Special Rept Spr 85-014:on 850914,main Steam Line Process Radiation Monitor RMG-19A Declared Inoperable Due to Erratic Indication.Caused by Bad Detector.Detector & Associated Signal Cable Replaced
ML20198D751
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 09/27/1985
From: Dixon O
SOUTH CAROLINA ELECTRIC & GAS CO.
To: Grace J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
SPR-85-014, SPR-85-14, NUDOCS 8511120428
Download: ML20198D751 (2)


Text

-

l SOUTH CAROLINA ELECTRIC & GAS COMPANY Post OFFICE 764 Cotuue!A. SOUTH CAROLINA 29218 t*,. = 0 65 00I I A10 : I 8

~~ ""*"

September 27, 1985 Dr. J. Nelson Orace Regional Administrator U.S. Nuclear Regulatory Commission Suite 2900 101 Marietta Street, NW Atlanta, Georgia 30323

SUBJECT:

Virgil C. Summer Nuclear Station Docket No. 50/395 Operating License No. NPF-12 Special Report (SPR 85-014)

Dear Dr. Grace:

Attached is a Special Report for the Virgil C. Summer Nuclear Station.

This Special Report is submitted pursuant to the requirements of Section 6 of the Technical Specifications.

Should there be any questions, please call us at your convenience.

Very trul you f'}

~

O. W. Di on, r.

RJB:0WD/ led Attachment cc:

V. C. Summer K. E. Nodland T. C.

Nichols, J r./0. W. Dixon, Jr.

R. A. Stough E. H. Crews, Jr.

G. Percival E. C. Roberts C. W. Hehl W. A. Willigma, Jr.

J. B. Knotts, Jr.

s*- #

    1. D.. A. Nauman S.

D. Hogge O'roup Managers I&E Washington O. S.

Bradham Document Management C. A. Price Branch S. R. Hunt INPO Records Center J. F. Heilman ANI Library C. L. Ligon (NSRC)

NPCF File 5

l N 19

?~

j e

/

Dr. J. Nelson Grace SPR 85-014 Page Two September 27, 1985 EVENT DESCRIPTION On September 14, 1985, Main Steam Line Process Radiation Monitor RMG-19A was declared inoperable due to erratic indication.

A Maintenance Work Request was initiated for the repair of the unit.

Health Physics was notified of the inoperable monitor and a preplanned alternate method of monitoring was initiated as required by Action 30, Table 3.3-6 of Technical Specification 3 3.3, " Radiation Monitoring Instrumentation." The cause of the erratic indication was found to be a bad detector.

During the investigation of the erratic indication, it was noted by maintenance personnel that the insulation on the cable which connects the output of the detector to a junction box had dried and cracked due to heat.

This condition resulted in the exposure of the internal shielding which could eventually affect operability of the unit.

The subject cable on process monitors RMG-19B and 19C were inspected and also found to exhibit a similar condition.

Although this condition was not the cause of the erratic indication, a Nonconformance Notice (NCN) was written documenting the as-found condition.

This condition was evaluated and found not to be reportable under the requirements of 10CFR21.

The existing cable (designed for operating temperatures of 60*C) was replaced with a quality related cable rated for operating temperatures of 90aC.

Upon replacement of the detector and associated signal cable, RMG-19A was satisfactorily tested and declared operable September 26, 1985.

The signal cable associated with RMG-19C has also been replaced and the RMG-19B signal cable will be replaced by October 4,

1985.