Rev 14 to QA Program Description,South Texas Project Electric Generating Station QA During Design & Const
ML20197B003
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 05/02/1986
From:
EBASCO SERVICES, INC.
To:
Shared Package
ML20197A965 List:
References
NUDOCS 8605120438
Download: ML20197B003 (111)


Text

__

.e '

PART C EBASCO QUALITY ASSURANCE PROGRAM DESCRIPTION SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION QUALITY ASSURANCE DURING DESIGN AND CONSTRUCTION (STP-ETR-1001 Rev. 13)

REVISION 14 5/2/86 Date 8

hh A

O ,

l l EBASCO

! QUALITY ASSURANCE PROGRAM DESCRIPTION PART C I

e00 OXO Y

i HOUSTON LIGHTING & POWER COMPANY ELECTRK: GENERATING STATION UNITS 1 & 2

- = ,

ESASCO SERVICES INCORPORATED Two World Trade Center, New York, N Y.10048

(@dQ FOREWORD This Quality Assurance Program Description - Part C, reflectc ofiicial Ebasco policy and has been prepared to also reflect the requirements of the United States Nuclear Regulatory Commission document 10 CFR 50 Appendix B (18 Quality Assurance Criteria), and American National Standards Institute document N45.2), entitled Quality Assurance Program Requirements for Nuclear Power Plants.

Enclosure " Statement of Authority" dated June 29. 1984 confirms the authority for the establishment of a Quality Assurance Program and a Quality Assurance Program Manual.

The enclosure letter of R H Vollmer to L F C Reichle dated May 12, 1975 is the NRC's acceptance of Ebasco's Quality Assurance Program Manual (Ebasco Report ETR-1001 Revision 0, March 14,1975).

The enclosure letter of U Potapovs to B E Tenzer dated May 4, 1984 is the NTC's latest acceptance of Ebasco's Quality Assurance Program Manual, Revision 12, dated June 1984 which is the current edition of the Manual and the basis of this Quality Assurance Program Description and the Ebasco Nuclear Quality Assurance Program Manual for the South Texas Project.

The primary responsibility for overall implementation and administration of the Ebasco Quality Program rests with the Vice President Corporate Quality Programs as delegated to him by the President. The Director Quality Assurance is assigned the responsibility and authority to enforce Ebasco Quality Program requirements and has the unqualified support of corporate management. His decisions may not be overriden by personnel in any division or department, except with the written consent of the Vice President Corporate Quality Programs or the President.

The Director Quality Assurance shall staff this project to the extent necessary to perform Quality Assurance tasks directly and audit

, departments other than his own in their performance of tasks related I

to Quality Assurance. The Director Quality Assurance has the authority to require immediate correction of.any non-conforming activity or condition to comply with Ebasco Quality Program requirements, or if necessary, to stop work until suitable corrective action has been taken or a satisfactory resolution reached.

i b[ ~

! B E Tenzer r Vice President Corporate Quality Programs April 19, 1985 Revision 11 l

l L

EBASCO SERVICES INCORPO2ATED Two World Trace Center, New York, N Y.10048 EBATO SIATDENT T AUDORr1Y The managenent of ham Services Irwigated remgnizes the necessity for a emprehensive Quality P&wimu for Nuclear Pcur Plants. ham Ct21pany Procedure No. N-21 eseah14=hes the basic organization, assigns authorities and respmsibility for inplansting the Quality Prwimu, and establishes the regairunent for a wimate Quality Assurance Ma:1ual. Accordingly, this Manual r ests h am Quality Pr%imu policy. In this respect, it is to be used as a standard by perscrinel in all Fhaam organizaticmal units.

The primary respcmsibility for overall inplementation and adninistration of the ham Quality Assurance Prwima rests with the Vice President Corporate Quality Programs as delegated to him by the President. The Quality Pr%iau remittee has been eseah14=hed under the auspices of the President, consisting of representatives of designated Vice Presidents. The Cmmittee is peImanent and its Chair-man shall be the Vice President Corporate Quality Programs.

R '6 Christesen President June 29,1984

DNITED STATES NUCLEAR REGULATORY COMMISSION W ASHINGTON. D. C. 20555 MAY 1 2 1975 Mr. Leonard F. C. Reichle Vice President Ebasco Services Incorporated Two Rector Street New York, New York 10006

Dear Mr. Reichle:

We have reviewed and evaluated the Ebasco Services Incorporated (ERASCO)

Nuclear Quality Assurance Program Manual (Ebasco Report ETR-1001, Revision 0, March 14, 1975). We find that it describes an acceptable Quality Assurance Program for the design, procurement, and construction activities which are within the Ebasco scope of work for nuclear power plants.

For the Ebasco Quality Assurance Program, applicants need only reference this Topical Report in Section 17 of license applications. We do not intend to repeat our review of this Topical Report when it is referenced in an applica tion.

Should regulatory criteria or regulations change such that our conclusions about this Topical Report are invalidated, we will notif y you. You will be given the opportunity to revise and resubmit it should you so desire.

Please include a copy of this letter and our evaluation in each of the reports and resubmit 70 copies to the NRC.

Sincerely, L

Richard H. Vellmer, Chief Quality Assurance Branch Division of Reactor Licensing

Enclosure:

NRC Topical Report Evaluation of Ebasco Report EIR-1001,Rev. O, 3/14/75 40tuffo4 d6 46

? 1 9 N N N

  1. / 76-1916

. +

TOPICAL REPORT EVALUATION Report Number: ETR-1001, Rev. O, Nonproprietary Report

Title:

Ebasco Nuclear Quality Assurance Program

' Report Date: March 14, 1975 Originating Organization: Ebasco Services Incorporated Reviewed By: Quality Assurance Branch

SUMMARY

OF TOPICAL REPORT Topical Report ETR-1001, Rev. O describes the Quality Assurance (QA)

Program which the Ebasco Services Incorporated (Ebasco) applies to those design, procurement, and construction activities involving safety related structures, systems, and components of nuclear power plants within the Ebasco scope of work. ETR-1001, Rev. O connits Ebasco to comply with the requirements of Appendix B to 10 CFR Part 50 and to follow the QA guidance provided by the NRC in:

1. " Guidance on Quality Assurance Requirements During Design and Procurement Phase of Nuclear Power Plants," WASH 1283, Rev.1, May 24, 1974, and
2. " Guidance on Quality Assurance Requirements During the Construction Phase of Nuclear Power Plants," WASH 1309, May 10,1974.

Ebasco has provided for our evaluation a detailed organizational description of those individuals and groups involved in carrying out activities required by the QA Program and a delineation of duties, responsibilities, and authority of those organizational elements involved in the QA Program. ETR-1001, Rev. O contains a description of the measures used to carry out the Ebasco QA Program activities and describes how applicable requirements of Appendix B will be satisfied by the administration and implementation of these measures.

SUMMARY

OF REGULATORY EVALUATION We have evaluated the QA Program and the organizations responsible for QA functions as described in ETR-1001, Rev. O. We find that QA policy and direction originate at an acceptably high management level and are ef fectively communicated to other parts of the organization.

