Text
p' *
- Geir,'o, r
UNITED STATES
! 't.
5.(di[hI)'~ e.,., j NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555
. t' ** 0 /i December 14, 1983
%,.....f e
f1Ef40RAflDUM FOR:
Darrell G. Eisenhut, Director Division cf Licensing FROM:
Thomas i:. foovak. Assistant Director for Licensing Division of Licensing
SUBJECT:
WT4P-2 LICEfiSE This memorandum is an update of cur December 1,1983, status report.
WT4P-2 is projected by Region V to be ready to load fuel December 16, 1983, at the earliest.
The following list identifies issues that require staff resolution to support this licensing action:
Fire Protection (DE)
CEB provided a list of acceptable fire protection deviations from BTP Cf4EB 9.5-1.
These have been incorporated into Attachment 4 of the license.
Hydrodynamic Loads (DE)
MEB provided SSER =4 input for the effect of hydrodynanic loads on its piping and components inside the containment justifying operation to Si..
The license has been conditioned to require resolution prior to Si;.
Equipment Qualification - Seismic (DE)
Justification has been provided for interim operation. Final qualification is being required prior to startup following first refueling as a license condition.
8312230111 831214 N
e ADOCK 05000397
)
I
w '
NRC Verification of Control Room Design Improvements -
Human Factors (DHFS)
Following the site visit the week of December 5, 1983. DHFS provided SSER input approving WPPSS program completion schedule which is reflected in Attachment 2 to the license.
CAT Inspection Issues (Region V)
Region V to provide the status of the review of WPPSS response on CAT issues.
Input from NRR/DE needed to close two isses - rebar placement and welding requirement deviations, is expected December 14, 1983.
2.206 Petition (IE)
On October 18, 1983, the Coalition for Safe Power filed with the Commission a petition requesting revocation of the CP and denial of an OL for WNP-2. NRC staff acknowledged receipt of the petition in a letter dated November 9, 1983.
Interim response to 2.206 has been drafted supporting operation to 5%.
IE memo to NRR supporting 5% power is expected 12/14/83.
Design Verification (DE/IE/ Region V)
The final design verification program report is currently under staff review. An NRC staff interim evaluation supports operation to 5% power.
No license condition is necessary. Final evaluation will be reported in a future SSER.
Region V is preparing Attachmert 1 to the license identifying carry-over items to be made license conditions. A partial draft is expected December 13, 1983.
'"-81041sie.g q,
Thomas M. Novak, Assistant Director for Licensing Division of Licensing cc: