APPEf1 DIX B
U.S. f:UCLEAR REGULATORY C0fMISSION
REGI0ft IV
flRC Inspection Report: 50-285/86-10
License:
Docket:
50-285
Licensee: Omaha Public Power District
1623 Harney Street
Omaha, Nebraska , 68102
Facility Name:
Fort Calhoun Station
Inspection At:
Fort Calhoun Station, Blair, Nebraska
Inspection Conducted: April 1-30, 1986
4
- 4
Inspector:
.
D(te'
(
T. W. harrell7 Senior /esident Reactor
- F Inspector
'
dA
Approved:
,
Mte '
-
D. R. Hunter, Chief, Project Section B,
Reactor Projects Branch
Inspection Surmiary
i
I
Inspection Conducted April 1-30, 1986 (Report 50-285/86-10)
i
Areas Inspected: Routine, unannounced inspection including operational safety
verification, maintenance, surveillance, plant tours, safety-related system
walkdowns, followup on licensee event reports, and followup on a
l
request from the NRC regional office regarding shipment of uranium hexafluoride
j
cylinders.
Results: Within the seven areas inspected, one violation (an inadequate
physical barrier for ' he protected area, Appendix A) was identified.
!
!
ENCLOSURE CONTAINS
I
SAFEGUARDS INFORMATION.
60S
UPON SEPARATION THIS
f
61gg$5000205
PAGE IS DECONTROLLED.
g
l
i
.
'
.
-2-
DETAILS
1.
Persons Contacted
- W. Gates, Plant Manager
C. Brunnert, Operations Quality Assurance Supervisor
M. Core, Maintenance Supervisor
D. Dale, Quality Control Inspector
J. Fisicaro, Nuclear Regulatory and Industry Affairs Supervisor
J. Foley, I&C and Electrical Field Maintenance Supervisor
M. Kallman, Security Supervisor
L. Kusek, Operations Supervisor
T. McIvor, Technical Supervisor
R. Mueller, Plant Engineer
C. Norris, Radiological Services Supervisor
G. Roach, Chemical and Radiation Protection Supervisor
J. Tesarek, Reactor Engineer
S. Willrett, Administration Services and Security Supervisor
- Denotes attendance at the monthly exit interview.
The inspector also contacted other plant personnel, including operators,
technicians, and administrative personnel.
2.
Followup on Previously Ideatified Items
(Closed) Open Item 8602-03:
Replacement of a railroad tie support for
a uranium hexafluoride (UF6) cylinder.
The licensee completed shipment of the UF6 cylinders from the
site on April 15, 1986.
Replacement of the railroad tie was no
longer required.
(Closed) Open Item 8602-09:
Removal of dead vegetation in the UF6
storage area.
,
The licensee completed shipment of the UF6 cylinders from the
site on April 15, 1986.
Removal of the dead vegetation was no
longer required.
3.
Licensee Event Report (LER) Followup
Through direct observation, discussions with licensee personnel, and
review of records, the following event reports were reviewed to determine
that reportability requirements were fulfilled, immadiate corrective
action was accomplished, and correct:ve action to prevent recurrence has
been accomplished in accordance with Technical Specifications.
ENOLOSU3E CONTAIUS
SAFEGUARDS INFORMATION.
UFON SEFARATION IMIS
PAGE IS DE003 TROLLED.
.
.
--
-
-- .
'
.
-3-
The LERs listed below were closed:
85-10 Relay failure during a surveillance test
85-11 Loss of offsite power during a refueling outage
85-12 Failure to properly post a fire watch
LER 85-10 reported a problem with an 86-type lockout relay that failed to
properly function during a monthly surveillance test.
The relay is part
of the containment spray logic and was being tested during a refueling
shutdown.
The licensee determined that the reason for the relay failure
to operate properly was due to a contact being out of adjustment.
The
contact was adjusted, the relay reinstalled, and the test performed.
No
additional problems were noted.
The licensee checked other 86-type
lockout relays but noted no other problems.
LER 85-11 discussed an event that occurred during performance of
maintenance activities on the electrical distribution system.
While in a
refueling shutdown, the plant was in an altered electrical lineup when an
individual performing maintenance on the transformer supplying onsite
electrical loads from offsite inadvertently tripped the incorrect relay
causing a loss of offsite power.
The loss of offsite power caused the
loss of power to all 480-volt AC buses,125 volt DC bus 2, and 125 volt AC
instrument buses B and D.
The buses were reenergized within approximately
30 minutes.