Those performing QA functions have responsibility and authority commensurate with their duties in implementing the QA Program. We also find that measures have been establishec, to be implemented by written procedures and instructions, which address each of the criteria of Appendix B and demonstrate conformance with each criterion.

Based on our review and evaluation of ETR-1001, Rev. O we conclude that:

1. The organizations and persons performing QA functions within Ebasco have the required independence and authority to effectively carry out the QA Program without reservation or undue influence from those directly

responsible for costs and schedules, and

2. The nasco QA Program contains the necessary requirements, procedures, and controls to demonstrate that quality-related activities will be conducted in accordance with the requirements of Appendix B to 10 CFn Part 50.

REGUl.ATORY POSITION It is the staff's position that the nasco Nuclear Quality Assurance Program Manual (Basco Report ETR-1001, Revision O. March 14, 1975) is acceptable for use in the design, procurement, and construction of nuclear power plants. The Topical Report can be referenced by report ntsaber in Section 17 of future Safety Analysis Reports. ,

t L

  1. ""'*% UNITED STATES p' '

, NUCLEAR REGULATORY COMMISSION D

tf.f REGION IV

$11 RYAN PLAZA DRIVE. SulTE 1000 9 8 ARLINGTON. TEXAS 70011 NAY 041984 Docket No. 99900505 Mr. B. E. Tenzer, Vice President Corporate Quality Programs Ebasco Services. Incorporated Two World Trade Center New York, NY 10048

Dear Mr. Tenzer:

Subject:

NRC Acceptance of Revised Ebasco Quality Assurance Topical Report We have completed our review of Revision 12 to Ebasco Topical Report ETR-1001 submitted through your letters of May 27, July 13, August 5 September 23, October 7. October 31, and November 9,1983, and February 15, 1984. Revision 12 updates the topical report to reflect the current Ebasco Quality Assurance Program.

Based on our evaluation of the proposed changes described in Revision 12, we find that the revised topical report continues to meet the criteria of Appendix B to 10 CFR Part 50 and is, therefore, acceptable. Should regulatory criteria or regulations change such that our conclusions about this topical report are invalidated, we will notify you. You will be given the opportunity to revise and resubmit it should you so desire.

Programmatic changes by Ebasco to this topical report are to be submitted to NRC for review prior to implementation. Organizational changes are to be submitted no later than 30 days after announcement.

To use this topical report in future license applications, applicants need only reference this topical in Section 17 of the SAR. Should it be referenced in a SAR for a new nuclear power project, the basis of our evaluation will be the acceptance criteria in the latest revision to the Standard Review Plan (SRP) Section 17.1 (currently Revision 2). Appropriate l

changes may, therefore, be necessary.

! Please replace our letter of May 17, 1982, with a copy of this letter, I

renumber ETR-1001 as Revision 12 and forward eight copies to the Document Control Desk and one copy to the Vendor Program Branch, Division of Quality Assurance, Safeguards, and Inspection Programs, U.S. Nuclear Regulatory Comission, Washington, D.C. 20555.

l l

l l

t t

Mr. B. E. Tenzer Your submittal should point out the changes by use of a black bar in the margin where a change is made, and the revision number should be adjacent to the bar.

Should you have any questions regarding our review, or if we can provide assistance please contact this office.

Sincerely, M M Uldis Potapovs. Chief o

Vendor Program Branch Division of Quality Assurance, Safeguards, and Inspection Programs l

l l

l

esos aitsrew4s case 1 or 2 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EtAsc0 Services ELECTRIC GENERATING STATION UNITS 1 & 2 ETP-ETR-1001 mcompoa Avao QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C Revision 13 TABLE OF CONTENTS Date 4/10/86 Rev No. Date Introduction & Scope of Services 5 7/5/84 PART I - General Section Title QA-I-1 Quality Assurance Program 9 3/28/86 lR13 QA-I-2 Organization and Responsibilities 9 3/28/86 lR13 QA-I-3 Personnel Indoctrination and Training Program in Quality Assurance 5 9/24/84 QA-I-4 Deleted (not applicable)

QA-I-5 Deleted (not applicable)

QA-I-6 Quality Assurance Records 6 7/26/85 PART II - Engineering Offices Deleted (not applicable)

PART III - Construction Site Section Title QA-III-1 Instructions, Procedures, and Drawings 6 7/26/85 QA-III-2 Document Control 9 3/28/86 lR13 QA-III-3 Deleted (not applicable)

QA-III-4 Deleted (not applicable)

QA-III-5 Deleted (not applicable)

QA-III-6 Nonconformances 6 7/26/85 QA-III-7 Corrective Action 5 7/26/85 3222M Copyright @ 1986, 1985, 1984 Ebasco Services Incorporated

8 009 2t($7 P)4.S$ 2 2 PAGE OF HOUSTON LIGHTING AND power COMPANY SECTION SOUTH TEXA5 PROJECT EsASCO SERYlCE5 ELECTRIC GENERATING STATION UNITS 1 & 2 STP-F Rev on R-100 {3 INCORPORATED QUALITY ASSURANCE PROGRARI DESCRIPTION - PART C TABLE OF CONTENTS Date 4/10/86 PART III - Construction Site (Cont'd)

Section Title Rev No. Date QA-III-8 Control of Special Processes 5 7/5/84 QA-III-9 Quality Assurance Audits 8 7/26/85 QA-III-10 Identification and Control of Items 3 7/5/84 QA-III-11 Inspection 5 7/5/84 QA-III-12 Test Control 5 7/26/85 QA-III-13 Control of Measuring and Testing Equipment 5 11/13/84 QA-III-14 Control of Receiving, Handling, and Storage 6 7/26/85 QA-III-15 Inspection, Test, and Operating Status 4 7/26/85 Appendix I Terms and Definitions 3 7/5/84 Appendix II Ebasco Exceptions to US Nuclear Regulatory Guides and ANSI Standards Indicated in Section QA-I-1 6 7/26/85 3222M l Copyright @ 1986, 1985, 1984 Ebasco Services Incorporated h

L - - - - - -

siosausTes4s pace 1 o, 20 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBA5CO SENCES ELECTRIC GENERATING STATION UNITS 1 & 2 INCORPORATED QUAUTY ASSURANCE PROGRAM DESCRIPTION - PART C QA-I-1 QUALITY ASSURANCE PROGRAM 1.0 SCOPE The purpose of this Section is to describe the Quality Assurance Program of Ebasco Services Incorporated and its applicability to safety-related activities and services performed by Ebasco in the construction of the South Texas Project. This program has been designed to meet the applicable requirements of the United States Nuclear Regulatory Commission 18 Quality Assurance Criteria of 10 CFR 50, Appendix B. It has also been designed to meet the regulatory position of the following USNRC Regulatory Guides and ANSI Standards, with exceptions and clarifications as stated in Appendix II of this Manual:

Standard Title ANSI N45.2-1971 Quality Assurance Program R.G. 1.28 (Rev. O, 6/72) Requirements for Nuclear Power Plants ANSI N45.2.1-1973 Cleaning of Fluid Systems and R.G. 1.37 (Rev. O, 3/73) Associated Components During (See Appendix II Notes 3 through 5) Construction Phase of Nuclear Power Plants ANSI N45.2.2-1972 Packaging, Shipping, Receiving, R.C. 1.38 (Rev. O, 3/73) Storage, and Handling of Items (See Appendix II Notes 6 through 11) for Nuclear Power Plants (During the Construction Phase)

