Monthly Operating Rept for Nov 1998 for Oyster Creek Nuclear Generating Station.With
ML20198D209
Person / Time
Site: Oyster Creek
Issue date: 11/30/1998
From: Egan D, Roche M
GENERAL PUBLIC UTILITIES CORP.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
1940-98-20711, GL-97-02, GL-97-2, NUDOCS 9812230035
Download: ML20198D209 (3)


Text

e l

GPU Nuclear,Inc.

4 U.S. Route #9 South NUCLEAR Post Office Box 388 Forked Rwer, NJ 087310388 Tel 609-9714000 t

December 15, 1998 1940-98-20711 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555

Dear Sir:

SUBJECT:

Oyster Creek Nuclear Generating Station Docket No. 50-219 Monthly Operating Report - November,1998 Enclosed are two copies of the November,1998 Monthly Operating Report for Oyster Creek Nuclear Station. The content and format ofinformation submitted in this report is in accordance with the guidance provided by Generic Letter 97-02.

If you should have any questions, please contact Ms. Brenda DeMerchant, Oyster Creek Regulatory Affairs Engineer, at 609-971-4642.

Very truly yours,

(

Michael B. Roche Vice President & Director Oyster Creek MBR/BDeM/gl Enclosures I

I fg'Ph Administrator, Region I(2 copies) cc:

l NRC Project Manager NRC Sr. Resident Inspector 9812230035 981130 Y

}

PDR ADOCK 05000219 9 R

pg g

)

I A

APPENDIX A Operatine Data Report Docket No:

50-219 Date:

12/08/98 Completed By:

David M. Egan

- Telephone:

(609)971-4818 Reporting Period:

November 1998 YEAR TO MONTH DATE CUMULATIVE 1.

DESIGN ELECTRICAL RATING (MWe NET).

The nominal net electrical output of the unit specified by the utility and used for the purpose of plant design.

650 2.

MAXIMUM DEPENDABLE CAPACITY (MWe NET).

The gross electrical output as measured at the output terminals of the turbine generator during the most 619 restrictive seasonal conditions minus the normal station senice loads.

3.

NUMBER OF HOURS REACTOR WAS CRITICAL.

The total number of hours during the gross hours of the reporting period that the reactor was critical.

429.4 6473.8 176,316.0 4.

HOURS GENERATOR ON LINE.-

(Senice Hours) The total number of hours during tic gross 393.3 6350.9 172,434.0 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> of the reporting period that the unit operated with the breakers closed to the station bus. The sum of the hours that the generator was on line plus the total outage hours in the reporting period.

5.

UNIT RESERVE SHUTDOWN HOURS.

The total number of hours during the gross hours of tic 0

0 918.2 reporting period that the unit was removed from senice for economic or similar reasons but was available for operation, f

6.

NET ELECTRICAL ENERGY (MWH).

The gross c!cctrical output of the unit measured at the 227,350 3,830,889 97,115,829 output terminals of the turbine generator minus the normal station senice loads during the gross hours of the reporting period, expressed in magawatt hours. Negative quantities should not be used.

  • Design values have no " Year to Date" or " Cumulative" significance.

Appendix B Unit Shutdowns Docket No:

50-219 Date:

12/8/98

- Completed By:

David M. Egan Telephone:

(609)971-4818 Reporting Period:

November 1998

. No.

Date Typc*

Duration Reason' Method of Cause & Corrective Action to (Hours)

Shutting Down Prevent Recurrence Reactor:

9 9/26/98 S

326.7 C

1 The plant shutdown for its 17R outage. Outage completed at 14:44 on I1/14/98.

I 2

F Forced Reason:

htethod:

S Scheduled A-Equipment Failure (Explain) 1-htanual B-hlaintenance or Test 2-hianual Scram C-Refueling 3-Automatic Scram D-Regulatory Restridion 4 Other (Explain)

F Operator Training & Licensing Examination F-Administrative G-Opaational Enor(Explain)

II-Other(Explain)

Summary:

Oyster Creek's 17* refueling outage ended on November 14,1998 at 14:44 when the generator was placed on-line.

The plant generated 227,350 MWh net electric and achieved a MDC rating of 51.0% for the month.