Requests Review of Allegations Re Cracking of Cavity Liner Plates & Failure to Remove Two or Three 5-gallon Cans of Trash Prior to Concrete Placement in Unit 1 Containment Wall
ML20198J986
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 05/30/1986
From: Westerman T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Counsil W
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
References
NUDOCS 8606030274
Download: ML20198J986 (2)


Text

f .s [

  • L;

-w  %~..g. , , , . .

1 3 -

,% W -

~ ,

AY 3 01386 sj ,gg[j s',  % ,i

. y

} ., t .

4 y' ' , ' '

q u ' , t N.f ,, n Li A w ~

c
c ,-
  • * - +

/

Ef 4 . + $, ~e m j')

In Ra' ply.Refar To: , ., . , ,

/

M Dockets: 50-445- 4

,i ~ /

'50-446 L N' s

um_ r.

4 ,

2 ~

1

~ u "'

Texas Utilities Generating Company JATTN Mr. W. G. Counsil 4 Executive Vice President 400 North Olive, Lock Box 81 Dallas, Texas ^75201

Reference:

4-86-A-019

-Gentlemen:

We hereby request that you review the attached allegations received by NRC that relate to your operations.. As part of your review, we furthermore

. request that you conduct whatever inspections or investigations necessary to reasonably prove or disprove the allegations. .Should your review of the allegations bring into question a safety issue (such as the adequacy of a safety component, system, or analysis), we expect that that issue will be promptly brought to our attention.

A substantiated allegation may warrant corrective action, and we would expect you to'be prompt and diligent in implementing such corrective measures.

Therefore, we request for the following two potentially safety related allegations that you periodically inform NRC of the resolution of these matters and make records of your completed action available for NRC inspection. It is alleged that:

1.- ~There was cracking of the cavity liner plates. The alleger recommended

that the cracking problem be looked at generically based on lot and heat number.
2. ~Two or three five gallon cans of trash were not removed prior to concrete placement in the Unit I containment wall'at a location 50 feet from the L- personnel airlock in the WNW wall and at the same elevation as the personnel airlock.

The following allegations are forwarded to you for your information.

.1. There'is spider web cracking of the main condenser tube sheets.

'2. The radius and taper of the Squaw Creek Reservoir is not in accordance

. with design. The fill for the dam was made in some _ cases in 18-inch lifts vice the 6-inch lift opecified by procedure. .(Region IV is concurrently informing'the State of Texas on this issue.).

- RIV:ACf EO C:RSB DRSPM[

MEmerson DAPo ers TWesterman EHJohnson tin b /$ /86 6/p'/86 [/9/86 ( / 3/86 86 8606030274 860530

~

PDR ADOCK 05000445 P PDR

s ,. **

3. The main circulating water pump intake baffles were improperly fitup (gap) and the proper weld procedures were not followed. In addition, the

" emergency' gates" retaining insert for the main circulating water pump is not properly attached structurally. _

4 Should you have any questions concerning our requests or our role in these matters, please contact our Allegations Coordinator, Mark Emerson at (817) 860-8100.

Sincerely, ,

Thomas F. Westerman "

Reactor Safety Branch cc:

Texas Utilities Electric Company

' ATTN: G. S. Keeley, Manager ,

Licensing Skyway Tower 400 North Olive Street Lock Box 81 Dallas, Texas 75201 Juanita Ellis President - CASE 1426 South Polk Street Dallas, Texas 75224 Renea Hicks Assistant Attorney General Environmental Protection Division P. 0.. Box 12548 Austin, Texas 76711 Texas Radiation Control Program Director bec:

, M. Emerson, AC V. Noonan, NRR

'L. Ellershaw, RSB S. Trelby,. ELD

-I. Barnes, CPTG RRI-OPS T. Westerman, RSB RRI-CONST E. Johnson, DRSP RIV Files R. Bangart, DRSS DMB (IE31) se '

R. Martin, RA l