W "O DUKE POWER Goxnoxy P.O. Box 33180 CHARLOTTE, N.C. 28242 HAL H. TUCKER mEPHONE 04 JUN I4 Pl2 ; g
[E June 11, 1984 Mr. James P. O'Reilly, Regional Administrator U. S. Nuclear Regulatory Commission
_ Region 11 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30323 Re: Catawba Nuclear Station Units 1 and 2 Docket Nos. 50-413 and 50-414
Dear Mr. 0'Reilly:
In my letter of May ll,1984 transmitting Significant Deficiency Report SD 413-414/84-09, it was incorrectly stated that inspection personnel have been instructed that verification of tubing clamps would be perfonned at the mechanical inspection of the support.
Inspection personnel were instructed to perform this verification at the torque inspection.
Please find attached a revised statement of the corrective action for this deficiency. All corrective action has been taken and we are in full compliance.
Very truly yours, k
Hal B. Tucker LTP/php Attachment cc: Director INP0 Records Center Office of Inspection & Enforcement Suite 1500 U. S. Nuclear Regulatory Commission 1100 Circle 75 Parkway Washington, D. C. 20555 Atlanta, Georgia 30339 NRC Resident Inspector Mr. Robert Guild, Esq.
Catawba Nuclear St, tion Attorney-at-Law P. O. Box 12097 Palmetto Alliance Charleston, South Carolina 29412 21351 Devine Street
. Columbia, South Carolina 29205 Mr. Jesse L. Riley Carolina Environmental Study Group 854 Henley Place Charlotte, North Carolina 28207 8406190155 840611 19,COVI.
gDRADOCK 05000413 Off PDR V
g}
UT~
3 ?e i,
Catawba Nuclear Station-Units 1 and 2'
,~-
SD 413-414/84-09 June 11, 1984 Corrective Action (Revised):
All individuals.. involved with the) erection and inspection of tubing supports have been made aware'of this' situation. To. prevent recurrence, inspection
~
l personnel have been' instructed that verification of tubing clamps shall be performed at. torque inspection rather than at the mechanical inspection of the support.
i I
J l