Even though the electrical distribution system was degraded,
no safety significant problems were encountered.
The licensee has
reviewed this problem with operating personnel to ensure personnel do not
place the plant's electrical distribution system in a position where loss
of one power source will degrade the system.
The licensee also stressed
to operating personnel, the need for controlling maintenance activities to
ensure maintenance is not performed on redundant equipment at the same
time.
The licensee stressed to maintenance personnel the importance of
ensuring the component being worked on is the correct one.
LER 85-12 reported the failure to properly post a fire watch when the
Halon system for the switchgear room was secured.
The failure to properly
establish a continuous fire watch was determined by the license. to be due
to personnel not clearly understanding the fire watch requireme rts.
Instead of posting a full-time fire watch as required by the Technical
Specifications, the fire watch was posted only during welding activities.
The licensee has revised the procedures that establish the requirements
for posting and maintaining fire watches.
It appears that the revised
procedures will establish the necessary requirements to ensure fire watch
activities will be properly controlled in the future.
No violations or deviations were identified.
4.
Followup on a Regional Request
Based upon a request from Region IV, the NRC inspector reviewed the
licensee's activities associated with shipment of the uranium hexafluoride
(UF6) cylinders offsite.
The licensee shipped 52 cylinders to a
ENCLOSUEBCONTAINS
SAFEGUARDS INFOP2ATION.
UPON SEPARATION THIS
PAGE IS DECONTROLLED.
_
_
_
_
-
.
-4-
Department of Energy facility in Paducah, Kentucky, via semitrucks.
Shipment of the cylinders commenced on April 4 and was completed on
April 15, 1986.
The NRC inspector observed licensee activities associated with the
preparation and loading of the cylinders.
This review was performed to
verify that activities were conducted in accordance with approved
procedures and Materials License SMC-1420.
The items reviewed / observed by
the NRC inspector are listed below:
Lifting equipment had been satisfactorily tested prior to use
.
Appropriate individuals were present during lifting and shipping
.
operations
Job briefings were performed prior to commencing activities
.
Each individual involved in the lifting and shipping activities were
.
trained in appropriate actions in the event of a cylinder rupture or
other anomaly
Radiation surveys were performed prior to departure of cylinders from
.
the site
Cylinders were inspected and determined to be structurally
.
. satisfactory before shipment
Repair to cylinders was performed for the cylinders requiring repair
.
Plant review committee. approved procedures were used and followed
.
Documentation for offsite shipment was completed
.
Based on the reviews performed and observations by the NRC inspector, it
appears that the licensee completed shipment of the UF6 cylinders in
accordance with procedures and other requirements.
No violations or deviations were identified.
5.
Performance of a Regulatory Effectiveness Review
A team of inspectors from the NRC's Nuclear Material Safety and Safeguards
(NMSS) Office performed a review of the security program at the plant
site.
The review was performed from April 28 to May 2 and included a
detailed evaluation of the licensee's security program.
The senior
resident inspector participated as a member of the review team.
The
results of the review will be discussed in detail in a report to be issued
by NMSS.
ENCLOSEM?CONTAINS
SAFEGUARDS INFORMATION.
UPON SEPARATION THIS
PAGE IS DE00NTROLLED.
- _______________ _
. _ - - _
.
-S-
6.
Operational Safety Verification
The NRC inspector conducted the reviews and observations described below
to verify that facility operations were performed in conformance with the
requirements established under 10 CFR, administrative procedures, and the
Technical Specifications.
The NRC inspector made several control room
~
observations to verify:
Proper shift staffing
.
Operator adherence to approved procedures and Technical
.
Specifications
Operability of reactor protective system and engineered safeguards
.
equipment.
Logs, records, .ecorder traces, annunciators, panel indications, and
.
switch positions complied with the appropriate requirements.
Proper return to sers'ce of components.
.
Maintenance orders had been initiated for equipment in need of
.
maintenance.
Appropriate conduct of control room and other licensed operators.
.
No violations or deviations were noted.
7.
Plant Tours
The NRC inspector conducted plant tours at various times to assess plant
and equipment conditions.
The following items were observed during the
tours:
General plant conditions.
.
Equipment conditions, including fluid leaks and excessive vibration.
.
Plant housekeeping and cleanliness practices including fire hazards
.
and control of combustible material.
The physical security plan was being implemented in accordance with
.
the station security plan.
Adherence to the requirements of radiation work permits.
.
Work activities being performed in accordance with approved
.
procedures.
