|
---|
Category:SAFETY EVALUATION REPORT--LICENSING & RELATED ISSUES
MONTHYEARML20210P9181999-08-10010 August 1999 Safety Evaluation Authorizing Request for Reliefs CIP-01,02, 06,07,08,09,10 & 11 (with Certain Exceptions) & 12-18,for Second 10-year ISI Interval.Request CIP-04 & 05 Would Result in hardship,CIP-03 Not Required & CIP-11 Denied in Part ML20210P9441999-08-10010 August 1999 Safety Evaluation Accepting Licensee Assessment of Impact on Operation of Plant,Unit 1,with Crack Indications of 2.11, 6.36 & 1.74 Inches in Three Separate Jet Pump Risers ML20210N2341999-08-0505 August 1999 SER Accepting Response to NRC GL 87-02, Verification of Seismic Adequacy of Mechanical & Electrical Equipment in Operating Reactors,Unresolved Safety Issues (USI) A-46 ML20206G1871999-05-0404 May 1999 Safety Evaluation Approving Third 10-year ISI Program Requests for Relief (RR) RR-08,RR-15 & RR-17 ML20205F9031999-03-30030 March 1999 Safety Evaluation Supporting Proposed Rev to BSEP RERP to Licenses DPR-62 & DPR-71,respectively ML20203D7061999-02-0909 February 1999 SER Accepting Proposed Alternatives Contained in Relief Requests PRR-04,VRR-04,VRR-13,PRR-01,PRR-03,VRR-01.VRR-07, VRR-08 & VRR-09 Denied ML20154P8151998-10-16016 October 1998 SER Accepting Revised Safety Analysis of Operational Transient of 920117,for Plant,Unit 1 ML20154P8591998-10-16016 October 1998 SER Accepting Equivalent Margins Analysis for N-16A/B Instrument Nozzles for Plant,Units 1 & 2 ML20217K8461998-04-24024 April 1998 Safety Evaluation Approving Proposed Use of Code Case N-535 at Brunswick Unit 1 During Second 10-yr Interval,Pursuant to 10CFR50.55a(a)(3)(i).Authorizes Use of Code Case N-535 Until Code Case Included in Future Rev of RG 1.147 ML20217K3941998-04-24024 April 1998 SER Approving Relief Request for Pump Vibration Monitoring, Brunswick Steam Electric Plant,Units 1 & 2 ML20217E6841998-04-23023 April 1998 Safety Evaluation Accepting Code Case N-547, Alternative Exam Requirements for Pressure Retaining Bolting of CRD Housings ML20217E7471998-04-21021 April 1998 Safety Evaluation Accepting Alternative to Insp of Reactor Pressure Vessel Circumferential Welds ML20217B5241998-04-20020 April 1998 SE Accepting Licensee Request for Approval to Use Alternative Exam Requirement for Brunswick,Unit 1,reactor Vessel Stud & Bushing During Second 10-yr ISI Interval Per 10CFR50.55a(a)(3)(ii) ML20216B1041998-03-0404 March 1998 SER Approving Alternative to Insp of Reactor Pressure Vessel Circumferential Welds for Brunswick Steam Electric Plant, Unit 1 ML20198J0921997-09-18018 September 1997 Safety Evaluation Authorizing Licensee & Suppls & 16 Request for Approval of Alternative Reactor Vessel Weld Exam,Per 10CFR50.55a(g)(6)(ii)(A)(5) for Plant, Unit 2 for Next 2 Operating Cycles ML20198H2351997-09-0808 September 1997 Safety Evaluation Approving Licensee 970311 Request for Use of ASME Code Case N-509 & Relief from ASME Code Section IX Requirements for Exam of Hpcip Studs for Plant,Units 1 & 2 ML20137A4831997-03-18018 March 1997 SER Re CP&L Review of Power Uprate Process & Commitment Preventing Operation at Uprated Power Levels for Plant, Units 1 & 2 ML20129E0821996-09-26026 September 1996 Safety Evaluation Supporting Request to Use Certain Portions of Later Edition of ASME Code for Inservice Leakage Testing Valves for Brunswick Steam Electric Plant Units 1 & 2 ML20056D6761993-07-28028 July 1993 Safety Evaluation Concluding That Interior Masonry Walls May Be Downgraded to non-fire Related ML20128K7711993-02-11011 February 1993 Safety Evaluation Granting Relief from Certain Inservice Testing Program Requirements for Several Pumps & Valves ML20198E5081992-11-23023 November 1992 Safety Evaluation Accepting Licensee 120-day