ML20197J144
ML20197J144 | |
Person / Time | |
---|---|
Site: | Three Mile Island ![]() |
Issue date: | 04/03/1986 |
From: | NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
To: | |
Shared Package | |
ML20197J131 | List: |
References | |
50-320-85-99, NUDOCS 8605190379 | |
Download: ML20197J144 (47) | |
See also: IR 05000320/1985099
Text
- o.
...
1
U. S. NUCLEAR REGULATORY COMMISSION
REGION I
SYSTEMATIC ASSESSMENT OF LICENSEE PERFORMANCE
GPU NUCLEAR CORPORATION
THREE MILE ISLAND UNIT 2
MAY 1, 1984 to FEBRUARY 28, 1986
-;
April 3, 1986 ,
-
l
.
k
.m -
8605190379 860508 :
PDR ADOCK 05000320 E.
.G_ PDR , ta
..;;.
l
.. . - . . . - . - . .-.. - , - - , - - - - - - - - . . . . - - - . . -- - - -- -- - - -
. . , .
. .
.
TABLE OF CONTENTS
.Page
I. INTRODUCTION. . . . . . . . . . . . . . . . . . . . . . . . 1.
A. Purpose and Overview . . . . . . . . . . . . . . . . . 1
B. SALP Board Members . . . . . . . . . . . . . . . . . . 1
C. Background . . . . . . . . . . . . . . . . . . . . . . 2
t
II. CRITERIA. . . . . . . . . . . . . . . . . . . . . . . . . . 5
III. SUMMARY OF RESULTS. . . . . . . . . . . . . . . . . . . . . 7
A. Facility Performance . . . .............. 7
B. Overall Summary. . .................. 7
4
IV. P ER FO RMAN C E ANA LY S I S . . . . . . . . . . . . . . . . . . . . 9
A. Shutdown Plant Operations /Defueling Preparation. . . . 9
B. Radiological Controls. . . . . . . . . . . . . . . . . 14
4 C. Effluent Monitoring and Control . . . . . . . . . . . . 18
D. Quality Assurance. . . . . . . . . . . . . . . . . . . 20
E. Maintenance. . . . . . . . . . . . . . . . . . . . . . 23
F. Design, Engineering and Modifications. . . . . . . . . 25
G. Emergency Preparedness . . . . . . . . . . . . . . . . 28
H. Security . ......................29
I. Licensing Activities . . . . . . . . . . . . . . . . . 30
j V. SUPPORTING DATA AND SUMMARIES . . . . . . . . . . . . . . . 32 I
A. Licensee Event Report Tabulation and Causai Analysis . 32
B. Investigation Activities . . . . . . . . . . . . . . . 32
C. Escalated Enforcement Actions. . . . . . . . . . . . . 33
D. Management Conferences During the Assessment Period. . 33
1
TABLES
Table 1 -
Inspection Hours Summary. . . . . . . . . . . . . .T1-1
Table 2 -
Inspection Activities . . . . . . . . . . . . . . .T2-1'
Table 3 -
Enforcement Data. . . . . . . . . . . . . . . . . .T3-1 .
-
J
Table 4 -
LER Synopsis. . . . . . . . . . . . . . . . . . . .T4-1
Table 5- --
Summary of Significant Licensing ' Actions and
Supporting Activities . . . . . . . . . . . . . . .TS-1
. . . . . - -. - -
. .- .-,- . .-
.
.
I. INTRDDUCTION
,
A. Purpose and Dverview
The Systematic Assessment of Licensee Performance (SALP) is an
integrated NRC staff effort to collect the available observations
and data on a sampling and periodic basis and to evaluate licensee
performance based upon this information. The SALP is supplemental
to normal processes used to ensure compliance to NRC rules and
regulations. It is intended to be sufficiently diagnostic to
provide a rational basis for allocating NRC resources and-to provide
meaningful guidance to the licensee's management to promote quality
and safety of plant operations and modifications.
An NRC SALP Board, composed of the staff members listed below, met
on April 3, 1986, to review the collection of performance
observations and data to assess the licensee's performance in
accordance with the guidance in NRC Manual. Chapter 0516, " Systematic
Assessment of Licensee Performance." A summary of the guidance and
evaluation criteria is provided in Section II of this report.
This report is the SALP Board's assessment of the licensee's safety
performance at the Three Mile Island (TMI) Nuclear Station, Unit 2
for the period May 1, 1984 through February 28, 1986. This report
takes into account the unique mode of operation for defueling and
the necessary preparations required for safe movement of fissile and
radioactive waste material generated as a result of the March 1979
- accident. Some of the areas rated have not been previously
evaluated. However, they were incorporated to make the SALP
evaluation more reflect ive of the licensee activities at TMI-2 and
the utility's responsibilities.
B. SALP Attendees
Chairman:
T. T. Martin, Director, Division of Radiation Safety and Safeguards
(DRSS)
Board Members
,
S. D. Ebneter, Director, Division of Reactor Safety (Part-time)
W. D. Travers, Director, TMI-2 Cleanup Project Directorate
W. J. Johnston, Deputy Director, DRS
W. F. Kane, Deputy Director, DRP
R. R. Bellamy, Chief, Emergency Preparedness and Radiation
Protection Branch, DRSS
C. J. Cowgill, Chief, TMI-2 Project Section
M. T. Masnik, Project Manager, TMI-2
R. J. Cook, Senior Resident Inspector, TMI-2
).
, ,, , . . - - .-, .
_
.
2
Other NRC Attendees
J. M. Bell, Senior Radiation Specialist, TMI-2
T. A. Moslak, Resident Inspector, TMI-2
C. Background
(1) Licensee Activities
'
At the beginning of the period, the reactor plant was in cold
shutdown. The reactor vessel head was installed and shutdown
margin was being maintained by boron in the reactor coolant.
Major licensee activities centered around preparing for reactor
vessel head lift and conducting extensive decontamination
activities in both the reactor and auxiliary buildings.
By early July 1984, the reactor vessel (RV) head closure studs
were detensioned and removed without complication. The head
was lifted on July 24, 1984 and positioned on the storage stand
at the south end of the 347' elevation in the reactor building.
The lift was controlled from a shielded control station located
on top of the "A" D-ring. Dose levels were less than
anticipated (about 3R/hr) and contamination was controlled.
Some problems were experienced with polar crane malfunctions .
and limited reach capability during the head lift and work
platform and internal indexing fixture (IIF) installation.
During August 1984, the Reactor Building Polar Crane was taken
out of service for routine maintenance. During this
maintenance the licensee discovered that one of two redundant
crane brakes was inoperable due to a loose part on the hand
release mechanism. The crane was restored to service after
maintenance. Subsequent review identified the fact that the
hand release mechanism modification (installed in 1982) was not
made in conformance with licensee procedures. As a result, the
crane was again declared inoperable in September pending a
complete review of all maintenance and modification activities
performed on the crane. During the fall of 1984, GPU conducted
a thorough inspection of the polar crane and conducted a
complete review of all crane modifications.
In mid-Novemoer 1984, four hydraulic jacks equipped with
mechanical followers were installed around the reactor vessel
upper plenum. On December 6,1984, the plenum was jacked 2
inches without binding or measurable increases in reactor
building radiation levels. The licensee inspected the plenum
using television cameras. Later in December the assembly was
jacked to 7 inches.
)
I
_ .
3
On January 9,1985, after extensive review, the NRC approved
use of the polar crane to its load rating capacity of 170 tons.
On February 20, 1985, a small camera was lowered into the lower
reactor vessel to perform examinations below the core support
structure. The pictures showed debris in the form of a gravel
pile. Unlike the upper core rubble, the material in the lower
reactor vessel head was not identifiable.and appears to consist
of previously molten core material. Most rubble pieces
measured from two to four inches long and about half as wide. A
few larger pieces, however, appeared to be eight inches or more
in length. The debris in the lower vessel head is estimated to
be about 30 inches deep and contain approximately 15 to 20
tons.
On May 17, 1985, the licensee removed the reactor vessel plenum
and placed it in storage underwater in the deep end of the fuel
transfer canal. No significant problems were experienced
during the transfer.
The NRC licensed five individuals as Fuel Handling Only Senior
Reactor Operators in October 1985. This followed an extensive
training program conducted by the licensee over the previous
nine months.
The licensee experienced QA problems with the manufacture of
filter, knockout, and fuel shipping canisters. This required
the licensee to take additional measures to assure that
canisters were fabricated to design. specifications. As a
result, the initiation of defueling slipped approximately two
months. The licensee has ordered canisters from two other
manufacturers in response to these problems.
To date, canisters have been loaded using a pick and place
technique for identifiable pieces such as end fittings, spiders
and fuel pins. The bulk of the remaining debris removed from
the core has been loaded using a hydraulically operated spade
bucket. Visibility in the reactor vessel is poor (2-3 inches
using T.V. cameras) because of biological growth in the reactor
coolant system. The licensee continues to evaluate methods for
eliminating these organisms.