During a tour of the plant, the NRC inspector noted that a protected area
security barrier was not being maintained in accordance with requirements.
ENCLO9EE CONTAINS
SAFEGUARDS INFOR.*ATION.
UPON SEPARATION THIS
PAGE IS DECONTROLLED.
1
~
I
i
r
.
,
-6-
The discussion of the details of this occurrence contains safeguards
information, as defined in 10 CFR Part 73.21; therefore, the details are
discussed in the attachment to Appendix A of this inspection report.
8.
Safety-Related System Walkdowns
The NRC inspector walked down accessible portions of the following
safety-related systems to verify system operability.
Operability was
determined by verification of valve and switch positions.
The systems
were walked down using the drawings and procedures noted:
Auxiliary feedwater system (Drawings M-253, Revision 50 and M-254,
.
Revision 55, and Procedures OI-FW-4, Revision 28 and 01-AFW-1,
Revision 1).
Raw water system (Drawing M-100, Revision 26 and Procedure 01-RW-1,
.
Revision 13).
During the walkdowns, the NRC inspector noted minor discrepancies of an
editorial nature between the drawings, procedures, and plant as-built
,
conditions.
None of the conditions noted affected the operability or safe
operation of the system.
Licensee personnel stated that the noted minor
discrepancies would be corrected.
During the previous inspection period, as a result of a system walkdown,
the NRC inspector noted discrepancies in the procedure and on the station
-
one-line electrical diagram for the plant.
At the end of the inspection
period, the NRC inspector was still attempting to resolve the
discrepancies with licensee personnel.
The licensee has resolved the
discrepancies and has determined that the discrepancies do not affect the
operability or safe operation of the plant.
The NRC inspector concurred
with tha results of the licensee's review.
In an effort to upgrade system
procedures and drawings, the licensee has instituted a program to perform
wa14 downs of all plant systems.
The result of the program will be
procedures and drawings that will reflect the as-built plant.
No violations or deviations were identified.
9.
Monthly Maintenance Observation
The NRC inspector observed station maintenance activities of
safety-related systems and components to verify the maintenance was
conducted in accordance with approved procedures, regulatory requirements,
and the Technical Specifications.
The following items were considered
during the observations:
The limiting conditions for operation were met while systems or
.
components were removed from service.
Approvals were obtained prior to initiating the work.
.
ENCI,0SUFI CONTAINS
SAFEGUARDS INF03'.'ATION.
UPON SEPARATION THIS
PAGE IS DECONTROLLED.
_ - - _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
=
.
-7-
Activities were accomplished using approved maintenance orders (MO)
.
and were inspected, as applicable.
Functional testing and/or calibrations were performed prior to
.
returning components or systems to service.
Quality control records were maintained.
.
Activities were accomplished by qualified personnel.
.
Parts and materials used were properly certified.
.
.
Radiological and fire prevention controls were implemented.
The NRC inspector observed the following maintenance activities:
Radiation portal monitor annual calibration (CP-PM/8).
.
Evacuation of UF6 cylinders (SP-UF6-3).
.
Replacement of valve on UF6 cylinders (M0 861469).
.
Loading of UF6 cylinders (M0 861454).
.
No violations or deviations were noted.
10. Monthly Surveillance Observation
The NRC inspector observed the Technical Specification required
surveillance testing on safety-related systems and components.
The NRC
inspector verified the following items during the testing:
!
Testing was performed using approved procedures.
.
Test instrumentation was calibrated.
.
Limiting conditions for operation were met.
.
Removal and restoration of the affected system and/or component were
.
accomplished.
Test results conformed with Technical Specification and procedure
.
requirements.
Test results were reviewed by personnel other than the individual
.
directing the test.
Deficiencies identified during the testing were properly reviewed and
'
.
resolved by appropriate management personnel.
I
'
E:ICLCXJRE CO:rtAIng
SAIEGUARDS INFORY.ATION~
,
UPON SEPARITION THIS
j
-
..
,
-8-
The NRC inspector witnessed the following surveillance test activities.
The procedures used for the test activities are noted.
Station battery checks (ST-0C-1-F.1).
.
Auxiliary feedwater pump check (ST-FW-1-F.2).
.
Diesel generator monthly test (ST-ESF-6-F.2).
.
Containment hydrogen monitor checks (ST-VA-6-F.2).
.
No violations or deviations were identified.
11.
Exit Interview
The NRC inspector met with Mr. W. G. Gates (Plant Manager) at the end of
this inspection.
At this meeting, the inspector summarized the scope of
the inspection and the findings.