the

tanks were located to verify that piping was still connected.

A discussion was held with the licensee concerning control of dismantlement activities to

ensure systems were not inadvertently deactivated or disconnected. Prior to work being

conducted in an area, the engineering department identified all systems that were not to

be dismantled and placed pink tape on the system. A tour of several work areas

included observation of the pink tape on selected systems.-

During the tour, the work areas were observed to be relatively free from unnecessary

trash Work areas appeared to be safe with no noticeable industrial hazards observed

during the tour. Fire loading was minimal and no fire hazards were observed.

I

_ _ _ _ _

-

i

..

.

..

7

Contamination areas were properly identified and posted. Radiation rope or tape was

evident to prevent unintentional entry.

3.3

Conclus10D

Dismantiement activities were proceeding with a large number of tanks removed since

the last inspection. A tour of work areas indicated general conditions were safe,

housekeeping was acceptable, and fire hazards were low.

4

Cot >.rol of Radioactive Material and Contamination (83726)

4.1

Inspection Scope

The licensee's program for control of sealed radioactive sources was reviewed to verify

the current inventory was accurate and provisions were in place to annually inventory

sources.

The site survey effort underway to determine if contaminated material had been

improperly released from the radiologically controlled area was reviewed. This effort

invcived a comprehensive survey of areas onsite where material was stored or placed

that could have been released from the radiologically controlled area. The effort was

part of the corrective actions committed to by the licenser in response to the Notice of

Violation issued with Inspection Report 50 344/97 03 dated September 9,1997,

4.2

Qhervation and Findinas

'

Technict.l Specification 5.9.2(e) required records to be maintained of the annual physical

inventory of sealed source material. In addition,10 CFR 20.1801 and 20.1802 require

security and controls for sealed sources. The annual physicalinventory sheet dated July

1997 was reviewed during this inspection. Them were 128 radioactive sources listed.

Most sources were stored in either the chemistry laboratory or the radiation protection

cabinet. The storage cabinets were kept locked. A random selection of ten sources was

identified from the inventory list. The radiation protection supervisor 'ocated all sources

selected.

NRC inspection conducted July 21-24,1997, resulted in issuance of a Notice of Violation

to the licensee on September 9,1997, related to the discovery of contaminated material

outside the radiologically controlled area. *lhe mateiial had been inadvertently released

from the radio'ogically controlled area during the final surveying process. The licensee

initiated a comprehensive effort to determine if additional contaminated material had

been released. This included surveying all buildings onsite where material was stored or

placed that had been removed from the radiologically controlled area.

On September 17,1997 a corrective action request (CAR-97-0024)'was initiated by the

licensee describing the discovery of additional radiological material outside the

w

-

..

.

.

8-

radiologically controlled area. A bucket was found on September 15,1997, by a

radiation protection technician outside the normal radiologically controlled area, but

inside a satellite radiologically controlled area, with fixed contamination on its bottom side

reading 1 million disintegrations per minute (dpm)/100 crd. The bucket had come from

the North American tool room. Surveys were conducted of the North American tool room

and shops plus the licensee's rnaintenance tool room and shops. Several additional

items were subsequently found which had fixed contamination levels of up to

25,000 dpm/100 cm' with one item reading 50,000 dpm/100 cnf. These items included

two welding leads, an electrical cord, socket, lifting eye, impact wrench, metal cable

sling, screwdriver, torque wrench, packing puller, and two shackles. All had fixed

contamination except for one item with smearable contamination. The licensee later

identified numerous other items, including scaffolding, that was found to be

contaminated.

Technical Specification 5.7.2.1 requires that procedures for personnel radiation

protection be prepared in a manner consistent with the requirements of 10 CFR 20 and

be approved, maintained, and adhered to for all operations involving personnel radiation

exposure.10 CFR 20.1501(a)(2)(li) requires that each licensee make, or cause to be

made, surveys that evaluate concentrations and quantitles of radioactive material. Limits

for the release of beta / gamma con'aminated material from the radiologically controlled

area at Trojan were established in the NRC-approved Trojan Decommissioning Plan,

Table 4.2.1, as 5,000 dpm/100 cnf average,15,000 dpm/100 cnf maximum, and

1,000 dpm/100 cm'smearable. The 5,000 dpm/100 cnf fixed and 1,000 dpm/100 cnf

smearable limits were also specified in Step 6.1 of Trojan Procedure 20-19, ' Release of

Materials from Radiologically Controlled Areas," Revision 1. Contrary to the above, the

inspector determined that a violation of Trojan Technical Specification 5.7.2.1 had

occurred due to the release of contaminated material from the radiologically controlled

urea exceeding both the average and maximum fixed contamination release limits of the

Trojan Decommissioning Plan and Procedure 2019 (Violation 50-344/9705-01). Despite

having been identified by the licensee, this violation is being cited because of

programmatic significance of the violation.