(2) NRC Activities
NRC oversight and inspection is performed by a staff of two
resident inspectors, three radiation specialists assigned from
the Region I office and a.Section Leader,and three project
engineers from the office of Nuclear Reactor Regulation. There
is a Senior NRC manager onsite who is_ responsible for overall
4
.
c.
4
coordination of NRC activities. In addition, there is a
Region I Section Chief assigned onsite. Periodic specialist
inspections were conducted in security and modification activi-
. ties and to evaluate specific problems that have surfaced.
'
NRC continues to approve certain operational and maintenance
procedures as well as Safety Evaluation Reports -for major
.defueling activities. Senior site NRC management changed
.
'
during the period. The NRR Project Director changed in August
1984 and the Region I Section Chief changed in December 1984. .
1
N
.
1
4
'
.)
l
.
1
l
' 'l
i
,
,
I
i
i
'
i:
'
!
__
G
'
5
II. CRITERIA
The following evaluation criteria were applied to each functional area:
1. Management involvement in assuring quality.
2. Approach to resolution of technical issues from a safety standpoint.
3. Responsiveness to NRC initiatives.
4. Enforcement history.
5. Reporting and analysis of reportable events.
6. Staffing (including management).
7. Training effectiveness and qualification.
To provide consistent evaluation of licensee performance, attributes
associated with each criterion and describing the characteristics
applicable to Categories 1, 2, and 3 performance were applied as
discussed in NRC Manual Chapter 0516, Part II and Table 1.
The SALP Board conclusions were categorized as follows:
Category 1: Reduced NRC attention may be appropriate. Licensee
management attention and involvement are aggressive and oriented toward
nuclear safety; licensee resources are ample and effectively used such
that a high level of performance with respect to operational safety or
construction is being achieved.
Category 2: NRC attention should be maintained at normal levels.
Licensee management attention and involvement are evident and are
concerned with nuclear safety; licensee resources are adequate and are
reasonably effective such that satisfactory performance with respect to
operational safety or construction is being achieved.
Category 3: Both NRC and licensee attention should be increased. ,
Licensee management attention or involvement is acceptable and considers i
nuclear safety, but weaknesses are evident; licensee resources appeared i
strained or not effectively used such that minimally satisfactory I
performance with respect to operational safety and construction is being j
achieved.
)
l
The SALP Board also assessed each functional area to compare the !
licensee's performance during the last quarter of the assessment period
'
to that during the entire period in order to determine the recent trend
for each functional area. The trend categories used by the SALP Board
are as follows:
Improving: Licensee performance has generally improved over the last
quarter of the current SALP assessment period.
Consistent: Licensee performance has remained essentially constant over
the last quarter of the current SALP assessment period.
--
- . .
_
- _ . ,_ . .
?.x
.
6
Declining: Licensee performance has generally declined over the last
quarter of the current SALP assessment period.
4
I
')
.
O l
'
7
III. SUMMARY OF RESULTS
A. Facility Performance
Functional Area Category Category Recent
Last Period This Period Trend
(October 1, 1981 - (May 1, 1984 -
September 30,1982) February 28,1986)
1. Shutdown Plant Operations /
Defueling Preparations 2 2 Improving'
2. Radiological Controls 1 1 Consistent
3. Effluent Monitoring and Control 1 1 Consistent
4. Quality Assurance 1 1 Consistent
5. Maintenance 2 1 Consistent
6. Design, Engineering and
Modifications 2 2 Consistent
7. Emergency Preparedness 1 No Basis- No Basis
8. Security 1 No Basis No Basis
9. Licensing Activities 2 1 Consistent
B. Overall Summary
This assessment is based on licensee performance over a period when
complex and, in some cases, unprecedented activities have been underway
to recover from plant conditions created by the March 1979 accident.
Activities during this period have been primarily directed towards
initiating reactor vessel defueling and on50ing decontamination of
building and equipment surfaces. In order to evaluate licensee
performance relating to defueling and decontamination, NRC assessment has
focused on activities including; personnel training, management controls,
plant modifications, radiological controls, maintenance, quality-
assurance and_ operations.
Overall, the licensee has carried out its cleanup and shutdown activities -
in a safe and technically competent manner. The licensee's emphasis on
safety has been demonstrated by a conservative approach, and a. generally
high degree of management involvement in TMI-2 issues. Licensed Fuel
Handling and Control Room operators have carried out their responsibili-
ties effectively and professionally. Some difficulty, early in the
assessment period, was experienced in conducting major evolutions. 'These
.
'
8
problems can be attributed to some inattention to detail which, as
demonstrated by more recent activities, has been improved upon by the
licensee.
As a result of the accident, radiation protection has presented a complex
and difficult challenge at TMI-2. The licensee has an appropriately
large number of resources dedicated to protecting workers and the
environment from radiation. The radiological controls organization has
performed effectively as evidenced by; 1) substantial progress in the
decontamination of building and equipment surfaces, and 2) the low
radiation doses incurred by cleanup workers.
A problem area which warrants improved licensee attention involves the
preparation of detailed procedures for carrying out cleanup activities.
Due to the unique nature of the cleanup, the licensee is required to
submit some detailed procedures to the NRC for review and approval. The
number of flawed procedures initially disapproved by the NRC indicates
that the licensee's review process is not effective in assuring all
procedural details are correct.
The site quality assurance (QA) department remains strong in their
involvement in all functional areas. The QA department has been
particularly effective in providing oversight for maintenance and design
engineering activities. The department appears to be a significant factor
in the success of major maintenance activities and in the design of
specialized modifications and tooling required for defueling. The multiple
levels of review incorporated into the QA organization are expected to
provide adequate support for remaining cleanup activities.
The licensee's engineering organization is an integrated staff composed
of engineers from the licensee and Bechtel in Gaithersburg, Maryland.
Early in the assessment this staff experienced problems conducting
adequate reviews of planned plant modifications. This was attributed to
d general lack of understanding of the licensee's administrative review
requirements and certain applicable regulatory requirements. The licensee
implemented an aggressive training program to correct this deficiency. NRC
observations later in the period showed subst&ntial improvement in this
area.
The licensee has been successful in carrying out cleanup and shutdown
operations safely and has generally operated in conformance with NRC
regulatory requirements.
l
l
l
l
i
i
1
)
.
.
IV. PERFORMANCE ANALYSIS
A. Shutdown Plant Operations /Defueling Preparation
Analysis-
a. Shutdown Plant Operations
Shutdown operations have been under continuous scrutiny by NRC. The
-plant is in a shutdown recovery mode with highly borated primary-
coolant at ambient temperature. Incore temperature is monitored by
the remaining operable incore. instruments. The Reactor Coolant
System is vented to the reactor building atmosphere with the. reactor
vessel head.and plenum assembly removed.from the reactor vessel.
Reactor coolant system cooling is by natural heat loss to the
reactor building atmosphere. A defueling platform is installed over
the reactor vessel an.d defueling operations are in progress. The
licensee has~ established two command centers located outside the
control room. One controls the reactor building. evolutions and the
other controls fuel handling activities.
The licensee's major shutdown operation emphasis has been
maintaining reactor coolant system water chemistry and level,
containment-integrity, controlled and assayed liquid discharges,
prevention of uncontrolled airborne releases, minimizing and
controlling personnel exposure, processing of. contaminated water,-
performance of routine plant surveillar,ces, maintaining security,-
maintaining industrial safety, and plant housekeeping. Two
violations were identified in this area during the assessment
period. The violations were assessed by the NRC to be isolated
~
cases of operator error and were not indicative of a programmatic
breakdown in procedural control.
The plant operators are well tra'ined and' qualified and perform their:
duties in a professional manner. However, one problem with operator
training was identified early in the assessment period. During
operator licensing examinations, weaknesses were noted in
candidates' overall knowledge and understanding of administrative -
and operational procedures.- An examination conducted 'later in the
-
period noted a marked improvement in candidate knowledge in these
areas. This improvement is-attributed to the--increased licensee '
management attention to operator training p.rograms.
The control room is maintained quiet' and orderly to provide an
appropriate atmosphere for monitoring-plant parameters and
evolutions. The control room operators monitor and interface with
the command centers which have direct control of' operations in the.
reactor building. In general, these interfaces have been smooth and-
.
no problems have been identified. The Command. Center and the Fuel-
)-
._ . - . _ - _ _ . . _ . . _ . _ .. -_ ._ - . . _ . _ _ __-
.
l -
10
i ,
'
Handling Control Center have been maintained in an appropriate
- manner. Personnel access is restricted and operator communication
j_ i s formal.