Response to Suppl 1 to GL 87-02 ML20246D6811989-08-18018 August 1989 Safety Evaluation Supporting Installation & Design of Nitrogen Pneumatic Sys,Per Generic Ltr 84-09,by Adding New Check Valves to Existing Drywell Noninterruptible Instrument Air Lines ML20246C4201989-06-27027 June 1989 SER Accepting Util Response to Generic Ltr 83-28,Item 4.5.3 Re Reactor Trip Sys Reliability for All Operating Reactors ML20247P6201989-06-0101 June 1989 Safety Evaluation Supporting Util SAFER/GESTR-LOCA Analysis ML20247M1911989-05-25025 May 1989 Safety Evaluation Re Denial of Amend Request to Licenses DPR-71 & DPR-62 ML20246P9401989-05-10010 May 1989 Safety Evaluation Accepting Plant Second 10-yr Interval Inservice Insp Program ML20246J5531989-05-0909 May 1989 Safety Evaluation Concluding That Plant Can Be Safely Operated for Another 18-month Fuel Cycle in Configuration Following Reload 5,per Improvements,Insps & Repairs to Plant IGSCC ML20245D3761989-04-25025 April 1989 Safety Evaluation Supporting Licensee IGSCC Program for Refuel 7 Outage ML20236D5481989-03-17017 March 1989 Safety Evaluation Accepting Util Response to Generic Ltr 83-28,Item 4.5.2 Re Reactor Trip Sys Reliability ML20236D5381989-03-17017 March 1989 Safety Evaluation Accepting Util 831107 Response to Generic Ltr 83-28,Item 2.2.1 Re Equipment Classification Programs for safety-related Components ML20236D4641989-03-15015 March 1989 Safety Evaluation Re Generic Ltr 83-28,Item 2.1 (Parts 1 & 2) Concerning Equipment Classification & Vendor Interface for Reactor Trip Sys Components ML20235Z2841989-03-0808 March 1989 Safety Evaluation Supporting Util Responses to Generic Ltr 83-28,Items 3.2.1 & 3.2.2 ML20235Z3451989-03-0808 March 1989 Safety Evaluation Supporting Util Compliance W/Atws Rule, 10CFR50.62 Re Power Testability Features of Alternate Rod Insertion Sys & Recirculating Pump Trip Design ML20235M5771989-02-16016 February 1989 Safety Evaluation Supporting Control Room Habitability Sys of Plant & Acceptability of Existing Tech Spec Re Control Room Pressurization Requirement ML20147G0661988-03-0202 March 1988 Safety Evaluation Supporting Proposed Functional Testing Plan for Snubbers ML20236D1311987-10-22022 October 1987 Safety Evaluation Re Util Request for Relief from Schedular Requirements for Performance of Visual Insp & Hydrostatic Test of CRD Withdrawal & Insert Lines.Granting of Request Recommended ML20235A7331987-09-18018 September 1987 Safety Evaluation Re Installation of Alternate Rod Injection (ARI) Sys & Adequacy of Plant Reactor Coolant Recirculating Pump Trip (RPT) Sys,In Compliance W/Atws Rule 10CFR50.62. ARI & RPT Acceptable NUREG-0661, Safety Evaluation Re Util 840831 Submittal of Addendum to Plant Unique Analysis Rept on Mark I Containment Mod Program.Safety/Relief Valve Load Cases C3.2 & C3.3 Adequately Addressed & Resolved1987-05-0707 May 1987 Safety Evaluation Re Util 840831 Submittal of Addendum to Plant Unique Analysis Rept on Mark I Containment Mod Program.Safety/Relief Valve Load Cases C3.2 & C3.3 Adequately Addressed & Resolved ML20212H5671987-01-16016 January 1987 Safety Evaluation Supporting Util Response to Generic Ltr 83-08 Re Restoring Safety Margins of Vacuum Breakers by Replacing Critical Parts W/Adequate Matls ML20207A8531986-11-0505 November 1986 Safety Evaluation Supporting Operation for Full Fuel Cycle W/O mid-cycle Insp for Crack Growth ML20215N3771986-10-30030 October 1986 Safety Evaluation Re Util 860320 Response to Generic Ltr 84-09, Recombiner Capability Requirements of 10CFR50.44(c)(3)(ii). Licensee Should Remove All Potential Oxygen Sources from Containments ML20203N0081986-09-17017 September 1986 Safety Evaluation Supporting Util 850919 Request for Relief from Installing Excess Flow