In the response by the licensee to the violation issued in inspection Report 50-344/97-03

dated September 9,1997, the licensee identified that between 1994 and 1997, tools

removed from the radiologically controlled area were offered for sale to the public.

Scaffolding was also loaned-out for personal use. As discussed during our telephone

exit on January 14,1998, a reasonable efforts is expected of Po-tland General Electric to

identify, locate and resurvey, tools and scaffolding that may have been removed frem the

radiologically controlled area and sold or released to members of the public during the

1994 through 1997 time frame. For all future releases of material from the site that were

not surveyed as part of the recent corrective actions effort, additional controls should be

identified that will preclude releases of contaminated material from the Trojan site in

excess of the limits approved in the Trojan Decommissioning Plan.

.

-

..

.

.,.

t

9

l

4.3

Conclusion

Accountability for sealed sources was being maintained by the licensee through an

annual inventory. The sources were being stored in locked cabinets.

I

One violation concerning the discovery by the licensee of contaminated tools and

scaffolding outside the radiologically controlled area in excess of the release limits

specified in the Trojan Decommissioning Plan and site radiological procedures was

identified. The NRC has requested that in response to the violation, the licensee is to

take appropriate actions to locate and resurvey tools and scaffolding that were removed

from the radiologically controlled area.

5

Organization, Managernent, and Cost Controls (36801)

5.1

Insoection Snom

The 1997 annual exercise and changes completed during the year to the emergency

plan implementing procedures were reviewed. In addition, the year 2000 computer

problem was discussed with the licensee to determine if any impact on licensee activities

relating to decommissioning was expected.

5.2

Qbservation and FindiDOS

On August 14,1997, the licensee submitted changes to its emergency plan

implementing procedures to the NRC. These changes included the addition and

clarification of terminology related to the emergency action levels and a new attachment

containing guidance and considerations for emergency classifications. These changes

were reviewed during this inspection with the emergency preparedness engineer and

found acceptable.

The annual exercise for Trojan wee conducted on September 30,1997, The scenario

involved a fire in containment which caused significant amounts of smone and the

explosion of several gas bottles exposed to the heat of the fire. A possibly contaminated-

worker was injured during evacuation of containment. The containment purge exhaust

pro-filters became plugged causing smoke to enter the fuel / auxiliary building through the

equipment hatch.

Offsite agencies and organizations that participated in the exercise included the Rainer

Rural Fire Protection District, St. John Medical Center, and Professional Communication

Servicec. Limited participation was provided by Columbia County and the Oregon Office

of Energy. Emergency response actions included offsite notifications, acJvation of the

emergency response organization, communications with offsite response organizations,

dispatching of inplant emergency teams, removal of an injured and contaminated person

from the site and treatment at St. John Medical Center, protective actions for onsite

personnel, and issuance of a news release.

I

_

_

-

..

.

.

10-

l

'

The strengths identified by the Trojan evaluation team included the response to the

scenano by the emergency team and the drillmanship of the players to deal with the

l

scenario events as if actual occurrences. No weaknesses were observed and all

23 exercise objectives were met. A number of observations and areas needing

improvement were identified including clarity and volume of the plant public address

system, coordination of information with the media representative, unavailability of a

radiation survey instrument during initial fire brigade response, and information flow

within the emergency response organization. Completion of the exercise satisfied the

annual exercise requirements in Section 0.1.3 of the Trojan Permanently Defueled

Emergency P:an, Revision 5.

Over the past several years, special concerns have surfaced related to the year 2000

software issue. This issue affects software that uses only the last two digits of the year

to perform calculations. When the year 2000 is reached, errors could be encountered for

any computer operation that subtracts dates.

Portland General Electric had hired a contractor to assist in determining which software

in use at the Trojan facility will encounter problems due to the year 2000 problem.

Examples of systems being evaluated included the work management system,

scheduling software, licensing tracking system, radiation information management

system, CAD system for plant drawings, fire protection tracking system, security access

control system, and iecords management system. There were no computerized systems

in the control room identified as beint susceptible to this problem.

5.3

Conclusion

Changes to the licensee's emergency plan implementing procedures submitted

August 14,1997, were reviewed with the emergency preparedness engineer and found

acceptable.