NRC reviewed the licensee's surveillance testing program routinely
- during the evaluation period. Licensee performance continues to be
i
excellent with a well established program. The program is implemen-
- ted using a computerized scheduling system for routine surveillances
j and supplemented with a manual system for non-routine surveillances.'
j Weekly schedules are reviewed and used by each department in produc- '
- ing their work lists to assure that all required surveillances are
- performed in a timely manner. Daily planning meetings serve to !
minimize conflicts in the scheduling and conduct of surveillances. ;
i Surveillance procedures are detailed and consistent with the ,
licensee's administrative controls and current technical specifica- ;
4
tion requirements. !
'
l
Management has aggressively pursued identification and changes of
j those Technical Specifications (TS) which are no longer appropriate for
, present plant conditions and has received approval-from the NRC to
delete unnecessary requirements. Several systems which are no
- longer required to maintain plant safety have been removed from the
4 TS. However, the licensee has maintained integrity and operability i
for some of these systems to maintain a backup capability for
j systems currently in use.
The licensee is required by Technical Specifications to submit
- certain procedures with safety significance to the NRC for review
- prior to implementation. A large number of these procedures have
- been initially disapproved by the NRC. The reasons for NRC
j disapproval range from relatively minor editorial adjustments, to
major equipment and/or system line-ups deficiencies which have-a
potential safety impact, or result in violations of the Technical
j Specifications. The lack of procedural adequacy was addressed in
<
the previous SALP evaluation. Examples of the above problems
include one procedure that was submitted with mathematical errors i
- and one procedure that would have violated Techr.ical Specification '
l requirements in that the procedure used a check valve for
containment isolation instead of a manual valve as required by the
- Technical Specifications. Both of-these procedures had received the
'
required licensee reviews including those performed by the Safety
Review Group before being submitted to the NRC for review. These
i problems are indicative of'probTemsFiffthe licensee's ~techriical
~
2
ire _v.iew of procedures. 7 . Z .[ Z T _
.
E ' _11~ _ -
- - - _ - . . - - - - -
" * * * " " ' ' " ^ * ' ~~
, _ ._ m , . , . - .,
'
- .-- .
e, m . . / =
-- .. - _. -__ -~ ~
~ = =e.ne- e s -e . - + . se
a.... - -
- .
i _. , _ , _ -
,
l'
,g - . w*r . - , - ,- = mimr-vre-w-ta----.-e-.- ----=".e,y,-.,,.- y .-se,-.c," *----av-=w v.r-*-.-+-M -
ww . mv-e-v e.-*.*-e-wr ms -v - --rm*=---*-wag-++ - - * = e-a- ~w +we *d- *wr.a-w*wr
. . _ _ _ _ _ _. _ __ . . _ _ _ - .
.
-
11
b. Defueling Preparation
The licensee's primary efforts during the evaluation period have
centered around preparations for and conduct of initial defueling
activities. Management involvement in all activities remains
strong. Senior management is involved in daily planning, project
status meetings, and makes frequent plant tours to maintain a close
working relationship with the technical staff. The licensee remains
committed to a safe expeditious cleanup of the facility. A lengthy
defueling checkoff was completed, reviewed and approved by senior
licensee management prior to the start of defueling. Technical and
Safety Advisory Groups-are still retained by the licensee to provide
independent review of activities. The licensee has a continuing
effort to review and upgrade existing procedures to reflect changing
needs. This review has identified a number of areas where errors or
conflicting requirements existed. The licensee has consolidated,
simplified, and streamlined the procedures and this effort has
expedited the defueling process.
The first major evolution leading to defueling was reactor vessel
head lift. During the preparations the licensee installed lead
blankets around the periphery of the head for shf aldf r.g. The
original hangers for the lead blankets experienced weld failure
before the lead blankets and hangers were completely installed.
Even with this experience, the licensee installed new hangers
without first verifying weld quality. This resulted in the need to
make an entry into the Reactor Building to verify weld quality after
blanket installation. During the head lift a number of relatively
minor problems were encountered which extended the time required to
complete this evolution. This rest.? ted, at least in part, from the
licensee's failure to utilize information gained from previous
experience moving the head.
The licensee conducted a detailed inspection of the polar crane
prior to each major lift and made repairs as necessary. NRC also
inspected the crane and identified several items that had been
missed in licensee inspections. These items ranged from loose
equipment on the crane to missing nut locking devices and loose
cables. While individual discrepancies were not significant, the
number of discrepancies identified were relatively large. The
i licensee subsequently assigned a systems engineer and revised their
preventive maintenance program including management review. These
improvements appear effective. (Additional discussion in
Maintenance, Section 5.) The above problems are indicative of a
lack of attention to detail during preparation for and conduct of-
major evolutions.
'
In conducting later major evolutions including plenum jacking, lower ,
reactor vessel head exploration and the subsequent plenum lift and
storage in the Fuel Transfer Canal, licensee preparations were more ]
thorough and showed appropriate attention to detail and resulted in
smooth evolutions.
i
,
l
]
.
.
12
1
i
The licensee conducted a vigorous training program to qualify Fuel
Handling Senior Reactor Operators (FHSR0s) to assure that they would
be licensed by the NRC to handle fuel. The training program was
closely monitored by the NRC, including witnessing reactor operation
at the Penn State University pool reacter. The licensee was
selective in choosing the FHSRO candidates with experience being a
key prerequisite. Five of the six candidates were granted-FHSR0
licenses by the NRC. The sixth individual was subsequently granted
a license after reexamination. Similarly, existing . control room
SR0s were trained in defueling operations during their
requalification program. NRC review indicated that the overall
program was conducted in a thorough, professional manner.
On October 30, 1985, the licensee initiated preliminary defueling
activities. These activities involved rearrangement of core debris
within the reactor vessel to allow complete installation and
uninterrupted rotation of the Canister Positioning System. The
licensee had in place an organization that included a Defueling
Director and engineering and radiological controls support to assist
the defueling crews in solving problems while defueling was in
progress. By the end of the evaluation period, 16,000 pounds of
core debris had been removed. NRC observation of initial defueling
efforts indicated that the licensee has taken a deliberate, cautious
!
approach to each new evolution. Operator performance and
_
! coordination of activities has been good.
Late in the period, the licensee reorganized the Unit 2 project
organizational structure to incorporate a newly formed Defueling
Group reporting directly to the Director of TMI-2. The new group is
managed by a Defueling Manager and consists of a Defueling
Operations Section, a Defueling Engineering Section and a Defueling
Support Section. The new group was formed to place management
emphasis on increasing productivity.
In summary, the licensee has safely maintained the plant in a safe
shutdown condition while preparing for and conducting initial
defueling. The licensee continues to have problems during technical
review of new procedures. The licensee has pursued conservative
solutions to technical problems which have arisen during initial
4
defueling and has conducted operations in a cautious manner. The
licensee has modified its organization as necessary to meet changing
needs.
Conclusion
i
Rating: 2
Trend: Improving
)
.
' -
13
Recommendations
Licensee: Review system for development and review of procedures to
ensure technical adequacy.
!{RC: Perform inspection of the licensee's procedure development and
review process,
_ _ _ _ _ _ _ _ _ _ - _ _ -
.
14
B. Radiological Controls
Analysis
Radiation Protection and Waste Management are under continuous review
by siw radiation specialists. Additional specialist inspections were
performed by both site and region-based inspectors.
Radiation Protection
The licensee's radiation protection program has been effective
throughout the appraisal period. Management commitment to the
maintenance of a high quality program is evidenced by its active,
timely and decisive involvement. Worker concerns and suggestions
are accommodated by means of the Radiological Awareness Report (RAR)
and the Incident / Event Report (IER) systems. RAR and IER reviews
are generally timely and corrective actions appropriate. In
addition, radiological concerns are discussed at " Radiological
Awareness" meetings open to all workers. These meetings are
conducted about once per month.
The Radiological Controls Department (Rad Con) has been generally
effective in impleinenting the ALARA principle at the task level by
means of pre-work reviews, radiation work permits and personnel dose
followup. Examples of the application of this process include cork-
seal replacement work in the Control and Service. Building, valve
alley flushing (decontamination), and auxiliary building reactor pit
decontamination. Pre work reviews resulted in the specification of
l
' such things as appropriate protective clothing, training (including
mockups), monitoring, high radiation areas to be avoided based on
appropriate survey results, the use of local shielding and eye
,
,
protection for high energy beta. In the case of work in the makeup ,
i
valve rooms, analysis of pre-work survey data resulted in the use of
l
locally fabricated plastic hoods that resulted in the avoidance of i
substantial dose from high energy beta radiation. Post-job reviews
compared cumulative dose estimates with the cumulative dose
received, analyzed the causes of higher than expected doses and made
recommendations for improvements for future work. As an example, an
evaluation of conditions experienced during decontamination work in
the auxiliary building elevator pit resulted in recommendations for
improvements in tooling, exhaust air filtration, personnel shielding
for high energy beta, and respiratory protection / personnel stress i
reduction. !
NRC reviews of the personnel selection, qualification and training
indicated that formalized training programs are being implemented
for Rad Con technicians, Rad Con Supervisors, and Rad Con Support-
Technicians. Additionally, the licensee is developing ALARA
training for engineers and managers. Positions are adequately
)
.