ANSI N45.2.3-1973 Housekeeping During the R.G. 1.39 (Rev. O, 3/73) Construction Phase of Nuclear (See Appendix II Notes 12 and 13) Power Plants ANSI N45.2.4-1972 Installation, Inspection, and R.G. 1.30 (Rev. O, 8/72) Testing Requirements for (See Appendix II Notes 14 and 15) Instrumentation and Electric Equipment During the Construction of Nuclear Power Generating Stations ANSI N45.2.5-1974 Supplementary Quality Assurance (See Appendix II Notes 1 and 2) Requirements for Installation, Inspection, and Testing of Structural Concrete and Structural Steel During the Construction Phase of Nuclear Power Plants 3222M

s ios-msre>4.es ,we 2 o, 20 HOUSTON LIGHTING AND POWER COMPANY SECTION

$00Di TEXAS PROJECT EBA5CO SERWCES ELECTRIC GENERATING STATION UNITS 1 & 2 tNCORPORATED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-I-1 QUALITY ASSURANCE PROGRAM Standard Title ANSI N45.2.6-1973 Qualifications of Inspection, R.G. 1.58 (Rev. O, 8/73) Examination, and Testing As Modified by Positions C.5, C.6, Personnel for the Construction C.7, C.8, and C.10 of Rev. 1 Phase of Nuclear Power Plants (See Appendix II Note 24)

ANSI N45.2.8-1975 Supplementary Quality Assurance R.G. 1.116 (6/76) Requirements for Installation, (See Appendix II Notes 16 through 18) Inspection, and Testing of Mechanical Equipment and Systems for the Construction Phase of Nuclear Power Plants ANSI N45.2.9-1974 Requirements for Collection, Storage, R.G. 1.88 (Rev. 2, 10/76) and Maintenance of Quality Assurance (See Appendix II Notes 19 through 21) Records for Nuclear Power Plants ANSI N45.2.10-1973 Quality Assurance Terms and R.G. 1.74 (Rev. O, 2/74) Definitions ANSI N45.2.12-1977 Requirements for Auditing of Quality R.G. 1.144 (Rev. 1, 9/80) Assurance Programs for Nuclear Power (See Appendix II Notes 22 and 23) Plants ANSI N45.2.23-1978 Qualification of Quality Assurance R.G. 1.146 (Rev. O, 8/80) Program Audit Personnel for Nuclear Power Plants Table I-1.1 provides a matrix which shows the sections of the Ebasco Nuclear Quality Assurance Program Manual that correspond to the requirements of 10 CFR 50, Appendix B and USNRC Regulatory Guide 1.28, Rev. O. The Ebasco Quality Assurance Program is comprised of: The Ebasco Nuclear Quality Assurance Program Manual, written corporate policies, procedures, departmental instructions, and other site-specific documents related to quality.

Table I-1.2 provides a matrix of the principal implementing procedures as they relate to 10 CFR 50, Appendix B criteria. Table I-1.3 is a listing of these procedures by title. The principal implementing procedures are not necessarily limited to those indicated in the matrix. Implementing procedures will be issued for South Texas Project use as the need for specific procedures arises due to changes in scope of Ebasco safety-related activities.

3222M

e sos.msrea-as 3 paos or 20 HOUSTON UGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SERVICES ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C INCORPORATED QA-I-1 QUALITY ASSURANCE PROGRAM The Ebasco Nuclear Quality Assurance Program Manual has been designed to meet the requirements of 10 CFR 50.34(7) for a quality assurance program description. It will be incorporated into applicable portions of Houston Lighting & Power Company safety analysis reports in whole or by reference as provided by 10 CFR 50.32.

The Ebasco Quality Program for the South Texas Project is in force at the Ebasco home office and Construction operations. The Ebasco home office is an organized unit where project-related support functions are performed.

Construction operations encompass those activities related to the construction of the nuclear power station. Ebasco's responsibility for implementing the Ebasco Quality Program shall begin at the commencement of activities affecting quality and shall end with the turnover of completed systems to the Client or his designee.

Definitions pertaining to the Ebasco Quality Program are listed in Appendix I of this Manual.

2.0 QUALITY ASSURANCE ORGANIZATION The Ebasco Quality Assurance organization is responsible for establishing new, and updating existing, quality assurance requirements. In addition, this organization is responsible to administer and enforce the implementation of the Ebasco Quality Assurance Manual.

3.0 QUALITY PROGRAM COMMITTEE 3.1 The Ebasco Quality Program Committee is responsible for and has authority to make and approve procedures for any changes to this Manual.

This committee is comprised of representatives of International Operations, Corporate and Consulting Engineering, Advanced Technology, Project Procurement, Project Management Services, Corporate Quality Programs, Envirosphere Company, Ebasco Plant Services Inc, and Ebasco Constructors Inc. These representatives are appointed by the Vice President of the respective organizational area.

The Vice President Corporate Quality Programs is designated by the President as the Chairman of the Quality Program Committee. A member of the Quality Assurance organization shall be designated by the Chairman as Quality Program Coordinator, who shall function as the Quality Program Committee's secretary and be a member of the Committee.

The Director Quality Assurance is designated by the Vice President Corporate Quality Programs as a permanent representative of Corporate Quality Programs on the Quality Program Committee.

3222M

sios ritsTP)445 4 20 PAGE Or HOUSTON LIGHTING AND POWER COMPANY S ECTION SOUTH TEXAS PROJECT EBA5CO SENE5 ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C _I_1 INCORPORATED QUALITY ASSURANCE PROGRAM The Committee shall be responsible for and shall have authority to make any changes to the policies and procedures of the Ebasco Quality Program. All changes or revisions to the Ebasco Nuclear Quality Assurance Program Manual shall be processed through the Quality Program Committee by the Quality Program Coordinator.

3.2 Ebasco Quality Program Procedures document the various significant activities of the Quality Program that are the direct responsibility of the Quality Program Committee or the Quality Program Coordinator. These procedures include but are not limited to the following:

3.2.1 Quality Program Procedure No. 4 entitled, QUALITY PROGRAM COORDINATOR - DESCRIPTION OF POSITION, DUTIES, RESPONSIBILITIES.

3.2.2 Quality Program Procedure No. 5 entitled, DEVIATING FROM THE CORPORATE EBASCO NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL. This provides for control of such deviations by requiring execution of an authorization form involving approval of specified authorities to assure, among other things, that safety and/or quality will not be sacrificed.

3.2.3 Quality Program Procedure No. 6 entitled, ASSIGNMENT, DISTRIBUTION AND CONTROL OF THE EBASCO NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL.