The site emergency exercise was conducted September 30,1997. The exercise

involved a fire in containment and a medical emergency involving a potentially

contaminated individual. The licensee's evaluation 'ound that all exercise objectives had

been successfully met.

The year 2000 computer system problem was being evalua'ed by a consultart hired by

the licensee. A numter of tracking and scheduling systems were being evaluated to

determine the magrytude of the problem for software used at Trojan.

6

Onsite Follow up of Written Reports on Nonroutine Actions (92700)

(Qpened and Closed) Licensee Event Reoort 50-344/9705-02: oH Limit Exceeds NEDES

Limit: On September 6,1997, Trojan notified the NRC Duty Officer that a violation of the

licensee's national pollution and discharge effluent system (NPDES) permit had

occurred. While rinsing a sodium bisulfite barrelin the discharge and dilution structure

. .

..

.

..

.

_ - - - _

- - _ - _ - - - _ - - - - - - - - - - - - - - - - - - - -

.

,.

.

.*

11

,

after refilling the sodium bisulfite tank, the licensee received a low pH alarm on the

control room annunciator for the discharge and dilution structure effluent pH monitor.

The minimum pH measured was 5.6 according to the recorder, and 5.3 based on a grab

sample. The lower limit for the licensee's discharge permit was 6.0. The licensee was

,

able to return the pH level to above 6.0 within approximately 10 minutes. The discharge

permit limit was not an NRC requirement or licensee technical specification requirement,

however, since the licensee notified the State of Oregon, then notification to the NRC

was required by 10 CFR 50.72(b)(2)(vi).

The licensee issued Corrective Action Request C 97 0021 and evaluated the event.

Approximately 24,000 gallons were released to the Columbia River outfall during the

period the pH level was below the permit limit. The licensee determined that other

methods of rinsing the barrels were available which would preclude recurrence of the

event and planned to develop procedural guidance on rinsing the barrels. The incpector

found the licensee's actions appropriate.

7

Exit Meeting

The inspector presented the inspection results to members of the license 9 management

and the Resident inspector for the Oregon Office of Energy at the exit meeting on

December 3,1997. The licensee acknowledged the findings presented. The licensee

did not identify as proprietary any information provided to, or reviewed by, the inspector.

On January 14,1997, a telephone followup exit briefing was conducted to discuss the

final results of the inspection as presented in the inspection report.

,

m

m

- -

-

- - .- - -

..-.._ - -.

- - -

- -

'

a.

.

.

.

ATTACHMENT

,

PARTIAL LIST OF PERSONS CONTACTED

Licensen

.

A. Bowman, Radiation Protection Supervisor

J. Cooper. Emergency Preparedness Engineer

M. Gatlin, Nuclear Security Manager

T. Meek, Radiation Protection Manager

D. Nordstrom, Nuclear Oversight Manager

H. Pate, Licensing Manager

S. Schnieder, Plant Operations Manager

State _of013900

,

A.' Bless, Resident inspector, Oregon Office of Energy

INSPECTION PROCEDURES USED

36801

Organization, Management, and Cost Controls at Permanently Shutdown Reactors

60801

Spent Fuel Pool Safety at Permanently Shutdown Reactors

71714

Cold Weather Preparations

71801

Decommissioning Performance and Status Review at Permanently Shutdown

Reactors

83726

Control of Radioactive Materials and Contamination, Surveys, and Monitoring

86700

Spent Fuel Pool Activities

92700

Onsite Follow-up of Wri* ten Reports of Nonroutine Events

ITEMS OPENED, CLOSED, AND DISCUSSED

Ooened

50 344/9705-01

VIO

Free Release of Contaminated Material

50-344/9705-02

IFl

pH Limit Exceeds NPDES Limit

GQind

50-344/9705-02

IFl

pH Limit Exceeds NPDES Limit

Discussed

None

,

4

, - , _ _ , , _ . , . . . _ _ , _

. . , , _ , , _ - -

,

.

,.,,y,~

y,,,,

, -.

.-,-y

.

...

m..

.._-, ,

.

.g.

.

O'

2

LIST OF ACRONYMS

cm

centimeter

CFR

Code of Federal Regulations

dpm

disintegrations per minute

mrem

milli Roentgen equivalent man

mSv

milli Sievert

NPDES

National Pollution and Discharge Emuent System

PDR

Public Document Room

ppm

parts per million

rem,

Roentgen equivalent man

Sv

' Sievert

_

_

__