Switch & Automatic Shutoff Valve in Diesel Fire Pump Fuel Line to Provide Protection in Event of Fuel Line Rupture ML20212N0201986-08-22022 August 1986 Safety Evaluation Denying Util 860325 Request for Relief from Inservice Insp Requirements of ASME Code Section XI, Table IWC-2500-1 for Volumetric Exam of HPCI Pump Studs ML20211G6081986-06-12012 June 1986 Safety Evaluation Supporting IGSCC Insp,Repair & Replacement Program During Dec 1985 Refueling Outage ML20205S2541986-06-0404 June 1986 Safety Evaluation Accepting Rev 2 to Nuclear Const Issues Group Spec 1, Visual Weld Acceptance Criteria for Structural Welding at Nuclear Power Plants, for non-ASME Code Welds ML20211A8281986-06-0303 June 1986 Safety Evaluation Re Rev 4 to Offsite Dose Calculation Manual.Rev Acceptable ML20198S7281986-05-29029 May 1986 Safety Evaluation Supporting 851203 Proposal to Modify Tech Spec 3/4.5.3 to Clarify Min Amount of Condensate Storage Tank Water Required to Ensure Operability of Core Spray Sys During Operating Conditions 4 or 5.Rev to Tech Specs Encl ML20133N4141985-10-23023 October 1985 Safety Evaluation Re Util 831107 & 850828 Responses to Generic Ltr 83-28,Items 3.1.2 & 3.2.1 & 850701 Request for Addl Info.Responses Re Vendor & Engineering Test Guidance & Testing Requirements After Maint Acceptable ML20134P5211985-08-28028 August 1985 Safety Evaluation Approving Use of ASME Code Case N-411 for Damping Curves ML20128M2911985-07-16016 July 1985 Safety Evaluation Supporting Licensee Response to Generic Ltr 83-28, Salem ATWS Event, Items 3.1.3 & 3.2.3 Re post-maint Testing 1999-08-05
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217N3271999-10-21021 October 1999 Part 21 Rept Re non-linear Oxygen Readings with Two (2) Model 225 CMA-X Containment Monitoring Sys at Bsep.Caused by High Gain Produced by 10K Resistor Across Second Stage Amplifier.Engineering Drawings Will Be Revised BSEP-99-0168, Monthly Operating Repts for Sept 1999 for Bsep,Units 1 & 2. with1999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Bsep,Units 1 & 2. with ML20212D0431999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Brunswick Steam Electric Plant,Units 1 & 2 ML20210P9441999-08-10010 August 1999 Safety Evaluation Accepting Licensee Assessment of Impact on Operation of Plant,Unit 1,with Crack Indications of 2.11, 6.36 & 1.74 Inches in Three Separate Jet Pump Risers ML20210P9181999-08-10010 August 1999 Safety Evaluation Authorizing Request for Reliefs CIP-01,02, 06,07,08,09,10 & 11 (with Certain Exceptions) & 12-18,for Second 10-year ISI Interval.Request CIP-04 & 05 Would Result in hardship,CIP-03 Not Required & CIP-11 Denied in Part ML20210N2341999-08-0505 August 1999 SER Accepting Response to NRC GL 87-02, Verification of Seismic Adequacy of Mechanical & Electrical Equipment in Operating Reactors,Unresolved Safety Issues (USI) A-46 ML20210R1191999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Bsep,Units 1 & 2 ML20210R1311999-06-30030 June 1999 Revised Monthly Operating Rept for June 1999 for Bsep,Unit 2 BSEP-99-0118, Monthly Operating Repts for June 1999 for Bsep,Units 1 & 2. with1999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Bsep,Units 1 & 2. with BSEP-99-0095, Monthly Operating Repts for May 1999 for Brunswick Steam Electric Plant,Units 1 & 2.With1999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Brunswick Steam Electric Plant,Units 1 & 2.With ML20210M8581999-05-14014 May 1999 B214R1 RPV Hydrotest Bolted Connection Corrective Action Evaluation, Rev 0 ML20211L3711999-05-10010 May 1999 Rev 0 to ESR 98-00333, Unit 2 Invessel Feedwater Sparger Evaluation ML20206G1871999-05-0404 May 1999 Safety Evaluation Approving Third 10-year ISI Program Requests for Relief (RR) RR-08,RR-15 & RR-17 BSEP-99-0075, Monthly Operating Repts for Apr 1999 for Brunswick Steam Electric Plant,Unit 1 & 2.With1999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Brunswick Steam Electric Plant,Unit 1 & 2.With ML20206N1791999-04-23023 April 1999 Rev 0 to 2B21-0554, Brunswick Unit 2,Cycle 14 Colr BSEP-99-0059, Monthly Operating Repts for Mar 1999 for Brunswick Steam Electric Plant,Units 1 & 2.With1999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Brunswick Steam Electric Plant,Units 1 & 2.With ML20205F9031999-03-30030 March 1999 Safety Evaluation Supporting Proposed Rev to BSEP RERP to Licenses DPR-62 & DPR-71,respectively ML20206N1831999-02-28028 February 1999 Rev 0 to Suppl Reload Licensing Rept for Bsep,Unit 2 Reload 13 Cycle 14 BSEP-99-0043, Monthly Operating Repts for Feb 1999 for Brunswick Steam Electric Plant,Units 1 & 2.With1999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Brunswick Steam Electric Plant,Units 1 & 2.With ML20203D7061999-02-0909 February 1999 SER Accepting Proposed Alternatives Contained in Relief Requests PRR-04,VRR-04,VRR-13,PRR-01,PRR-03,VRR-01.VRR-07, VRR-08 & VRR-09 Denied BSEP-99-0005, Monthly Operating Repts for Dec 1998 for Brunswick Steam Electric Plant,Units 1 & 2.With1998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Brunswick Steam Electric Plant,Units 1 & 2.With BSEP-98-0231, Monthly Operating Repts for Nov 1998 for Brunswick Steam Electric Plant,Units 1 & 2.With1998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Brunswick Steam Electric Plant,Units 1 & 2.With BSEP-98-0218, Monthly Operating Repts for Oct 1998 for Bsep,Units 1 & 2. with1998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Bsep,Units 1 & 2. with BSEP-98-0210, Special Rept:On 980824,temp Element 2-CAC-TE-1258-22 Failed. Cause of Failed Temp Element Cannot Be Conclusively Determined.Temp Element Will Be Replaced & Cable Connections Repaired1998-10-30030 October 1998 Special Rept:On 980824,temp Element 2-CAC-TE-1258-22 Failed. Cause of Failed Temp Element Cannot Be Conclusively Determined.Temp Element Will Be Replaced & Cable Connections Repaired ML20154P8151998-10-16016 October 1998 SER Accepting Revised Safety Analysis of Operational Transient of 920117,for Plant,Unit 1 ML20154P8591998-10-16016 October 1998 SER Accepting Equivalent Margins Analysis for N-16A/B Instrument Nozzles for Plant,Units 1 & 2 BSEP-98-0202, Monthly Operating Repts for Sept 1998 for Brunswick Steam Electric Plant,Units 1 & 2.With1998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Brunswick Steam Electric Plant,Units 1 & 2.With ML20151Y6211998-09-14014 September 1998 BSEP Rept Describing Changes,Tests & Experiments, for Bsep,Units 1 & 2 ML20151Y6371998-09-14014 September 1998 Changes to QA Program, for Bsep,Units 1 & 2 BSEP-98-0185, Monthly Operating Repts for Aug 1998 for Brunswick Steam Electric Plant,Units 1 & 2.With1998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Brunswick Steam Electric Plant,Units 1 & 2.With ML20151T5021998-08-0505 August 1998 Project Implementation Plan, Ngg Yr 2000 Readiness Program, Rev 2 BSEP-98-0164, Monthly Operating Repts for July 1998 for BSEP Units 1 & 21998-07-31031 July 1998 Monthly Operating Repts for July 1998 for BSEP Units 1 & 2 ML20236T1961998-07-0101 July 1998 Rev 1 to 2B21-0088, Brunswick Unit 2,Cycle 13 Colr ML20236T1921998-07-0101 July 1998 Rev 1 to 1B21-0537, Brunswick Unit 1,Cycle 12 Colr BSEP-98-0142, Monthly Operating Repts for June 1998 for BSEP Units 1 & 21998-06-30030 June 1998 Monthly Operating Repts for June 1998 for BSEP Units 1 & 2 ML20236T1971998-06-30030 June 1998 Rev 2 to 24A5412, Supplemental Reload Licensing Rept for Brunswick Steam Electric Plant Unit 2 Reload 12 Cycle 13 ML20249B9691998-06-11011 June 