15
staffed and vacancies were filled with qualified experienced
individuals. The licensee has experienced a high turnover in
contractor technician positions primarily due to competition within
the industry for personnel'. When vacancies have existed, the
licensee has acted promptly to obtain qualified replacements and to
ensure that personnel are properly qualified and trained. Inspector
observations of formal training, interaction with plant workers, and
participation in special task briefings indicate that personnel at
all levels are aware of their responsibilities with respect to
radiation protection.
The quality of the licensee's radiation protection program is
evidenced by major. reductions in airborne, surface, and general area
radioactivity and radiation levels, accreditation of its personnel
I
dosimetry program by the National Voluntary Laboratory Accreditation
Program of the National Bureau of Standards, improved personnel
contamination detection and assessment (including testing and
installation of state-of-the-art personnel frisking devices),
upgrading of its respiratory protection program, and the development '
of special purpose radiation detection and measurement instruments.
The licensee has been particularly effective in minimizing personnel
exposures associated with defueling operations. This has been
accomplished by coordinated and complimentary efforts including; 1)
shielding design of the work platform, 2) general area decontamina-
tion, 3) training, and 4) continuous monitoring of radiological
conditions by health physics technicians. Radiation fields on the
defueling work platform, which has the highest worker occupancy in
the reactor building, are the lowest in the reactor building.
One significant licensee-identified radiation exposure event
occurred where three persons exceeded the licensee's administrative
skin exposure limit during an entry into- the Seal Injection Valve
room in the Auxiliary Building. NRC limits were not exceeded during
this event. The causes of this problem were inadequate radiological ,
engineering review, inadequate prejob briefing and mockup training '
and inadequate performance by a Rad Con technician. Licensee
investigation into the incident and subsequent corrective actions
were aggressive and thorough. Although there were major l
4
deficiencies associated with this event, NRC review of subsequent !
activities in high radiation areas conclude that there was not an
overall breakdown in the conduct of the licensee's radiological- l
controls' program, i
l
Some ;*oblems have occurred which indicate that communications
between workers and Radiological Controls technicians could be
improved and that lessons learned from these problems could be more
effectively included in technician training. Examples include (1)
in August 1984, a worker received internal contamination because of I
poor communication between supervisors; (2) in May-1985, unclear
direction was provided with respect to decontamination of a steel .
I
l
l
..
, - - , ,
.. _ _ _ _ _ - _ _ _ .
C
16
plate; and (3) in June 1985, a worker received internal
contamination in the Reactor Building annulus because of confusion
, over where work was to be performed.
Radioactive Waste Management
4
The licensee is implementing an effective radioactive waste
management program. The responsibilities and functions of the rad-
'
waste organization are adequately described in administrative proce-
dures. However, there was some confusion regarding communication
among the personnel involved in radioactive waste system operations;
1
shipping and packaging; equipment decontamination; and laundry and
respiratory protection maintenance because they reported to different
supervisors within the Plant Operations Department. An example of
this problem involves misclassification of a waste shipment. Three
separate groups did calculations to determine the classification of
- the affected packages but the groups did not properly coordinate
their efforts and as a result the misclassification went unnoticed.
In responding to these problems, the licensee consolidated most of
the radwaste functions under one experienced manager reporting to the
Director of Site Operations in September 1985. This change has
resulted in better communications and smoother radwaste operations.
Subsequent review by the NRC has identified no similar problems.
I Personnel at all levels in the radwaste organization.have been
i
adequately trained and are qualified with regard to each individual's
4
functions and responsibilities within the organization.
A significant problem was identified by the licensee late in the
period in the assay of solid samples for Strontium-90 content. The
licensee was using unverified computer programs and did not have an
interlaboratory QA/QC program to detect analysis errors. This
resulted in underestimating the value of Sr-90-reported on some
waste shipments by a factor of two and caused one shipment to be
improperly classified (not related to the above problem). Licensee
action on this error once identified, was prompt, thorough and
should preclude similar errors in the future. The laboratory
program was examined by a contractor, and some additional steps
recommended. The licensee has begun a QA/QC interlaboratory
program.
The NRC routinely inspects radwaste shipments leaving the site. In
general, the shipment documentation is adequate and the shipments
are properly prepared. Licensee Operations Quality Assurance
reviews all shipments of greater than Type A quantities. No
i
significant problems have been identified.
Some radwaste operational problems occurred during this assessment
period: including; a resin liner becoming jammed in a concrete
shield; slight contamination of two workers while clearing a hose
line; and the incomplete solidification of one liner, requiring
extra handling of the liner and some additional exposure of workers.
4
- .
t
'
17
These problems were the result of personnel errors and in the case
of incomplete solidification, a_ deficiency in the contractor's
process. NRC review has concluded that the~se were isolated problems-
and not indicative of a programmatic breakdown.
Decontamination efforts by the licensee have resulted in improved
radiation exposure conditions and personnel access to large areas
within the plant, especially access to the chemical addition area,
the hallways of the 281' level auxiliary building, and the auxiliary
building elevator pit; the latter resulting.in restoration of the
elevator to general use. The waste management group has also helped
in the dose reduction effort by scabbling the floors of the reactor
building, and by shielding and decontamination-of the 281 fuel
handling building valve alley.
Radwaste Management has implemented a plan to reduce the amount of
radwaste stored outside and exposed to weathering. Stored radwaste
has been largely removed from the " paint shed" at_ South East Acres.
Radwaste packages are now being olaced in an enclosed Interim Solid
Waste Storage Facility. A radwsste handling and packaging facility
is under construction. This building will provide spaces for
decontamination, survey, compaction and disassembly of contaminated
items so as to reduce the amount of radwaste for burial.
'
Conc?usion
Ratirg: 1
Trend: Consistent
,
Recommendations
i
Licensee: The licensee should continue efforts to maintain
effective communications between supervisors and workers.
NRC: None
f
T
_ ._i_'__._._._.____ - . . . _ _ _ _ _ _ _ _ _ . _ _ _ _ . _ . _ _ _ _ _ _ _ _ _ _ . _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ - . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ . _ _ _ _ _ . _ _ _ _ _ _ _ _ _ _ . _ _ _ . - _ . _ _ _ _ _ _ _ _ _ . _ _ _ _ _ _ _ . _ _ . _ _
'
,
,
n
a '
18
C. Effluent Monitoring and Control
Analysis
The NRC onsite inspectors routinely reviewed the licensee's Effluent
Monitoring and Control Programs. In addition, one inspection of the
Radiological Environmental Monitoring Program (REMP) was performed
by a regionally based specialist inspector. <
The licensee maintains a strong, well-managed REMP. ' Personnel are
knowledgeable, well trained and thorough. The quality of analytical
reasurements is maintained by a good quality assurance program. For
example, licensee contractor laboratories are required to participate
in the Environmental Protaction Agency (EPA) Cross-Check program and
do periodic duplicate analyfes'. In addition, the licensee splits
samples from certain Radiological Environmental Monitoring (REM)
sampling stations between two laboratories. The licensee partici-
pates in the International Environmental Intercomparison Project,
sponsored by the Department of Energy (DOE) and EPA for dosimeters
(TLD). These comparisons indicate that the licensee's measurements
are accurate. \
The licensee maintains more than twice the number of TLD radiation
monitoring stations required by the Technical Specifications. In
addition, the licensee maintains pressurized ion ~ chamber gamma
detectors and cryogenic krypton samplers at selected REM sampling
stations which are not required by Technical Specifications, and
collects more than the required number of environmental samples
'(milk, soil, leafy vegetables). In support of the defueling, the
licensee is doing analyses of transuranics in soils from~ eleven
_
locations and high volume air samples from four offsite locations.
The licensee has an extensive on and off site well monitoring
program. Groundwater aquifers are monitored by wells on two sides-
of the site. In addition, several wells are monitored onsite to
detect leaks before aquifers are affected. As a result of t.his
onsite monitoring program, several problems have been identified and'
corrected including several leaks on the borated water storage tank
valves.
There were no unplanned liquid or gaseous releases to the
environment during the assessment period. The NRC reviewed GPU
Quarterly Dose Assessments and Semi-Annual Radiological
Environmental reports for the period. The reported effluent
releases and corresponding calculated doses in each report were
small fractions of the TMI-2 Technical Specification limits for
annual averaged releases and were consistent.with the results of
environmental and effluent monitoring systems independently
monitored by EPA and NRC. When problems are identified, the
licensee evaluated the problems for potential generic implications.
For example, as a result of a licensee identi_fied potential
i ,
i)
- . -. - .. .. . ._
..- . -.. _ - - .
,
I
- l
l
19
unmonitored release pathway to the environment, an extensive-
investigation was initiated to determine if other similar release
paths exit.