3.2.4 Quality Program Procedure No. 7 entitled, REVISIONS TO THE EBASCO NUCLEAR QUALITY ASSURANCE PROGRAM MANUAL.

4.0 GENERAL 4.1 Section QA-I-2 of this Manual describes the organizational structure, functional responsibilities, levels of authority, and lines of internal and external communication for management, direction, and execution of the Ebasco Quality Assurance Program. By the Statement of Authority at the front of this Manual, Ebasco's Fresident mandates the use of this Manual and its supporting documents which make up the Ebasco Quality Program for the South Texas Project.

4.2 It shall be the responsibility of each Ebasco department and the individual personnel of that department to adhere to the requirements of this Program. Section QA-III-1 of this Manual requires these departments to develop and control Ebasco instructions, procedures, and/or drawings which describe the manner in which activities affecting quality are to be 3222M

sios.utstem4s pace 5 or 20 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SERMES ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C INCORPORATED QA-I-l QUALITY ASSURANCE PROGRAM i

necc=plished. When documented evidence ic required for the coti= factory performance of these activities, checklists, forms, and/or other appropriate means shall provide this evidence. The documents which contain the procedures listed in Table I-1.3 and are used to implement the Ebasco QA Program are:

4.2.1 Quality Assurance Procedures Manual for South Texas Project 4.2.2 Standard Quality Assurance Procedures for the South Texas Project 4.2.3 Quality Program Procedures Manual 4.2.4 Company Procedures Manual - Nuclear 4.2.5 Quality Control Procedures Manual for South Texas Project 4.2.6 Site Quality Assurance Instructions Manual for South Texas Project 4.2.7 Construction Procedures Manual - Administrative Site Procedures for South Texas Project 4.2.8 Construction Procedures Manual - Construction Site Procedures for South Texas Project 4.2.9 Construction Procedures Manual - Construction Maintenance Instructions for South Texas Project 4.2.10 Standard Site Procedures for the South Texas Project The above-listed manuals may also contain departmental working procedures which do not describe activities affecting quality and therefore are not governed by the requirements of this Manual. Furthermore, certain implementing procedures may require changes in order to suit unique client requirements; such procedures for the South Texas Project will be included in a project manual of procedures and/or a site manual. In this case, the changed procedure shall be designated a Project Procedure.

These procedures will be subject to controls similar to those applicable to the original documents.

4.3 In addition to the requirements of Section QA-III-1 of this Manual and Paragraph 4.2 above, Section QA-III-8 of this Manual further assures control over quality-related activities by requiring that special processes shall be performed in accordance with written qualified 3222M

sios4usrea4s paar 6 or 20 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SENES ELECTRIC GENERATING STATION UNITS 1 & 2 INCORPORATED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-I-l QUALITY ASSURANCE PROGRAM procedures, and that they shall be performed only by qualified personnel. All qualifications shall be in accordance with applicable codes, standards, specifications, and other requirements as applicable.

The Ebasco Quality Program provides for the verification of quality requirements through written policies, procedures, and instructions for the performance of inspections and tests. These inspections and tests are performed on services provided by Ebasco. All inspections shall be performed by individucls other than those who performed the activity.

5.0 INDOCTRINATION AND TRAINING Section QA-I-3 of this Manual provides for the company-widi indoctrination and training of Ebasco personnel engaged in activities subject to the requirements of the Ebasco Quality Assurance Program. The objectives of the training program are to familiarize applicable Ebasco personnel with this Quality Assurance Program Manual and the implementing procedures identified in Table I-1.3. Overall responsibility for training as delineated in Section QA-I-3 rests with the Quality Assurance organization.

6.0 REVIEW OF QUALITY PROGRAM ADEQUACY 6.1 The adequacy of the Ebasco Quality Program is reviewed on a regular basis. The determination of program adequacy is based on audit results and trend analyses. Section QA-III-9 of this Manual provides for the performance and follow-up of audits by Site Quality Assurance and home office Quality Assurance Engineering and of management audits of the Materials Applications and Quality Assurance functions.

6.2 Audits performed by home office Quality Assurance Engineering and Site Quality Assurance are designed to evaluate the Quality Program effectiveness on a project basis. When corrective action is necessary, re-audits are scheduled to assure implementation of corrective action.

Section QA-III-9 of this Manual defines review activities and reports involved in the auditing function.

6.3 Information on audits performed by home office Quality Assurance Engineering and Site Quality Assurance shall be submitted to the Quality Assurance Engineering Supervisor of Auditing. He shall make an analysis of the available quality data with respect to quality trends and report the result at least semi-annually to the appropriate executive level of management for review and assessment in accordance with Quality Assurance Procedure QA-D.3. The Vice President Corporate Quality Programs shall be responsible for initiating the implementation of any changes or corrective action deemed necessary to improve the effectiveness of the Ebasco Quality Assurance Program.

3222M

i sios ausTew.es 7 20 l pace or s

HOUSTON LIGHTING AND POWER COMPANY SECTION A SOUTH TEXAS PROJECT EBASCO SENCE5 ELECTRIC GENERATING STATION UNITS 1 & 2 I. QUALITY ASSURANCE PROGRAtl DESCRIPTION - PART C l lNCORPORATED QA-I-1 j ,

. QUALITY ASSURANCE PROGRAM i

, TABLE I-1.1 MATRIX OF COMPLIANCE TO USNRC 10 CFR 50 APPENDIX B AND ANSI N45.2 10 CFR 50 ANSI N45.2 Ebasco Nuclear Quality Assurance Appendix B Criteria Paragraph Program Manual Section i

I I 3 QA-I-2 ,

II 2 QA-I-1, QA-I-3 f

III 4 Not Applicable to Ebasco STP

, Work Scope

. IV 5 Not Applicable to Ebasco STP Work Scope

! V 6 QA-III-1 VI 7 QA-III-2 VII 8 Not Applicable to Ebasco STP Work Scope i

! VIII 9 QA-III-10 i

j IX 10 QA-III-8 i

! X 11 QA-III-11

. XI 12 QA-III-12 XII 13 QA-III-13 XIII 14 QA-III-14 XIV 15 QA-III-15

)

l XV 16 QA-III-6

! XVI 17 QA-III-7 XVII 18 QA-I-6 l

XVIII 19 QA-III-9

3222M

~ , , _ _ . ~ . _ . _ . _ . . _ , , ,, _ - . _ _ _ _ - _ _ _ _ _ . . _ _ _ _ - , _ _ _ _ . _ , - . _ . _ ,_ _ _

m TAst.E t-1.2 y

MATRit OF ConPL1ANCE OF PRINCIPAL IMPLFMFJfTINC PROCEDURES TO 10 CFR 50 APPENota 8 h

N ret G Standerd Construction Proced4ree i to j Quality Site Quality Qualit y Quality Adelaistrative Construction Coestruction Quality Standard og  ;

Nuclear Control Assurance Assurance Amourance Site Site Malatenance Progree Site O n g Instructione Procederve Procedures Procedares Procedures lastructioes Frecedures Procedures 3 O

  • Crl- Procedures Procedure s (ASP-) (CSP-) (Ott a) (QPP-) (SSP-) oy t*rton (N-) (tJCP ,NDE ,QC-) (QAl-) (QA-) (SQAP-)

2 f4

-2

> N 1 -21 -1.1 -001 -4 <<

-24 -2.1.-2. 2,-6. 3 -017.-018 -C.3 -34 -4 through -55 $

It -7 w

-022 -023

-01 -1,-7.-10, -1 through -1,-3 2,- 4 9 V -23 -6.1 -6. 3 -002.-005 -C.1,-C.2

-017.-022 -12,-17 -94 (as applicable)

T1 -6.2 -002,-022 -C.1,-C.2 -6 C

-18,-32 -38,-39 -13.-30,f48, >

1111 -9.3 through .