1998 Rev 1 to VC44.F02, Brunswick Steam Electric Plant,Units 1 & 2,ECCS Suction Strainers Replacement Project,Nrc Bulletin 96-003 Final Rept BSEP-98-0129, Monthly Operating Repts for May 1998 for Bsep,Units 1 & 21998-05-31031 May 1998 Monthly Operating Repts for May 1998 for Bsep,Units 1 & 2 ML20151S9041998-05-31031 May 1998 Revised Pages to Monthly Operating Rept for May 1998 for Brunswick Steam Electric Plant,Unit 1 BSEP-98-0104, Monthly Operating Repts for Apr 1998 for Brunswick Steam Electric Plant,Units 1 & 21998-04-30030 April 1998 Monthly Operating Repts for Apr 1998 for Brunswick Steam Electric Plant,Units 1 & 2 ML20151S8991998-04-30030 April 1998 Revised Pages to Monthly Operating Rept for Apr 1998 for Brunswick Steam Electric Plant,Unit 1 ML20247N7501998-04-30030 April 1998 Rev 0 to BSEP Unit 1,Cycle 12 Colr ML20247N7721998-04-30030 April 1998 Rev 0 to J1103244SRLR, Supplemental Reload Licensing Rept for BSEP Unit 1,Reload 11,Cycle 12 ML20217K8461998-04-24024 April 1998 Safety Evaluation Approving Proposed Use of Code Case N-535 at Brunswick Unit 1 During Second 10-yr Interval,Pursuant to 10CFR50.55a(a)(3)(i).Authorizes Use of Code Case N-535 Until Code Case Included in Future Rev of RG 1.147 ML20217K3941998-04-24024 April 1998 SER Approving Relief Request for Pump Vibration Monitoring, Brunswick Steam Electric Plant,Units 1 & 2 ML20217E6841998-04-23023 April 1998 Safety Evaluation Accepting Code Case N-547, Alternative Exam Requirements for Pressure Retaining Bolting of CRD Housings ML20217E7471998-04-21021 April 1998 Safety Evaluation Accepting Alternative to Insp of Reactor Pressure Vessel Circumferential Welds ML20217B5241998-04-20020 April 1998 SE Accepting Licensee Request for Approval to Use Alternative Exam Requirement for Brunswick,Unit 1,reactor Vessel Stud & Bushing During Second 10-yr ISI Interval Per 10CFR50.55a(a)(3)(ii) BSEP-98-0080, Monthly Operating Repts for Mar 1998 for Bsep,Units 1 & 21998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Bsep,Units 1 & 2 ML20216B1041998-03-0404 March 1998 SER Approving Alternative to Insp of Reactor Pressure Vessel Circumferential Welds for Brunswick Steam Electric Plant, Unit 1 1999-09-30
[Table view] |
Text
. _ _ _ . _ ._ _._________. _ - . _ . _ _ _ _ _ _ - _ . _ . _ _ _ _ . _ _ . _ . . _
4 ENCLOSURE 1 u
$genea, **,
!'- n UNITED STATES i NUCLEAR REGULATORY COMMISSION o, WASHINoToN. D.C. 20h06 SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO THE 120-DAY RESPONSE TO SUPPLEMENT NO, 1 TO GENERIC LETTER 87-02 FOR BRUNSWICK STEAM ELECTRIC PLANT. UNIT N05. 1 AND 2 ,
QOCKET NOS. 50-325 AND 50-324 4
l.0 " 'RODUCTlbN; By letter dated September 19, 1992, Carolina Power & Light Company, the licenste, submitted its response to Supplement No. I to Generic letter (GL) i 87-02, " Verification of Seismic Adequacy of Mechanical and Electrical Equipment in Operating Reactors, Unresolved Safety Issue (USI) A-46," dated May 22, 1992, for Brunswick Steam Electric Plant, Units 1 and 2 (BSEP 1 and BSEP 2). In this supplement, the staff requested that the licensees submit the following information within 120 days of the issue date of the supplement:
- 1. A statement whether the licensee commits to use both the Seismic Qualificattor, Utility Group (SQUG) commitments and the implementation l
guidance provided in the Generic implementation Procedure, Revision 2 (GIP-2) as supplennted by the staff's Supplemental Safety Evaluation Report No. 2 (SSER-2) for the resolution of USI A-46, in this case, any i deviation from GIP-2, as supplemented by the SSER-2, must be identified,
! Justified, and documented. if the licensee does not make such a commitment, the licensee must provide an alternative for responding to l GL 87-02.