The licensee has improved its sump sampling program during the
assessment period. Certain sump samples had not previously been
representative due to lack of recirculation' procedures. In response
to NRC concerns, permanent. recirculation piping was installed during
late 1984 and early 1985 in most sumps to' improve sump sample
- quality.
Conclusion
Rating: 1
Trend: Consistent
Recommendations ,
,
,
Licensee: None
1
NRC: None
1
1
I
s
a
l
,
,
,- - . , . _ - . . , - . , , , , , ,,.v... , - ,..,e , , ..-s,-,. .- - - ~ s w. . - -en - -
-g- ,, . - 4 -- ,
w
.
lb -
1/ 20
-
~,
D. Quality" Assurance
.
Analysis '
During this report period, a special inspection of the Recovery
Quality Assurance (QA) Plan was performed by a team consisting of
Resident,- I&E Headquarters, and contracted personnel; and the
.results of the' Performance Appraisal Branch inspection of the QA
Program, conducted between February 27 and March 28, 1984, were
received. Implementation of the program was routinely reviewed by
resident inspectors. There were no violations identified in this
area during the assessment period.
NRC review of this area determined that there is an extensive,
-detailed, and largely effective QA program. Many strengths were
identified. One.of the'mgre .significant strengths was the extensive
support for QA throughout the organization. Management support at
the highest levels was articulated in policy >Latements, corporate
procedures and memorandum addressing specific QA issues. This
backing was reflected at all- three levels (quality control,
operational monitoring, and' audits) of the QA Department in a
comprehensive goals ano: objectives program that addressed areas for
improvement. Specific action was taken by the Vice President,
Nuclear Assurance Divisiin to form an'Important to Safety (ITS)
working group to consider the classification of activities as they
relate to safety. Senior management has also strengthened and
clarified the management escalation program by better defining the
thresholds that trigger upper manag~ement action on longstanding
deficiencies; i.e. audit findings, Quality Deficiency Reports (QDR),
Material Nonconformance Reports (MNCR) and Quality Assurance
Monitoring Reports (QAMR).
The QA organization hcs used a graded approach to apply QA oversight
to facility operations. This graded approach allows QA to apply an
appropriate level of evaluation to activities, components, ,
procedures or systems b2$5d on their r 'clative contribution to plant
!
sa.fe ty. The licensee's i;11cy directsjthe QA organization to j
evaluate all site at i r? ~es including those not considered safety
significant. Fraq e t1 ,cheduled" audits and monitoring activities
complement the Q.s.ity .,' trol fuactions. Audits are thorough and !
timely. The monitoring program .is aggressive and ensures proper ;
implementation of administrative controls. Reports are timely and I
are distributed to appropriate senior _ management and review groups
within and outside the QA department. ' Corporate QA management is
frequently' involved in site activities. Quarte.rly presentations are
made by the Director, Quality Assurance to the GPUNC Board of
Directors on the status of site related QA issues.
-
s
%
w
C '-
- - - . -
.
.
21
Corporate QA has maintained an oversight role in evaluating the
performance of the Bechtel QA organization and its primary
suppliers. This oversight role involved routine visits to contractor
facilities and evaluating contractor compliance with a QA program
that had been approved by the licensee. During the initial phases
of fuel canister fabrication, this oversight was ineffective. NRC
inspections conducted in the Summer of 1985 of one contractor found
a number of problems with the implementation of the contractor's QA
program. Specifically, regulatory requirements were not satisfied
in several areas including use of unapproved vendors, failure to
identify and tag material, failure to perform receipt inspection,
failure to properly store material, and failure to maintain
up-to-date manuals. These findings precipitated a more aggressive
monitoring of the contractor QA programs by GPU Nuclear. Immediate
measures included increasing the frequency of visits to contractor
sites by QA personnel and using more detailed check lists in
evaluating the manufacture and testing of canister components.
Based upon the results of follow-up NRC inspections at contractor
facilities, these changes appear effective.
NRC evaluations determined that the onsite QA staff is experienced,
technically competent and sufficient to perform the functions
documented in the QA plan. The monitoring staff has issued over
1,000 QAMRs per year, covering the various aspects of licensee
activities; i.e. operations, surveillance, chemistry, maintenance,
radiological controls, etc. An example of the licensee's strong
commitment to quality was evident in the extent of action taken, in
response to NRC concerns, to ensure the quality of welds in the
Canister Storage Module. During the receipt inspection, a sampling
plan was developed to assure a representative sampling of the welds.
This plan involved spending approximately three man weeks performing
dye penetrant testing and visual examination of the welds, and then
adding as corrective action, an additional 1,900 stitch welds to the
four storage modules to ensure structural integrity.
QDRs, MNCRs, QAMRs, and Audit Findings were trended and evaluated to
provide recommendations for plant improvements. The program
consists of a four phase process that collects information in a l
computerized data base, evaluates the data to identify potential i
trends, investigates trends to determine underlying causes and I
implements corrective action to improve plant operations. A review
of QA records indicates steadily decreasing instances of procedural
problems such as failure to implement a procedure or failure to have
a procedure properly reviewed and approved. Through the trending of
QAMRs, QA identified that many procedures contained redundant
requirements. To improve these procedures, QA has tasked the
applicable departments to identify and remove needless duplication.
- _ _ _ _ _ _ - _ __
.
'
22
The licensee's commitment to the QA/QC program is also apparent from
the cooperation and extensive interface between the QA department
and plant personnel. NRC interactions indicate that licensee
personnel felt that QA unearthed substantial findings, made valid
suggestions for improvement, and enhanced the performance of their
line programs.
Conclusion
Rating: 1
Trend: Consistent
Recommendations
Licensee: None
NRC: None
I
e
__ . . . . .
_ _ _ _ - - - - - - - - - - - - - - - - - - - - -.
.
23
'
E. Maintenance
Analysis
Resident Inspector review in this area centered on maintenance of
equipment required by Technical specifications, selected corrective
and preventive maintenance activities and major maintenance support-
,
ing defueling preparation.
The licensee has a well developed maintenance control program which
prioritizes, assigns and schedules work activities. There appears
to be effective communication between the various groups involved.in
planning, coordinating and scheduling various maintenance
4
activities. The NRC has noted that the licensee considers
interdepartmental communications important and are supported by all
levels of management. The licensee conducts a daily planning
,
meeting where maintenance activities and coordinated support are
discussed and scheduled.
j-
NRC review of the annual diesel generator maintenance identified
that the persons performing activities were knowledgeable of
existing administrative controls requirements and technical aspects
of the maintenance to be performed. Procedures were detailed and in
1 all but one case accurate. During maintenance it was noted that the
licensee maintained good records, took accurate data and performed
appropriate quality reviews.
Early in the period substantial problems were encountered with the
quality of the polar crane maintenance and inspection. In response,
the preventive maintenance program was expanded and upgraded. NRC
reviewed the licensee's revised preventive maintenance program for
, the crane. Procedures are detailed. the data sheets are reviewed,
compared to established acceptance criteria and trended by the
-electrical maintenance engineer with responsibilities for the polar
crane. The licensee has also developed a~ lubrication schedule which
is tailored to the TMI-2 polar crane.
The NRC routinely observed major maintenance items. An example was
the replacement of a Neutralizer Tank (Radwaste) Transfer System
Filter due to high differential pressure and increased radiation
level. The NRC witnessed activities. including review of the Unit
Work' Instruction, valve cycling, opening of breakers and subsequent
tagging. Supporting departments, including Radiological Controls,
Waste Management, Plant Operations, and Plant Engineering had
effectively coordinated and consolidated their efforts during this
evolution. As a result, the replacement was effected without
4
incident even though' working conditions were difficult due to
working in a high radiation area.
)
. - , . . - . . -~ -
-_ -
.
.
24
As a prerequisite for initiating flooding of the deep end of the
refueling canal, the licensee inspected and subsequently refurbished
components of the fuel transfer system. During the NRC reviews it
was determined that the Startup and Test Group performed the testing
in accordance with instructions and procedures, Plant Engineering
performed required safety analyses for "like kind" replacement of
components, and that there was adequate QA and QC coverage and
review for the fabricated parts. NRC review of the Unit Work
Instruction, Preliminary Safety Evaluation, Engineering Safety
Analysis, QC Plant Inspection Report, Radiation Work Permits and
Test _ Procedures and other associated documentation revealed that the
documentation was complete and accurate to support the work. The
work was performed well and problems identified during conduct were
corrected.
There were two violations in this functional area during the
evaluation period. These were isolated cases and no programmatic
breakdowns were identified in either case.
Conclusion.
Rating: 1
Trend: Consistent
Recommendations
Licensee: None
NRC: None
,
4
.m.____._..______.____._.___.___..._________.____._i..___._____-__.__'__..___.._________.___
.
.
25
F. Design, Engineering and Modifications
Analysis
The analysis in this area is based primarily on the results of
technical and safety evaluations and regulatory oversight reviews
performed by the NRR technical staff of major plant design change
and modification packages. There has been no programmatic
inspection performed in this area, though indepth reviews of the
licensee's implementation of the Quality Assurance (QA) Plan did
evaluate some aspects of the design change / modification program.