-49 C

- 13. 3 (a s applicable),

ym

-17.2 y

-9. 3.- 10. 8, - 11.-8 7.-9 3, -9.-10,-16, C hj $O II

-002-1,-002-4,

-014.-015

-020 -94,-95,-97 - 17.- 18.-J 2,

- 29. - 30 ,- 31, h

6-s

~23 -

g ,2

-002-5,-005-1,

-005-2,-005-3, - 36,-46 N o m oC M 1,-007-1, m2%g

-009- t .-0003 f.o g Qx ,

-5,-10. 11, M o od > m--4 o 2 1 -2.1.-9. 3 -C.3.1 -04 through -13.3 -12.-14.-15 (as appiteente) 22 -23 $[N@>

HE , "

-24,-26.-27, g e,- ; 3

-28.-34 -34, 4o,-41, c: y;o o

-4 5,-4 9.- 5 2, m W a2n9 Jj c. H

-53.-57 n 8 a z 2a II -11.1.-11.2 -C. 3.1 -13 -5,-32 -2,-37.-38 2d >

Ill -12.1 -015 -23 -34,-94 [ j Itti -10.22 -13.1, 32 -3.-11.-12 -1 -13 $"

H

- 13.2,- 13.3 -82 -37.-63,-64

-45 n

-024 -13 -40 -7.-19.-33 IIT e i9 - n . i ,- 15. 2, - +4 7, -n - 3.- 4,- 8, g ,

-3>

e  ;;

- n. ) -O n "

O

-D.3 -02 -85,-16 -8 g EV1 -15.2 -16.1 -U07.-011

-82,-21.-16 CD 1111 - 8 7. 8.- 8 7. 2, -080,-019 -C.3.-C.4 -R

-87.3 O 9

g IVitt -24 -tu d ,-02 ) -D.4, -US

- 9. 5. 2,-C . )

H N

C3 H H H W H W W W W W

sios.zusm44s Pace 9 or 20 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SERHCES ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C INCORPORATED A-I-1 OffAT. TTY ASSURANCE PROGRAM TABLE I-1.3 PRINCIPAL IMPLEMENTING PROCEDURES Procedure No. Title NUCLEAR PROCEDURES (N)

N-21 Nuclear Quality Program Authorization and Implementation N-23 Reporting a Defect / Noncompliance to the NRC N-24 Ebasco Management Quality Assurance Audit Committee QUALITY CONTROL PROCEDURES (QCP, NDE, AND QC)

QCP-1.1 Quality Control Organization and Responsibilities QCP-2.1 Indoctrination, Training and Qualification of Quality Control Personnel to ANSI N45.2.6 Requirements QCP-2.2 Indoctrination, Training and Qualification of Quality Control Personnel to ASME Section III, Division 2 Requirements QCP-6.1 Preparation, Review and Approval of Quality Control Procedures QCP-6.2 Document Control QCP-6.3 Quality Control Review of Incoming Revisions /

Changes to Bechtel Specifications and Procedures lR13 QCP-9.3 Inspection of Post-Weld Heat Treatment lR13 QCP-10.1 Cadweld Inspection QCP-10.2 Preplacement Concrete Inspection QCP-10.3 Concrete Placement Inspection 3222M

6109-21(STPl445 20 PAGE 10 or HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EB 5 SER ES ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C

, , QA-I-1 QUALITY ASSURANCE PROGRAM Procedure No. Title QUALITY CONTROL PROCEDURES (Cont'd)

QCP-10.4 Concrete and Grout Post-Placement Inspection lR13 QCP-10.8 Protective Coatings Inspection QCP-10.9 General Inspection QCP-10.10 Soils Inspection QCP-10.11 Mechanical Equipment Installation Inspectiun lR13 QCP-10.13 Mechanical Instrumentation Installation Inspection QCP-10.14 System / Subsystem Walkdown Inspection QCP-10.15 Electrical Equipment Installation Inspection lR13 QCP-10.20 Electrical Penetration Installation Inspection QCP-10.21 HVAC Duct / Hanger Installation Inspection QCP-10.22 Receipt Inspection lR13 QCP-10.25 Inspection of Bending and Fabricating of Reinforcing Steel lR13 QCP-10.27 Modification / Removal Control Procedure QCP-10.28 Control of Inspection Stamps iR13 QCP-11.1 Hydrostatic and Pneumatic Pressure Test Inspection QCP-11.2 Duct and Housing Leak Test Inspection QCP-12.1 Control of Measuring and Test Equipment QCP-13.1 Storage and Maintenance Inspection / Verification QCP-13.2 Verification of Rigging and Handling Activities QCP-13.3 Housekeeping Inspections lR13 3222M

6 tC94 t($T P M43 PAGE 11 OF 20 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO 5ER I ES ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C

, QA-I-1 QUALITY ASSURANCE PROGRAM Procedure No. Titic QUALITY CONTROL PROCEDURES (Cont'd)

QCP-15.1 Identification and Control of Discrepancies and Nonconforming Conditions QCP-15.2 Stop Work Order QCP-15.3 Control and Processing of Transition Phase Deficiencies and Conditions QCP-16.1 Corrective Action QCP-17.1 Quality Assurance Records QCP-17.2 Preparation, Issuance, and Control of ASME Nameplates / Data Reports QCP-17.3 ASME On-Site Shop Fabrication NDE-002-1 Radiographic Standards for Welds and Components NDE-002-4 Radiographic Standards for Welder's Qualification , R13 (ASME IX) l NDE-002-5 Radiographic Standards for Welder's Qualification lR13 (AWS D.1) l NDE-005-1 Ult 1. sonic Examination (Thickness Measurement)

NDE-005-2 Ultrasonic Examination of Pipe Welds and Components NDE-005-3 Ultrasonic Examination of Structural Welds NDE-006-1 Liquid Penetrant Examination NDE-007-1 Magnetic Particle Examination Procedure NDE-009-1 Visual Examination of NF Welds QC-0003 Preparation, Control and Distribution of NDE Procedures for the South Texas Project 3222M

._ _ _ _ _ . _ m . _ _ . __ _ . . . . .

s tosa t t sT Pt44s 12

,,og or 20 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTi TEXAS PROJECT EBASCO SERWCES ELECTRIC GENERATING STATION UNITS 1 & 2 j

INCORPORATED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-I-l QUALITY ASSURANCE PROGRAM

, Procedure

, No. Title SITE QUALITY ASSURANCE INSTRUCTIONS (QAI)

QAI-001 Site QA Organization and Responsibilities I QAI-002 Preparation, Review, Distribution and Control of i Supplements to Quality Assurance Procedures QAI-004 Issuance and Processing of Nonconformance Reports QAI-005 Review and Approval of Quality Control and Construction Procedures j

