APPENDIX B NOTICE OF DEVIATION Public Service Company of Colorado Docket:
50-267/86-08 Fort St. Vrain Nuclear Generating Station License:
DPR-34 Based on the results of an NRC inspection conducted during the period of March 3-7, 1986, and in accordance with NRC Enforcement Policy (10 CFR Part 2, Appendix C), 49 CFR 8583, dated March 8, 1984, the following deviation was identified.
The Updated FSAR, Revision 3, states that the licensee is committed to the provisions of ANSI N18.7-1972, " Administrative Controls for Nuclear Power Plants." ANSI N18.7-1972, Section 4.5, states that the onsite review committee, PORC, "should provide... continuing review of plant operation...."
In deviation from the abave, by memo dated October 18, 1985, five different individuals were assigned to attend PORC meetings each day of the week. Only two persons were scheduled to attend PORC meetings more than once each week, and in those cases, were scheduled to attend meetings only twice.
(50-267/8608-03)
Public Service Company of Colorado is hereby requested to submit to this office, within 30 days of the date of this Notice of Deviation, a written statement or explanation in reply, including:
(1) the corrective steps which have been taken and the results achieved; (2) corrective steps which will be taken to avoid further deviation from commitments made to the Commission; and (3) the date when full compliance will be achieved.
Consideration may be given to extending your response time for good cause shown.
Dated at Arlington, Texas, lclW ay of1) q, 1986.