The licensee's current engineering organization has evolved through
the integration of GPU Nuclear and Bechtel staffs under one
management. This organization involves three separate, but
coordinated, staffs consisting of Plant Engineering and Site
Engineering located at the TMI site, and Design Engineering located
at the Bechtel project offices in Gaithersburg, Maryland. There was
no GPUN Technical Functions involvement in the design and
modification process. The engineering activities during this
assessment period have been primarily related to support of the
cleanup and defueling effort. Projects have involved engineering
support of plant operations and maintenance activities, plant
decontamination support, onsite management of plant modification and
construction, and detailed engineering design and procurement
related to major plant system modifications.
The organization is currently staffed with sufficiently qualified
personnel to provide an adequate level of multidisciplinary review
and management oversight. The organization is adequately defined in
procedures and policy documents which describe the functions,
responsibilities, and interorganizational-relationships of the three
engineering staffs. The organization generally assure an adequate
flow of communications, acceptable level of inter-departmental
reviews, and adequate implementation of both the GPU Nuclear
Recovery Quality Assurance Plan and the Bechtel Project Quality
Assurance Plan. Considerable GPUN and Bechtel management attention
are evident in the development of the organization and there have
been frequent management initiatives to modify the organization as
needed to best support the project as it'has evolved.
Although the present organization. appears to be functioning well,
there were several deficiencies noted early in the assessment period
that were indicative of significant problems in the licensee's
technical review process. To implement the review process, the
engineer preparing a document, performs a two step determination to
identify the quality requirements for the item. This determination
requires the use of applicable Regulatory Guides and TMI-2
Administrative Procedures. Secondly, the preparer then determines
the document's " Review Significance." This determination will
)
_ _ _ _ _ _ _ - _ _ - _ - - - _ _
s
.
26
indicate whether the document will be independently reviewed by the
Safety Review Group subsequent to reviews by the Responsible
Technical Reviewer (RTR) and the Cognizant Engineer (CE).
Throughout this review and approval process, the Modification
Control Group is responsible for tracking, expediting, and ensuring
that the document-has the required concurrences and that additional
requirements identified during the reviews are incorporated in the
final document.
Early in the period there was a general lack of understanding of
this review process and applicable regulatory requirements,
particularly with the Bechtel organization in Gaithersburg,
Maryland. There were instances where the licensee's review
concluded that a modification did not involve an unreviewed safety
question (USQ) but the documented evaluation lacked adequate
engineering basis to support that conclusion. There appeared to be
a tendency for the engineering staff to conclude that a design change
did not involve a USQ because the change was temporary or because it
involved a portion of a system that was classified as "not important
to safety." In one case, the licensee approved an Engineering
Change Authorization (ECA) to install a temporary waste
solidification system in the Auxiliary Building that was determined
by the licensee to not involve a USQ. The basis for that
determination was that the installation was temporary. In addition,
there was lack of assessment of a modifications impact on overall
pl. ant safety. The licensee approved a Unit Work Instruction (UWI)
to remove a section of decay heat system piping inside the reactor
building. The licensee's evaluation failed to recognize the fact
that the modification would have resulted in a containment
penetration being in a configuration that did not conform to the .
'
General Design Criteria.
As a' result of NRC concerns regarding adequacy of licensee reviews,
the licensee implemented a training program which included indepth
training of all RTRs and CEs. As a result of the training program,
there has been significant improvement in this area. The licensee
has shown a better awareness of the regulatory requirements,
attention to detail and overall safety impact of' design changes.
Later in the assessment period, major engineering activities were
accomplished with extensive prior planning and a generally sound
technical approach. Examples include fuel transfer canal
modifications, stationary work platform and fuel pool modifications.
Ther.e was significant management involvement in these efforts, and
an adequate level of interdisciplinary review was evident. There
also appeared to be a much better understanding by the licensee's
staff of the internal policies and programs relating-to.the
.
engineering and design review process. The licensee demonstrated a
!
much improved awareness of the regulatory and safety aspects of
these programs and a generally conservative approach toward insuring
health and safety of both the public and the onsite work force. The
_ - _ _ - _ - _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ - - - . __. . _ _ _ _ _ - - - _ _ _ _ _ _ _ _ - - _ _
"s.
- fi
27
licensee's technical review process showed considerable improvement
-with multiple levels of review, good flow of communication, good
feedback mechanisms within the organizations, and positive response
to resolve safety and. technical issues identified during the review
process.
Overall, the licensee has established an acceptable design,-
engineering and modifications program that provides for a sound
technical approach to solving engineering problems, adequate levels
of management control, acceptable degree of. technical review, and
resolution of technical problems in a manner that assures public
health and safety and conformance to regulatory requirements.
Conclusion
Rating: 2
Trend: Consistent
Recommendations
Licensee: Continued licensee attention to understanding the
application of regulatory requirements.
NRC: None
)-
- ..
,
'
T
l'
28
,
Analysis
NRC observations in this area were oriented towards Unit 2 support
of Unit 1 activities and included: (1) participation and witnessing
>
of the-Unit 1 Annual Exercises on October 3, 1984 and. November 20,
1985; (2) Unit 2 support activities associated with TMI-I drills;
i (3) routine monitoring of Unit 2 quarterly departmental and
!
integrated practice drills and (4) review of emergency plan
implementation during actual events.
Management attention to viable emergency planning was evident. In
'
addition to quarterly integrated site drills and unannounced shift
- drills, the licensee has initiated quarterly ' shift walk throughs for
specific departments (e.g. operations, radiological controls,
security, maintenance, and Chemistry), to enhance emergency response
training.
1
During declared unusual events, implementation of ~ the applicable
portions of the emergency plan was appropriate. The response of
control room personnel, problem identification, corrective steps,
and required notifications were accurate and timely.
'
Emergency Preparedness is an overall site function and its
effectiveness will be evaluated in the next full Unit 1 assessment.
Conclusion
Rating: No Basis
Trend: No Basis
1 Recommendations
- Licensee
- None
NRC: None
l
l
l
l
-w e w y <-. ~ -
-*y-
,
,
g
29
H. Security
Analysis
The licensee has created a corporate position of Director of
Security who is dedicated to the nuclear security programs at'Three
Mile Island Units 1 and 2. A small amount of ' inspection effort has
been conducted in this area at Unit 2. More security inspection
effort has been carried out'at Unit 1. The effectiveness of the
security organization will be evaluated with the next full Unit I
assessment.
Conclusion
Rating: No Basis
Trend: No Basis
Recommendations
Licensee: None
NRC: None
)
e
t'
30
I. Licensing Activities
Analysis
Evaluation and monitoring of licensing activities during the assess-
ment period occurred primarily by routine contact between the
licensee's licensing staff and the NRC headquarters and onsite
staffs. A total of 81 licensing actions were initiated by the
-licensee during the assessment period. A breakdown of the' licensing
actions by categories is given in Table 5 of this report.
As a result of the unique and changing status of the TMI-2 facility
the number of licensing actions has been relatively large. This has
required coordination and frequent contacts between NRC -and licensee
staffs. The level of management _ involvement during the assessment-
period was significant. Of particular note has been the extensive
involvement of management in licensing activities such as head lift,
plenum removal and commencement of defueling. Licensee management
has also acted to encourage interaction between licensee and NRC
staff level personnel. This interaction has expedited NRC reviews,
by promoting early resolution of technical issues and has,
accordingly, acted to ensure that cleanup activities are carried out
promptly. Licensee management has established frequent and routine
communication with NRC management to coordinate licensing priorities.
This was particularly useful in the identification of those licensing
actions, including changes-to the Technical Specifications that were
required prior to beginning defueling.
Responses, formal and informal, to NRC requests for detailed
technical information during licensing reviews were generally
timely. While the licensee has disagreed'with some NRC technical
positions these issues were quickly elevated through the licensee's
management chain to an appropriate level for resolution.
The licensing staff has acted as the principal point of contact with
the NRC staff. This organization has been effective in coordinating,
within the licensee's organization, resolutions of NRC technical
concerns. The licensee has demonstrated a thorough understanding of
the technical issues-and NRC requirements. Resolutions to technical
problems have been conservative and sound. As an example, the
licensee carried out a detailed study to determine the best means
for preventing the possibility of recriticality in the reactor
coolant system. This work utilized, as contractors, recognized
experts in the criticality field and relied upon bounding
conservatisms in developing a strategy.
Descriptions of most proposed actions'have been detailed and
thorough. However, the licensee has on occasion failed to provide
the NRC staff with adequate initial information on their safety
evaluation for a proposed action. For example, during the review of
the technical sp'ecification request to lower the containment airlock
e-
1
31
door seal pressure a number of phone calls and a visit by an NRC
staff member was required to determine that their position was
acceptable.