QAI-006 Audit of Ebasco Site Organization by the Client, Bechtel, Ebasco llome Office, Code or Regulatory Agency j QAI-007 Reportable Deficiencies QAI-010 Site Quality Assurance Records QAI-011 Corrective Action and Stop Work Authority lR13 QAI-014 Quality Assurance Review of Radiographs l QAI-015 Procedure for the Operation and Calibration Verification of the Radiographic Densitometer QAI-017 QA Review of Incoming Revisions to Bechtel and Houston Lighting & Power QA Program Documents QAI-018 Quality Assurance Indoctrination and Training Program i

l QAI-019 Review, Processing and Turnover of Quality Records QAI-020 Training, Examination and Certification of NDE Personnel QAI-021 Allegation Investigation QAI-022 Quality Assurance Instructions l

l 3222M

v sios-msreus - 13

. paos or 20 HOU5 TON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT-ESASCO SEntCE5 ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAll DESCRIPTION - PART C' BNCORPORATED QA-I-l QUALITY ASSURANCE PROGRAM f Procedure <

No. Title SITE QUALITY ASSURANCE INSTRUCTIONS (Cont'd) 4 QAI-023 Planning of Site Quality Assurance Engineering Activitica, QAI-024 System Turnover QUALITY ASSURANCE PROCEDURES (QA)

QA-G.1 Preparation and Control of Quality Assurance Procedures QA-G.2 Control and Distribution of Project-Related Manuals' QA-G.3 Qualification of QA Audit Personnel QA-G.3.1 Qualification of Inspection, Examination and Testing Personnel QA-G.4 Quality Assurance Records QA-D 3 Determination and Analysis of Quality Trends QA-D.4 Resolution of External Audit Findings QA-D.S.2 Site Audit Procedure STANDARD QUALITY ASSURANCE PROCEDURES (SQAP)

SQAP-01 Generation and Control of Standard Quality Assurance Procedures SQAP-02 Deficiency Reporting SQAP-03 Project Audits SQAP-04 Project Surve111ances i

1 3222M ,

1 .

s 1094 HST Pl445 14 ,, 20 PAGE HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SENCE5 E LECTRIC GENERATING STATION UNITS 1 & 2 INCORPORATED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-I-1 QUALITY ASSURANCE PROGRAM Procedure No. Title ADMINISTRATIVE SITE PROCEDURES (ASP)

ASP-1 Preparation of Site Procedures ASP-2 Organization and Responsibility lR13 ASP-4 Heavy Handling and Rigging lR13 ASP-6 Document Control ASP-7 Field Change Notice Procedure ASP-8 Preparation and Transmittal of Quality Assurance and Non-Safety Related Records lR13 ASP-10 Configuration Control lR13 ASP-12 Development of Construction Field Sketches lR13 ASP-13 Start-up Work Request Procedure lR13 ASP-15 Stop Work Procedure ASP-16 Corrective Action ASP-17 Configuration Control Package (CCP) -

Design Change Package (DCP)

ASP-18 Modification of Equipment / Component Tags ASP-20 ASME Section XI Repair Program lR13 ASP-22 Field Fabrication Modifications ASP-23 Measuring and Test Equipment Control ASP-32 Maintenance of Construction Equipment lR13 ASP-34 Indoctrination and Training ASP-82 Fire Prevention and Fire Protection 3222M

.s ,

sios.aiasted.e5 '

. pace 15 or 20 ,

HOU5 TON LeGHTING AND POWER COMPANY

' $ECTION SOUTH TEXAS PROJECT EBASCO SENCES ELECTRIG GENERA 7'NG STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C encomponArco QA_I_1 QUALITY ASSURAt;CE PROGRAM Procedure No. Title

,' c j CONSTRUCTION SITE PROCEDURES.(CSP) [

CSP-1 Excavation and Backfill CSP-2 Installation of Permanent Electrical and Mechanical Plant Equipment CSP-3 control of Lifting Apparatus CSP-4 Concrete Placement /

CSP-5 tuct and Housing Leak Test CSP-6 ~ Installation of HVAC Duct Hangers and Equipment fHangers lR13 CSP-9 Inscallation of Duct and Duct Accessorie:

lR13 CSP-11 . Storing, Installation, Cadwelding, Fabrication and

/ '/

. Modification of Rebar CSP-12[ General Instructions for Housekeeping Dubing

< Construction

. . - lR13 CSP-17 Hydrostatic and Pneumatic Testing CSP-18 Soil Test Fill Procedure

, . lR13 CSP-20 Construction Survey Activities CSP-21 Field Preparation and Coating of Surfaces <

Outside the Reactor Containment Building CSP-22 Valve / Pump Work CSP-24 Reactor Coolant Pump Volute Final Setting lR13 CSP-26 Reactor Vessel Final Setting CSP-27 ,y Steam Cenerator Final Setting

,n

>w 3222M j .

e sosausre>44s paos 16 or 20 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT E3 SC $E CES ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C

, QA-I-l QUALITY ASSURANCE PROGRAM Procedure No. Title CONSTRUCTION SITE PROCEDURES (Cont'd)

CSP-29 Reactor Vessel Internals Handling and Assembly CSP-30 Field Preparation and Coating of Surfaces Inside the Reactor Containment Building lR13 CSP-32 Insulation Resistance Testing CSP-33 High-Potential Testing CSP-34 Control and Verification of Survey Equipment CSP-35 Installation of Post-Tensioning Trumplate Assemblies and Sheathing CSP-36 Data Collection to Support Geotechnical Monitoring Program CSP-37 Crane and Hoist Load Testing CSP-38 Equipment or Component Interchange CSP-39 ASME Code Data Plate Modifications CSP-40 EE-580 Electrical Installations lR13 CSP-44 Installation of Electrical Penetration Assemblies CSP-47 Instrumentation Installation lR13 CSP-55 Field Fabrication of Reinforcing Steel CSP-56 Application and Repair of Waterproofing of Buildings lR13 CSP-63 Rigging for Setting the Reactor Head CSP-64 Rigging for Setting Unit II Reactor Internals 3222M

siosauste>44s eacc 17 or - 20 HOUSTON LIGHTING AND POWER COMPANY

$ECTION SOUTH TEXAS PROJECT ESA5CO SEWCE5 ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C i~coneonateo QA_y_1 QUALITY ASSURANCE PROGRAM Procedure No. Title CONSTRUCTION SITE PROCEDURES (Cont'd)

CSP-65 Reactor Coolant Pumps Rigging and Installation lR13 CSP-87 Welding Procedure Specification Qualification lR13 CSP-93 control of Weld Filler Material For Non-Permanent Plant Maintenance CSP-94 Maintenance, Calibration and Repair Program for Dimetrics Automatic Welding Equipment CSP-95 General Welding Requirements for HVAC lR13 CSP-97 Cold Bending CONSTRUCTION MAINTENANCE INSTRUCTIONS (CMI)

CMI-1 Care and Maintenance of Permanent Plant Items QUALITY PROGRAM PROCEDURES (QPP)