. 2. A plant-specific schedule for the implementation of the GIP and submission l
of a report to the staff that summarizes the results of the USI A-46 review, if t5e licensee is committing to implement GIP-2. This schedule shall be sucn that each affected 31 ant will complete its implementation and submit the summary report wit 11n-3 years after the issuance of the SSER-2, unless otherwise justifieo.
i
- 3. The detailed information as to what procedures-and criteria were used to l generate the in-structure response (IRS) spectra to be used for USI A-46 as requested in the SSER-2.- The licensee's IRS are considered acceptable for USI A-46 unless the staff indicates omrwise during a 60-day review period. ,
In additien, the staff requested in SSER-2 that the licensee inform the staff -
l in the-120-day response time if-it intends to chanse its licensing basis to
, reflect a commitment to the USI A-46 (GIP-2) methodnlogy for verifying the l seismic adequacy of mechanical and electrical equipmer,t, prior to receipt of l the staf f's plant-specific svaty evaluation resolving USI A-46.
i l
9212070257 921123' yDR ADOCK 05000324 PDR_
L-_ _a ..; . . _ _ _ _ _ _ _ __, _ _ _ __
( .
l 2-4 1 2.0 EVALUATION i i With regard to item 1, the licensee stated that it "... commits to the SQUG commitments set forth in the GIP-2 in their entirety, including the ,
clarifications, interpretations, and exceptions identified in SSER-2 as
- clarified by the August 21, 1992, SQVG-letter res)onding to SSER-2." The >
i licensee also stated that it "... generally will se guided by the remaining l (non-commitment) sections of the GIP-2, i.e., GIP-2 implementation guidance, whict comprises suggested methods for implementing the applicable i commitments."
The licensee's response is unclear as to whether or not the licensee intends i to implement both the SQUG commitments and the implementation guidance, in i
- accepting GIP-2 as a method for resolving USI A-46, it was the staff's i understanding that the SQUG menbers who chose to implement GIP-2 would i essentially uso the entire procedure, including the SQUG commitments, which t i contain the general programmatic objectives and goals, and the implementation j guidance, which contains the specific criteria and procedures to be used for j the resolution of USI A-46. This understanding was-the basis for the staff's position, which was stated in SSER-2, that if the licensee-commits to use i GIP-2 for the implement 1 tion of USI A-46, it must commit to both the SQUG commitments and the use of the entire implementation guidance provided in i GIP-2, unless otherwise justified to the staff. In order to allow soma l flexibility in implementing GIP-2, the staff acknowledged in the supplement to !
i GL 87-02 that SQUG members who commit to GIP-2 (both the SQUG commitments and s the implementation guidance) may deviate from it provided that such deviations
! are identified, documented and justified. However, it was also indicated in-SSER-2 that if a licensee uses methods that deviate from the criteria and i procedures described in the SQUG commitments and in the implementation i guidance of GIP-2 without prior NRC approval, the staff may find the use of
- j. such methods unacceptable with regard to satisfying the provisions of GL 87-02. ,
i in light of the above, the staff interprets the licensee's response to
- Supplement No. I to GL 87-02 as a comn.itment to the entire GIP-2 including both the SQUG commitments and the implementation guidance, and therefore e
considers.it acceptable. - If the staff's interpretation is incorrect, then in
- accordance with Supplement No. I to GL 87-02, the licensee should provide for
, staff review, as soon as practicable prior to implementation, its alternative-
! criteria and prccedures for responding to GL 87-02, t
i in addition, Enclosure 2 of the letter transmitting this Safety Evaluation
. (SE) provides the staff's response, dated October 2, 1992, to the August 21, 1992, SQUG 1etter. The staff does not concur with all of the SQUG's clarifications and positions stated in that letter, and thus, the licensee i- -should not use the August 21.-1992, letter as guidance in responding to '
- Supplement No. 1-to GL 87-02. The licensee should refer-to- Enclosure 2 for l- the staff's position _on the SQUG letter.
With regacd to item 2, the licensee stated that.it will submit a summary report to-the NRC summarizing the results of the USI-A-46 program at BSEP 1 by 120 days after the completion of BSEP 1 refueling outage 9 (scheduled for completion on December 28,1994), and, at BSEP 2 by 120 days after_.the-d
, + , - - +w,,.1,.w.ew.=.-- ,, ---s-w.-m-e- ,+,..,r%.,-me,.%,w.m,-w-,w-e-n.-.c re-. . ~ . , - . . , .w,,..-~,E,,,Ew.mm.,,,,,-E-.,,,,,rs,,
completion of BSEP 2 refueling outage 11 (scheduled for completion on June 14, 1995). These submittal dates are within the 3-year response period requested by the staff and are therefore acceptable.