In response to NRC staff requests the licensing staff has updated,
on a weekly basis, all licensing action items and has made a strong
effort to keep the NRC staff informed of the status of these items.
The licensee has an effective system to prioritize licensing
actions. Highest priority is given to issues with a potential for
directly impacting the cleanup schedule, while a lower priority is
assigned to those items that are not on the critical path. This
prioritization and close schedular coordination with the NRC staff
has generally been effective in helping to assure that licensing
actions are completed on a schedule that supports expeditious
cleanup.
Conclusion
Rating: 1
Trend: Consistent
Recommendations
Licensee: None
NRC: None
)
_
. .
- .
32
V. SUPPORTING DATA AND SUMMARIES
A. Licensee Event Report (LER) Tabulation and Causal Analysis
Tabular Listing
.
Type of Events
a. Personnel Error 10
b. Design / Manufacturing / Construction /
Installation Error 1
c. External Cause 0
d. Defective Procedures 3
, e. Component Failure 10
,
f. Other 3
Total 27
t
Licensee Event Reports reviewed:
- Report Nos.84-007 through 85-008
Causal Analysis
j
4
No trends were identified in the analysis performed on the LERs
z although three areas revealed some commonality.
1. Report Nos. 84-10, 84-13, 85-06, 85-07, and 86-02 involved
personnel error in implementing administrative requirements.
.
2. Report Nos. 84-09, 84-16, 84-21, 85-02, and 85-03 involved the
j inoperability irf incore thermocouples (accident damage).
$c 3. Report Nos. 84-12, 84-15, 85-08, and 85-10 involved
implementation of fire protection requirements.
B. Investigation Activities
During the SALP evaluation period one investigation was completed
pertaining to reactor coolant system leak rate data falsification
prior to the March 28, 1979 accident. The investigation culr.inated
in the Nuclear Regulatory Commission issuing an Order and Notice of
Hearing dated and served on December 18, 1985.
A report dated September 5, 1985 and titled, " Potential Willful
,
Material False Statement Concerning Polar Crane Modification" was
issued by NRC's Office of Investigations. This report ~is being
,
utilized by the agency in its consideration of appropriate enforcement
action related to polar crane violations.
,
_ _ _ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ . . . . - . _ _ _ _ . . _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ . _ . . _ _ . _
._.
.
3-
.
.. .
33
' C. Escalated Enforcement Actions '
-
1. Civil Penalties
On August 12, 1985, the NRC Office of Inspection and Enforcement
issued a Notice of Violation and Proposed Imposition of Civil
Penalty of $64,000. The Notice of Violation was for the
licensee demonstrating acts of discrimination against a contract
employee for raising safety concerns and communications with the
NRC. This was a violation against 10 CFR 50.7 which prohibits
such discrimination and was considered a Severity Level II
'
.
violation. On March 4,1986, the Director of the'0ffice of
i Inspection and Enforcement ordered the licensee to pay the civil ,
'
penalty. (Not applicable to activities during the assessment.)
! 2. Orders
An Order and Notice of Hearing was issued by the Nuclear
Regulatory Commission on December 18, 1985 concerning reactor
coolant system leak rate data falsification. (Not applicable
to activities during the assessment.)
i
- 3. Confirmatory Action Letters (CALs)
There was one CAL issued during the assessment period which was
dated October 2,1985. The escalated enforcement issue
'
pertained to the licensee's failure to properly determine the
Sr-90 content of radioactive waste material.
D. Enforcement Conferences Held During the Assessment Period
'
During the SALP assessment period, four enforcement conferences were
conducted to discuss the licensee's corrective actions for the
i following enforcement issues.
'
One enforcement conference was held at the Region I Office on August
17, 1984 to discuss the licensee's failure to secure and deactivate
the containment isolation valve on the "A" train purge line with the
outboard isolation valve inoperable while purging through the "A"
l train (Inspection Report No. 50-320/84-13, Enforcement Conference
Report No. 50-320-84-13).
Another enforcement conference was held at'the Region I offices on
February 8, 1985 to discuss the licensee's failure-to adequately
protect Safeguards Information from unauthorized disclosure on three
recent occasions (Inspection Report No. 50-320/85-02, Enforcement
Conference Report No. 50-320/85-05).
i
i
)
T
. _ _. ._.
s
N'
34
I
4
Also,1on February 8,1985, another enforcement conference was held
in the Region I offices to discuss the NRC concerns that work
activity involving entry into the seal injection valve room was not
adequately planned in that prior to entry, proper consideration was
not given to the high energy beta sources that were known to exist
- in the room (Inspection Report No. 50-320/85-03,- Enforcement
- . Conference Report No. 50-320/85-07).
The fourth enforcement conference was held in the Region I offices
on October 9, 1985 to discuss an error in the determination for
, Sr-90 content in radioactive material which had existed for four
years without detection. This error resulted in the Sr-90 content
being systematically understated by'a factor of two in most radwaste
shipments (Inspection Report No. 50-320/85-20).
1
T
i
I
l
l
!
!
I
o
f
a
TABLE 1
INSPECTION HOURS SUMMARY (5/1/84 - 2/28/86)
THREE MILE ISLAND UNIT 2
HOURS % OF TIME
1. Shutdown Plant Operations / 1935 32
Defueling Preparation
2. Radiological Controls 2937 49
'
3. Effluent Monitoring and Control 400 7
4. Quality Assurance 328 5
5. Maintenance 233 4
6. Design, Engineering and Modifications N/A N/A
7. Emergency Preparedness 131 2
8. Security 45 1
9. Licensing Activities N/A N/A
Total 6009 100%
.
I
.
4
TABLE 2
INSPECTION ACTIVITIES
THREE MILE ISLAND UNIT 2
INSPECTION REPORT NUMBER AREAS INSPECTED
84-09 Resident inspection
-10 Resident HP inspection, radwaste
-11 Resident inspection, preparation for
head lift
-12 Quality Assurance Program
-13 Review licensee's failure to close and
deactivate isolation valve on "A"
purge train with second isolation
valve inoperable
-14 Plant operations, radioactive material
shipments, Resident HP inspection,
radiological control practices
-15 Resident HP inspection, reactor
building operation
-16 Reactor operator examinations
-17 Resident inspection, plenum lift
preparations
-19 Resident inspection, polar crane
modifications
-20 Security plan and implementation of
security programs
-21 Resident HP inspection, dosimetry
-22 Operational radiological environmental
monitoring program
-23 Resident inspection
-24 Resident inspection
i
s
\
T2-2
-25 Resident HP inspection
85-01 Resident inspection
-02 Protection of Safeguards Information
-03 Unplanned radiation exposure to skin
of three individuals
-05 Enforcement Conference
-06 Security plan and implementation of
security programs
-07 Enforcement Conference
-08 Resident inspection
-09 Reactor operator examinations
-10 Resident inspection, plenum lift
preparation
-11 Defueling Water Cleanup System design
and fabrication
-12 Resident inspection
-13 Examination of the requalification
program for certification of presently
licensed SR0s to directly supervise
defueling operations
-14 Resident inspection
-15 Resident HP inspection, misclassified
radioactive waste material shipped
from site
-16 Resident inspection
-17 Reactor operator examinations
-18 Resident inspection, defueling
preparation
-19 Resident inspection, defueling
operations
>
e
\
T2-3
-20 Special inspection conducted to
evaluate method of determining Sr-90
by beta spectroscopy
-21 Resident inspection, defueling
operation
86-01 Resident inspection, defueling
operations
-02 Resident inspection
-03 Reactor operator examinations
,
b
. - - _ .. . _ _ _ . _. . . _ . -_. _
'
-
g.
'\
TABLE 3
ENFORCEMENT DATA.
THREE MILE ISLAND UNIT 2
, A. Number and Severity Level of Violations and Deviations-
4
1. Severity Level
,
[ Deviations- 0
Violations S.L. I O
i Violations S.L. II 1
i Violations.S.L. III 4
Violations S.L. IV 12
- Violations S.L. V 5
'
Total 22
- '~ .
B. Violations and Deviations vs. Functional Area <
] .
l FUNCi10NAL AREAS I II III IV V DEV
i
1. Shutdown Plant Operations / 1* 2
Defueling Preparation
i 2. Radiological Controls 4 5 3
<
)
3. Effluent Monitoring and Control 1
.
i 4. Quality Assurance
j 5. Maintenance 1 'l
! 6. Design, Engineering and Modifications
1
8. Security 4
j
9. Licensing Activities
,
,
1 4 12 5
- Violation not applicable to activities during assessment.
4
l-
I
l
-i
i 1
. . . .