QPP-4 Quality Program Coordinator - Description of Position, Duties, Responsibilities QPP-5 Deviating from the Corporate Ebasco Nuclear Quality Assurance Program Manual QPP-6 Assignment, Distribution and Control of the Ebasco Nuclear Quality Assurance Program Manual QPP-7 Revisions to the Ebasco Nuclear Quality Assurance Program Manual 3222M

sios msTe>44s enor 18 or 20 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT E AscO Rv1cES ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C

,p ,, QA-I-1 QUALITY ASSURANCE PROGRAM Procedure No. Title STANDARD SITE PROCEDURES (SSP)

SSP-1 Preparation, Issue, and Control of Standard Site Procedures SSP-2 Project Generic Preasure Test Procedure SSP-3 Construction Turnover and Release for Test SSP-4 Jurisdictional Release 1 l

SSP-5 Coring, Cutting or Drilling Concrete l 1

SSP-7 Work Package Statusing l 1

SSP-8 Nonconformance Reporting l 1

SSP-9 Pipe Support Installation l I

SSP-10 Installation and Field Fabrication of Piping i I

SSP-11 Fabrication, Erection and Bolt up of Structural l and Miscellaneous Steel l l

SSP-12 On-Site Shop Fabrication lR13 i

SSP-13 Material Control l I

SSP-14 Stud Anchor Installation and Inspection l l

SSP-15 Non-Shrink Grout and Mortars l I

SSP-16 General Structural Welding Requirements l l

SSP-17 General ANSI B31.1 Welding Requirements l SSP-18 General ASME III Welding Requirements l

SSP-19 STP QA/QC Responsibilities for System and Area l Turnovers l 3222M

t s ics-msr ei4.as paos 19 or 20 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT E A Co 5E CE5 ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C p QA-I-l QUALITY ASSURANCE PROGRAM Procedure No. Title STANDARD SITE PROCEDURES (Cont'd)

SSP-20 Control of ASME Code Nameplates and Permanent i Plant Tags l l

SSP-21 Preparation and Certification of ASME Code N-5 l Data Reports l l

SSP-22 Piping System Cleanliness l l

SSP-23 Release for Insulation l l

SSP-24 Disassenby/ Reassembly of Safety and Non-Safety i Related Valves l l

SSP-26 Termination of Electrical Cable l l

SSP-27 Installation of Electrical Cable l I

SSP-28 Installation and Inspection of Electrical Raceway I and Supports l lR13 SSP-29 Post-Weld Heat Treatment l l

SSP-30 Weld Filler Material Control l l

SSP-31 Welder Qualifications l l

SSP-32 Impact Review of Bechtel Documents l l

SSP-33 Construction Safety Tagging l l

SSP-34 Technical Requirements and Walkdown Procedure for l As-Pullding of Piping Systems i I

SSP-36 Construction Work Package - Work Package Control l l

SSP-37 Configuration Control Package l l

SSP-38 Installation and Inspection of HVAC Duct / Supports I and Accessories l 3222M

sios-a usreis.es pace 20 o, 20 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO $EWICES ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-I-1 INCORPORATED QUALITY ASSURANCE PROGRAM Procedure No. Title STANDARD SITE PROCEDURES (Cont'd)

SSP-40 Maxi-Bolt Installation and Inspection l l

SSP-41 Rock Bolt Installation and Inspection l l

SSP-45 Electrical Separation l l

SSP-46 Field Material Requisition Preparation and l Approval l I

SSP-48 Equipment or Component Interchange l l

SSP-49 Field Change Requests lR13 l

SSP-52 Installation, Assembly and Disassembly of l Permanent Plant Mechanical Equipment l l

SSP-53 Instrumentation Installation l l

SSP-55 Indoctrination and Training of Site Personnel l l

SSP-56 Project Record Review Activities l l

SSP-57 Installation and Inspection of Electrical l Equipment l 3222M

siosaustra4s race 1 or 13 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SENE5 ELECTRIC GENERATING STATION UNITS I & 2 lNCORPORATED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C

-I-2 ORGANIZATION AND RESPONSIBILITIES 1.0 SCOPE This Section of the Manual describes the organizational structure, functional responsibilities, levels of authority, and lines of internal and external communication for management, direction, and execution of the Ebasco Quality Program. It is recognized that quality assurance is an interdisciplinary function and not the sole domain of a single quality assurance group; for that reason, this Section of the Manual includes organizational and functional descriptions of several departments in addition to that organization whose sole function is quality assurance.

2.0 GENERAL 2.1 The Ebasco operations organization consists of five independent quality-related principal divisions headed respectively by Group Vice Presidents of Engineering, Construction and Plant Services, Advanced Technology and Special Projects, and International Operations; and the Vice President of Corporate Quality Programs. Each of these officers of the company report to the Ebasco President and Chief Operating Officer.

Quality-related subdivisions or subsidiary companies are headed by officers reporting to Group Vice Presidents. Reporting to the Engineering Group Vice President are the Senior Vice President of Corporate and Consulting Engineering; the Vice Presidents of Project Management Services, Project Procurement, and Project Engineering and Design; and the President of Envirosphere Company. Reporting to the Construction and Plant Services Group Vice President are the Presidents of Ebasco Constructors Inc, and Ebasco Plant Services Inc. Reporting to the Advanced Technology and Special Projects Group Vice President is the Vice President of Advanced Technology.

2.2 Representatives of the Ebasco Group Vice President International Operations; of the Ebasco Senior Vice President of Corporate and Consulting Engineering; of the Ebasco Vice Presidents of Advanced Technology, Project Procurement, Project Management Services, and Corporate Quality Programs; and of the Presidents of Ebasco subsidiaries Envirosphere Company, Ebasco Plant Services Inc, and Ebasco Constructors Inc, comprise the Quality Program Committee which is responsible for Ebasco Quality Assurance policy. This Committee is shown diagrammatically in Figure I-2.1 at the end of this Section.

2.3 The Ebasco organizational units most directly involved in the implementation of the Quality Assurance program for fabrication and installation are Corporate Quality Programs, and Ebasco Constructors Inc.

The organizational structures of these are shown in Figures I-2.2 and I-2.4 at the end of this Section.

3222M

sios.austpa as pace 2 or 13 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SERVICE 5 ELECTRIC GENERATING STATION UNITS 1 & 2 INCORPORATED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-I-2 ORGANIZATION AND RESPONSIBILITIES The responsibilities of the individual Ebasco organizational units for quality assurance requirements applied to nuclear power stations are described herein.

3.0 CORPORATE QUALITY PROGRAMS Primary responsibility for quality assurance rests with the Vice President Corporate Quality Programs who reports directly to the President.

Qualification requirements for the position of Vice President Corporate Quality Programs are: Bachelor of Science Degree in Engineering; 10 to 15 years of experience in quality-related work or equivalent experience in tne engineering or construction of a nuclear power plant, including at least 10 years experience in responsible managerial project positions; and a thorough knowledge of the Ebasco Quality Assurance Program. The Corporate Quality Programs unit is comprised of the following organizations, each of which contributes directly to the implementation of the Quality Program (see Figure I-2.2):

a) Quality Assurance b) Materials Applications c) Vendor Quality Assurance d) Quality Assurance Consulting Engineer e) Materials Engineering Laboratory 3.1 Quality Assurance is administered by the Director Quality Assurance who reports to the Vice President Corporate Quality Programs.

