HOPE CREEK GENERATING STATION MONTHLY OPERATING

SUMMARY

April 1986 The Hope Creek Generating Station was granted its Low Power License on April 11, 1986. Four days later fuel loading began together with control rod scram time and friction testing. Within twelve days, core loading and testing had been completed and preparation for initial criticality and power ascension testing had begun.

4 i

1

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50-354 UNIT Hope Creek Gen. Station DATE 5/10/86 COMPLETED BY Mike Phillips TELEPHONE 609-339-3738 MONTH April 1986 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net) (MWe-Net) -

1 N/A 17 0 2 N/A 18 0 -

3 N/A 19 0 4 ti/A 2g 0 5 N/A 21 0 6 N/A 22 0 7 N/A 23 0 8 N/A 24 0 l 9 N/A 25 0 lg N/A * ,

26 0 11 0 27 0 12 0 - 28 0 13 0 29 0 14 0 38 0 15 0 31 --

16 0

  • Low Power License issued April 11, 1986

OPERATING DATA REPORT UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-354 UNIT NAME Hope Creek Gen. Station DATE 5/10/86

,, COMPLETED BY Karen Head REPORT MONTH April, 1986 TELEPHONE 339-5239 ,

METHOD OF SHUTTING (

DOWN THE TYPE REACTOR OR F FORCED DURATION REASON REDUCING CORRECTIVE ACTION /

NO. DATE S SCHEDULED (BOURS) (1) POWER (2) COMMENTS N/A

SUMMARY

See Atitached 1

.e

SUMMARY

During April initial fueling activities were completed. The reactor status, however, remained as operational condition 5 (Refueling) through the last day of the month. As a result, there were no shut-downs or power reductions to report.

-- - -- y * < -_p

. .* l OPERATING DATA REPORT DOCKET NO. 50-354 UNIT Hope Creek Gen. Station DATE 5/10/86 COMPLETED BY Karen Head / Mike Phillips ;

TELEPHONE 609-339-5239/3738 I

OPERATING STATUS

1. REPORTING PERIOD April GROSS HOURS IN REPORTING PERIOD 0
2. CURRENTLY AUTHORIZED POWER LEVEL (MWt) 164.65 MAX. DEPEND. CAPACITY (MWe-Net) 1067 DESIGN ELECTRICAL RATING (MWe-Net) 1067
3. POWER LEVEL TO WHICH RESTRICTED (IF ANY) (MWe-Net) 53.35
4. REASONS FOR RESTRICTION (IF ANY) 5% License THIS YR TO MONTH DATE CUMULATIVE
5. 0 0 NO. OF HOURS REACTOR WAS CRITIACAL O __
6. REACTOR RESERVE SHUTDOWN HOURS 0 0 0
7. HOURS GENERATOR ON LINE O O O _
8. UNIT RESERVE SHUTDOWN HOURS 0 0 0
9. GROSS THERMAL ENERGY GENERATED (MWH) 0 0 0
10. GROSS ELECTRICAL ENERGY GENERATED (MWH) 0 0 0
11. NET ELECTRICAL ENERGY GENERATED (MWH) 0 0 0
12. REACTOR SERVICE FACTOR N/A
13. REACTOR AVAILABILITY FACTOR N/A
14. UNIT SERVICE FACTOR N/A
15. UNIT AVAILABILITY FACTOR N/A
16. UNIT CAPACITY FACTOR (Using Design MDC) N/A
17. UNIT CAPACITY FACTOR (Using Design MWe) N/A
18. UNIT FORCED OUTAGE DATE Ne'A
19. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, & DURATION) :
29. IF SHUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP:

, 21. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION:

FORECAST ACHIEVED

.sITIAL CRITICALITY 5/28/86 iJITIAL ELECTRICITY 6/24/86 COMMERCIAL OPERATION 10/15/86

Es.c Public Service Electric and Gas Company P. O. Box A Hancocks Bridge, New Jersey 08038 Hope Creek Generating Station May 14, 1986 U.S. Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555

Dear Sir:

MONTHLY OPERATING REPORT HOPE CREEK GENERATING STATION UNIT 1 DOCKET NO. 50-354 In compliance with Section 6.9, Reporting Requirements for the Hope Creek Technical Specifications, the operating statistics for April are being forwarded to you.

Sincerely yours, Sed g g N'b'S '

. S. Salvesen General Manager Hope Creek Operations KMH:bar Distribution CC Regional Administrator USNRC Region I 631 Park Avenue King of Prussia, PA 19406 Enclosures l l