..
e
T3-2
C. Summary
Inspection Severity Summary of
Report No./Date Level / Functional Area Violation
84-09 V Failure to post a
4/24/84-5/30/84 Rad Con Notice of Violation
involving radiological
working conditions as
required by 10 CFR Part
19
84-10 V Failure to calibrate a
5/14/84-5/29/84 Effluent Monitoring radioactive process
effluent monitor in -
accordance with written
procedures
84-13 I" Violation of Technical ,
5/25/84-6/29/84 Operations Specification limiting
condition of operation
84-21 IV Failure to control
10/16/84-11/26/84 Security Safeguards Information
84-21 IV Failure to adhere to
10/16/84-11/26/84 Rad con Rad Con Procedure
85-01 V Failure to attach Do
1/12/85-2/28/85 Maintenance Not Operate tag'to
inoperable breaker
85-01 -V Failure to cneck
1/12/85-2/28/85 Rad Con available dose for
individual entering RWP
area
85-03 III Failure to perform
1/14/85-1/22/85 Rad. Con adequate rad survey
85-03 III Failure to adhere to
1/14/85-1/22/85 Rad Con RWP
85-03 III Doses above
1/14/85-1/22/85 Rad Con administrative limits
85-06 IV Failure to properly
3/4/85-3/8/85 Security control photo ID badges
L___--__--_-_ _-- - - - ------------ --- -- --- ---- - - - - - - - - - - - - - - - - -- --
- . _
o
S
T3-3
,
85-06 IV Failure to complete
'3/4/85-3/8/85 Security annual physical fitness
tests by three
protection personnel
85-08 IV Failure to comply with
3/1/85-4/19/85 Maintenance procedures regarding
ventilation system
maintenance practices
85-10 IV Failure to comply with
4/11/85-5/17/85 s
Security procedures regarding
security practices
85-15 III Failure to properly-
7/31/85-8/5/85 Rad Con package and classify
waste in accordance
with Reg Guide
85-16 V Failure to inspect
8/6/85-9/6/85 Rad Con respiratory equipment
85-20 IV Failure to properly
9/30/85-10/2/85 Rad Con indicate Sr-90 content
on rad material
shipping papers
85-20 IV Failure to properly
9/30/85-10/2/85 Rad Con classify radwaste
shipment
85-20 IV Failure to properly
9/30/85-10/2/85 Rad Con indicate Sr-90 activity
on rad material
shipping papers
85-21 IV Failure to comply with
10/7/85-11/8/85 Operations a double isolation
valve requirement
85-21 IV Failure to perform
10/7/85-11/8/85 Rad Con adequate surveys prior
to entry
I&E Headquarters & II Personnel harassment
01 Report Operations
l
1
!
u
a
i
!
TABLE 4
LER SYNOPSIS
THREE MILE ISLAND UNIT 2
i
May 1, 1984 - February 28, 1986
LER Number Summary Description
84-007 Operation of RB purge system outside bounds of
Technical Specifications84-008 Examination and evaluation of pressure and level
transmitters for core flood tanks
'84-009 Incore thermocouple N-4 was declared inoperable
84-010 Operation of containmer.t isolation valves without
proper administrative approval
~
84-011 Exceeded timeclock without entering action statement
after defeating the Control Room air inlet radiation
monitor, HP-R-220, interlock
84-012 Failure to test within the required interval a Fire
i
System detector located in Control Building
84-013 Reactor Building airlock doors were operated using a
Temporary Change Notice that had not been submitted
to the NRC for approval
84-014 Representative reactor coolant samples were not
obtained due to failure to verify opening 'a manually
operated valve
]
84-015 Hourly fire watch was not performed when a fire door
was breached l
84-016 Incore thermocouples M-3, 0-10 and F-3 were declared
84-017 Sections of submerged toe of thetdike exhibited
evidence of degradation.84-018 "A" diesel generator was out of service to . replace
cylinder assembly and exceeded timeclock
)
.. . .. ..
. - _ _ _ _ _ _ - _ - _ - _ . _ --
.
. __
..
A .
V .
c
i T4-2
l
84-019 Action statement was not entered when the Fuel
Handling Building ventilation exhaust flowrate
dropped below the minimum limit of the Technical
Specifications84-020 The RCS sample performed through the TNS system was
non-representative because sample line not adequately
purged
t 84-021 Incore thermocouples F-12, 0-5, and G-11 were
- declared inoperable
85-001 Minor degradation of the Flood Protection dike
85-002 'Incore thermocouple E-4 declared inoperable
85-003 Incore thermocouple G-13 declared inoperable
85-004 Reactor Building Internal Pressure Indicator
i Registered Value in excess of Technical Specification
! limit
85-005 Reactor Building Internal Pressure Indicator
Registered Value in excess of Technical Specification
limit
85-006 Administrative error in operating procedure stating
wrong valve position
85-007 Containment isolation valve operated without an NRC
approved procedure
85-008 . Fire Suppression System inoperable for Emergency
Diesel Generator
85-009 .0pened Containment Isolation Valve
85-010 Failure to test the TMI-2 Fire Suppression Water
System Valves ,86-001 Inoperability of Emergency Diesel Generator exceeds
l
7-day timeclock
86-002 Containment Isolation Valve opened without
identifiable cause
l
l
l
!
i
. ._--- _ _ _ ______________________- _ ___ _ _____ _____ - -___-_-__ _ __________-_-___ _ ____- --_ ___.__.-_ - _ _
um:w
a
.'o
TABLE 5
SUMMARY OF SIGNIFICANT LICENSING ACTIONS
AND SUPPORTING ACTIVITIES
THREE MILE ISLAND UNIT 2
This table provides a summary of significant licensing actions and related
activities during the SALP evaluation period from the 1st of May 1984 through- !
the 28th of February 1986.
1. Updates to the Programmatic Environmental Impact 3tatement (1 completed) l
. Issuance of a Final Supplement Dealing with Occupational Radiation
Dose
2. Major Cleanup Evolutions (21 completed, 6 ongoing)
. Reactor Pressure Vessel Head Removal
--
Head Removal SER
. Reactor Pressure Vessel Plenum Removal
--
Plenum Removal Prep Activities SER I
--
Plenum Jacking SER
--
Reactor Building Heavy Loads Analysis for Plenum Lift
--
Polar Crane Auxiliary Hoist
--
Plenum Lift SER
--
Plenum Load Drop Analysis
. Defueling Actions
--
Preliminary Defueling Activities
--
Early Defueling SER
--
Defueling Canister TER *
--
Boron Dilution Hazards Analysis
--
Fuel Storage Rack TER
--
Defueling Water Cleanup System TER, Rev. 4
--
Heavy Load Handling SER for Defueling
--
Filter Canister QA Approval *
--
Fuel Pool "A" Refurbishment SER
--
Reactor Building Decontamination and Dose Reduction Program SER
--
Internals Indexing Fixture Processing SER
--
Modifications of Fuel Canisters
--
Modifications of Fines / Debris Vacuum System
--
NES Canister Closeout
--
Use of Debris Canisters >
--
Canister Handling - Preparations for Shipping *
--
Reactor Building Sump Criticality *
--
Temporary RCS Filtration System
--
i
--
Defueling Water Cleanup System TER, Rev. 7-9 *
)
4
i
i
. . - ,- . .- - .. _ . .
4
-
e
T5-2
. SER for Core Stratification Sample Acquisition *
. Relocation of Missile Shields SER
. Purification Demineralizer SER - Cs Elution-
- Ongoing as of February 28, 1986 '
4
. Submerged Demineralizer System TER Update
! . Once Through Steam. Generator Layup TER
- . Containment Air Control Envelope TER
4. Other Documents in Support of Cleanup (6 completed, 2 ongoing)
. Applicability of Seismic Design Critaria to GPUNC Recovery Efforts
. Clarification of the General Project Design Criteria
. Containment Access Control Envelope Design Criteria
<
. Solid Waste Staging Facility TER *
,
. Waste Handling Packaging Facility *
. GPU/0RNL Criticality Report
i .
Fuel Characterization in the Lower Vessel Head
. PWST and Recycle System / System Description
i 5. Exemptions (10 completed, 2 ongoing)
j .
Waste Classification of EPICOR II Resin Liners
!
. In-Service Inspection *
,
, Core Accountability
. Fire Protection *
<
. Pressurized Thermal Shock
<
. Residual Head Removal System and Testing Requirements for the ECCS
i . Code Safety Valves
i . Seismic Monitoring Requirements
i . FSAR Updating Requirements Relative to the QA Revisions
1 . Containment Penetration Design
, . Seismic Requirements for Containment Penetrations
! . Containment Isolation' Valves
- 6. Changes to the Technical Specification
! . Issued: 8
. Ongoing: 0
,
,
7. Recovery Operations Plan Change Requests '
. Issued: 10
. Ongoing: 1
,
i 8. License Amendments
. Issued: 2
- . Ongoing
- 2
i 9. Organization Plan Changes
- . Issued
- 4
. Ongoing: 0
4
I
r.
'
n
.
g> -
o
T5-3
e
/
10. Licensee /Commissior. Briefings - 2 i
.
Cleanup Schedule and Funding
- Ongoing as of February 28, 1986
t
I