The licensee indicated that it may change its licensing basis methodology at BSEP 1 and BSEP 2, via 10 CFR 50.59, for verifying the seismic adequacy of new and replacement, as well as existing electrical and mechanical equipment prior to receipt of final plant-specific SEs resolving USI A-46. The staff recognizes that the licensee may revise its licensing basis in accordance with 10 CFR 50.59 to reflect the acceptability of the USI A-46 (GIP) methodology for verifying the seismic adequacy of electrical and mechanical equipment covered by the GIP. However, if the licensee does not commit to implement both the SQUG commitments and the implementation guidance, and the licensee has not committed to any acceptable alternative criteria and procedures, then the staff does not believe that there is a basis for initiating a 10 CFR 50.59 review.
With regard to item 3, the NRC has reviewed the subject licensee response with a particular objective of assessing the acceptability of the response to item 11.4.2.3 of the SSER-2.
The plant safe shutdown earthquake (SSE) peak ground accelera.a ion (PGA) is i 0.169 The design response spectra (DRS) are based on the sm(othed 1940 NS El l Centro spectrum normalized to 0.089 PGA with the spectral shape and i amplifications similar to 84 percent NUREG-0098 spectra. An artificial I time-history was developed to envelope the DRS at the dam)ing values of I interest. This time-history was utilized in developing t1e IRS at various elevations. The spectral acceleration values are multiplied by two to arrive at the SSE IRS. 1he licensee states that the IRS should be cons Mered as
' conservative, design' spectra for verifying the equipment. All the principal parameters (e.g., the DRS, soil-structure com)11ance, modeling of structures,
, and three components of the earthquake) have 3een adequately considered in l arriving at the IRS. The damping values utilized are similar to those in l
Regulatory Guide 1.61. Overall, the amplifications and broadening of the IRS provided by the licensee at various floor levels appear to-be reasonable.
Based on the staff's review of the licensee response, and the staff positions delineated in the SSER-2, the staff concludes that the licensee response is adequate and acceptable, and that the IRS developed by the licensee should be considered as ' conservative design' IRS. This conclusion is based on the l
assumption that the statements made in the submittal, including the procedures i used in generation of the IRS, correctly reflect the FSAR and other licensing l bases. The staff may audit the process by which the IRS were generated.
L
3.0 CONCLUSION
S ,
1 I The NRC staff interprets the licensee's response to Supplement-No. I to GL i 87-02 as a commitment to the entire GIP-2 including both the-SQUG commitments i and the implementation guidance, and therefore considers it acceptable. If the licensee does not commit to-implement the entire GIP-2, then in accordance with Supplement No.-1 to GL 87-02, the licensee should provide for staff review, as soon as practicable prior to. implementation,t its alternative i criteria and trocedures for responding to GL 87-02. Additionally, .
.l
_. _ _ ------_._ ~ _ ._ _ . . _ _ _ _ _ _ _ _ _ _ . _ . . _ . _ _ _ _ . . _
i 4-the implementation schedules proposed by the licensee are within the 3-year response period requested by the staff in Supplement No. I to GL 87-02 and are
, therefore acceptable.
The staff recognizes that the licensee may revise its licensing basis in accordance with 10 CFR 50.59 to reflect the acceptability of the USI A-46 (GlP) methodology for verifying the seismic adequacy of electrical and mechanical equipment covered by the GIP. However, if the licensee does not commit to implement both the SQUG commitments and the implementation guidance, and the licensee has not committed to any acceptable alternative criteria and >
procedures, then the staff does not believe that there is a basis for i initiating a 10 CFR 50.59 review. ,
Based on the staff review of the licensee's response and the staff positions delineated in the SSER-2, we conclude that the procedures used to generate the IRS are adequate and acceptable, and that the IRS-developed by the licensee should be considered as ' conservative design' IRS. This conclusion is based ,
on the assumption that the statements made in the submittal, including the procedures used in generation of the IRS, correctly reflect the' FSAR and other licensing basis.
Principal Contributors: P. Y. Chen M. McBrearty H. Ashar J. Stewart 1
1 l
. -. _ , ,. . , - - _ - .....-,--,,,,,.,.,.4.,. ._,_w_.----...,-,--.___.__ -_u---~..
A ENCLOSURE 2
< . /,,, ,, ,,'* *o' UlTED STATES
?"
NUCLEt R REGULATORY COMMISSION wAsmnoToN. o, c. acons OCT 01 g Mr. Neil Smith, Chairman Seismic Qualification Utility Group c/o EPRI 1019 19th Street, N.W.
