Interim Deficiency Rept DER 85-38 Re Oa Audit at Ge. Initially Reported on 851108.Due to Need for GE to Retrieve Further Documentation,Final Rept Delayed Until 860612,per 860103,0214 & 0313 Ltrs
ML20198F005
Person / Time
Site: Palo Verde  Arizona Public Service icon.png
Issue date: 05/14/1986
From: Van Brunt E, Van Brunt S
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To: Kirsch D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
ANPP-36581-EEVB, DER-85-38, NUDOCS 8605280386
Download: ML20198F005 (2)


Text

..

o RECEIVED Arizona Nuclear Power Project U S pay ;g pp P.o. Box 52034 e PHOENIX, ARIZONA 85072-2034 bh May 14, 1986 PE(;p ANPP-36581-EEVB/LAS/DR1k'.11 U. S. Nuclear Regulatory Commission Region V 1450 Maria Lane - Suite 210 Walnut Creek, CA 94596-5368 Attention:

Mr. D. F. Kirsch, Acting Director Division of Reactor Safety and Projects Palo Verde Nuclear Generating Station (PVNGS)

Units 2 and 3 Docket No. 50/529, 530

Subject:

Time Extension For Report - DER 85-38 A 50.55(e) Potentially Reportable Deficiency Relating to QA Audit at General Electric File: 86-006-216; 86-056-026; D.4.33.2

Reference:

(A) Telephone Conversation between A. Hon and T. P. Siegfried on November 8, 1985 (Initial Reportability - DER 85-38)

(B) ANPP-34165, dated December 4, 1985 (Interim Report - DER 85-38)

(C) ANPP-34397, dated January 3, 1986 (Time Extension - DER 85-38)

(D) ANPP-35134, dated February 14, 1986 (Time Extension - DER 85-38)

(E) ANPP-35514, dated March 13, 1986 (Time Extension - DER 85-38)

(F) ANPP-36090, dated April 14, 1986 (Interim Report, Rev. 1 - DER 85-38)

Dear Sir:

The NRC was notified of a Potentially Reportable Deficiency in Reference (A),

Interim Reports by Reference (B) and (F), and Time Extensions by References (C),

(D), and (E).

Due to a need for GE to retrieve further documentation that is required for evaluation, it is now expected that the Final Report will be submitted by June 12, 1986.

There is no new information or change to the Interim Report at this time.

Very truly y urs W

4 M E. E. Van Brunt, Jr.

Executive Vice President Project Director EEVB/DRL/.ld f 8605280386 860514 Idf/001/TE85-38 pon ApocK 05000529 1 0 8

PDR I

ea8 @GG Ctmo TbD

$U

3 O'

Q ANPP-36581-EEVB/LAS/DRL-92.11 May 14, 1986 DER 85 Time Extension Mr. D. F. Kirsch Acting Director Page Two cc:

J. M. Taylor, Director Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555 A. C. Gehr (4141)

R. P. Zimmerman (6295)

Records Center Institute of Nuclear Power Operations 1100 Circle 75 Parkway - Suite 1500 Atlanta, Georgia 30339 Idf/009/ FORM-7