Washington, DC 20036
SUBJECT:
NRC RESPONSE TO SEISMIC QUALIFICATION UTILITY GROUP (SQUG)
Re: Letter, N. Smith, EPRI, To J. Partlow, NRR, dated August 21, 1992, concerning USI A-46 Issues.
Dear Mr. Smith:
This is to acknowledge the receipt of the SQUG response to Supplement No. I to Generic Letter (GL) 87-02, and Supplemental Safety Evaluation (SSER) No. 2, on the SQUG Generic Implementation Procedure for Seismic Verification of Nuclear i Plant Equipment, Revision 2, as corrected February 14, 1992 (GIP-2). The NRC staff believes that successful implementation of the entire GIP-2, supple-mented by the staff's SSER No. 2, by each SQUG licensee will result in cost-effective plant safety enhancement for their USI A-46 plants.
The staff also believes that the positions delineated in Supplement No I to GL 87-02 and SSER No. 2 are clear and correct, and should not be misinterpret-ed. The staff's comments on SQUG's August 21, 1992, letter and attachment are provided in the enclosure to this letter. If you need further clarification concerning our response, please contact Mr. James Norberg at 504-3288.
Sincerely, e
W dit James G. Partlow Associate Director for Projects Office of Nuclear Reactor Regulation
Enclosure:
As stated -
- . = _ . _. .- _ __ . . - ____ - ________
ENCLOSURE
- 1. hpr;L i g entt on ' M SOUG Letter of Auoust 21. 1992:
- i. 16 nemt te t> , issue of seismic qualification, the staff r W R. net 'Lt.e position stated in the SSER No. 2, in that the Q ! Nr.ocology is not considered to be a seismic qualification R .c A. rather, it is an acceptable evaluation method, for USI A-O t! <.ts only, to verify the seismic adequacy of the safe-u d oown equipment and to ensure that the pertinent equipment seismic requirements of Gerieral Design Criterion 2 and the purpose of the NRC regulations relevant to equipment seismic adequacy including 10 CFR Part 100 are satisfied.
- 2. The second paragraph on page 2 of your letter addressed the issue of timing of staff response to additional information requested from a licenses. Although you are correct in your statement regarding the sixty-day period for response to initial submittal of in-structure response spectra (ISRS) information, we do not agree that the same concept applies to a licensee's submittal of additional information received following a rejection or a question from the staff. To eliminate any potential misunder-standing in this regard, the staff has determined that it will respond to any submittal of additional information received from a licensee within 60 days. However, in this response, the staff will either state its approval (or rejection) of the information provided, or indicate the time duration needed for the review of such information, prior to transmitting a follow-up response of 4
acceptance (or rejection) to the licensee. This time duration will vary depending on the complexity of the submittal.
- 3. Regarding the EBAC and ANCHOR computer. codes, the staff's evaluations and concerns stated in the SSER No. 2 are correct and valid. The ANCHOR code does not consider the effects of base plate tiexibility on the anchorage capacity.
- 4. With respect to transfer of knowledge regarding major problems identified, and lessons learned, in the USI A-46 plant walkdowns and third-party reviews, we request that you include the NRC in the distribution of written communications to all member utilities in this regard, and inform the NRC staff of any planned workshops e A-46 implementation for possible staff participation.
- 11. NRC's Cements on the Procedure for Reviewina the GIP
- 1. The staff supports SQUG's establishment of a Peer Review Panel composed of seismic experts since it should serve to enhance the review process of substantive changes to the technical requirements in the GIP, prior to its submittal to NRC for approval. However, since the NRC no longer intends to help finance a Peer Review Panel, the staff does not believe it
. . : a .u.
4
\ .
2 is appropriate to participate in the selection of the Peer Review -
members, who will be financed by SQUG/EPRI. We would like to emphasize that staff's review of a proposed GIP change will receive thorough independent NRC evaluation and will be assessed on its merits.
- 2. With respect to the NRC review and approval of the changes to the GlP (Item 5, page 3 of the procedure), the staff's position on the issue of its response timing is identical to that delineated in the response to a licensee submittal of additional information (refer to item 2 of NRC's Comments on the SQUG letter in this enclosure). This comment also applies to the section " LICENSING CONSIDERATIONS" on page 5 of the Attachment to the SQUG 1etter.
- 3. With respect to item 4, " Additional Restrictions," the text should be expanded to reflect that new information which indicates that existing GIP criteria and guidelines may be unconservative should be evaluated for potential 10 CFR Part 21 implications.
_ _ _ _ _ _