Qualification requirements for the position of Director Quality Assurance are: Bachelor of Science Degree in Engineering; 10-15 years of experience in quality-related work or equivalent experience in the engineering or construction of a nuclear power plant, including at least 5 years experience in responsible managerial project positions; and a thorough knowledge of the Ebasco Quality Assurance Program. Quality 8.csurance is responsible to plan implementation of, evaluate, monitor, and enforce the Ebasco Quality Program. This responsibility is carried out by five functional subdivisions:

a) Quality Assurance Projects b) Quality Assurance Site Services c) Quality Assurance Engineering 3222M

s to s-211STPM 45 pact 3 or 13 HOUSTON LIGHT'NG AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EB ASCO $EWCES ELECTRIC GENERATING STATION UNITS 1 & 2 QUAUTY ASSURANCE PROGRAM DESCRIPTION - PART C A-I-2 INCORPORATED ORGANIZATION AND RESPONSIBILITIES d) Inservice Inspection / Nondestructive Examination Services e) Quality Assurance Consulting Managers in charge of the subdivisions report directly to the Director Quality Assurance. Engineers and Specialists are then assigned to specific projects from these subdivisions. The Quality Assurance Organization is shown in Figures I-2.6 and I-2.7 at the end of this Section. The organization and responsibilities of the four Quality Assurance subdivisions associated with the South Texas Project are described in the following paragraphs.

3.1.1 Quality Assurance Site Services - The Quality Assurance Site Services subdivision is headed by the Manager Quality Assurance Site Services who is responsible for all site-related Quality Assurance /

Quality Control activities, including implementation of the site phase for all Ebasco project quality programs. A Manager Site Quality Assurance, who reports to the Manager Quality Assurance Site Services, and a Quality Program Site Manager, who reports to the Director Quality Assurance, are responsible for Quality Program implementation for the South Texas Project in accordance with the following:

3.1.1.1 Site Quality Assurance - The Manager Site Quality Assurance, who reports to the Manager Quality Assurance Site Services in New York, is responsible for providing technical assistance and guidance to subordinate Quality Assurance Site Supervisors and staff, and for distribution and control of quality assurance manuals, as well as changes thereto, for the South Texas Project. (See Figures I-2.2 and I-2.6.) The Manager Site Quality Assurance has delegated authority to the Quality Program Site Manager on the preparation, review, approval, and distribution control of Site Quality Control Procedures and Site Quality Assurance Instructions; and to approve the Standard Quality Assurance Procedures, and the Standard Site Procedures when applicable, developed by the Client or his designee.

3.1.1.2 Site Quality Program - A Quality Program Site Manager is assigned to the construction site on a resident basis for the purpose of overall planning, direction, and implementation of the Ebasco Nuclear Quality Assurance Program Manual. The Quality Program Site Manager, who reports to the Director Quality Assurance, is subordinate to no individual on site and Fas the independent authority to identify site quality-related problems, to initiate or 3222M

sioseusTP)445 PAGE k OF 13 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SEWICES ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCR!PTION - PART C (NCORPOAATED QA-I-2 ORGANIZATION AND RESPONSIBILITIES recommend solutions, to control existing nonconformances, to verify implementation of approved dispositions, to direct efforts to obtain ASME Certificates of Authorization for Ebasco as may be required for the South Texas Project, to represent the Ebasco Quality Assurance organization with regard to South Texas Project activities, such as Client or his designee and/or Ebasco meetings, Client or his designee audits, management audits, and, when necessary, to stop work. He is responsible to assure that all personnel working for him are qualified for their respective positions and properly trained. The Director Quality Assurance has delegated authority to the Quality Program Site Manager on the preparation, review, approval, and distribution control of project-related supplements to the applicable Quality Assurance Procedures. The Site Quality Program function is divided into three groups: Quality Assurance, Quality Control, and Quality Records, each reporting through a respective supervisor to the Quality Program Site Manager.

(See Figure I-2.6.)

3.1.1.2.1 Site Quality Assurance - A Quality Assurance Site Supervisor and staff of engineers and representatives are assigned the following functions:

a) Review and audit safety-related site construction and engineering activities and records on a continuing basis.

b) Perform audits and surveillances of construction forces for adherence to prescribed approved procedures.

c) Review and advise on quality control procedures, construction procedures, and nondestructive examination procedures for compliance with this Manual and code and regulatory requirements. When necessary, the Quality Assurance Site Supervisor may request the Manager Site Quality Assurance to assist in the review of quality control procedures.

d) Generate records of all reviews and audits performed.

3222M

siosatisrei44s paos 5 or 13 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SERWCES ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C

. meonponarco QA-I-2 ORGANIZATION AND RESPONSIBILITIES e) Review all radiographic film for site-related nondestructive examination.

f) Audit records and documentation prior to turnover to the Client.

g) Develop and implement Quality Assurance Instructions and review the Standard Quality Assurance Procedures prior to the Quality Program Site Manager's approval and their implementation. When applicable, review the Standard Site Procedures prior to the Quality Program Site Manager's approval and their implementation.

4 h) Perform on-site distribution of those Quality Assurance procedures which are issued and controlled by the Manager Site Quality Assurance or his designee, and distribute the Standard Quality Assurance Procedures.

1) The Quality Assurance Site Supervisor has stop work authority.

3.1.1.2.2 Site Quality Control - A Quality Control Site Supervisor and staff of engineers and inspectors are assigned the following functions consistent with the scope of work assigned to Ebasco:

a) Planning and performance of inspection activities during the construction phase.

b) Identifying and initiating correction of nonconforming conditions to

. requirements indicated by drawings, specifications, codes, or procedures, and performance of reinspection to verify corrective action taken.

3222M

siosaustra4s pace 6 Or 13 HOUSTON LIGHTING AND POWER COMPANY $ECTION SOUTH TEXAS PROJECT EBASCO SENES ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-1-2 INCORPORATED ORGANIZATION AND RESPONSIBILITIES c) Establishing and enforcing quality control documentation and inspection requirements based upon specifications, codes, standards, and drawings as established by the Client or his designee.

d) Performance or monitoring of site NDE, soils, and concrete testing activities.

e) Assisting in organizing and administering training seminars as required to assure proper level of training, and engaging in the certification of Quality Control personnel to the required level of qualification.

f) Identification and control of the quality status of items.

g) Development and implementation of applicable Quality Control Procedures, implementation of applicable Standard Site Procedures, and generation of inspection reports covering mandatory inspection activities at the construction site.

h) The Quality Control Site Supervisor has stop work authority.

The Site Quality Control Group will only be responsible for first-level Quality Control activities for safety-related items and services being performed by Ebasco's forces.

3.1.1.2.3 Site Quality Records - A Quality Records Supervisor and staff of specialists are assigned the following functions:

a) Develop, establish, and implement a system for the collection, storage, and maintenance of quality assurance records at the project construction site.

3222M

stosaustr>44s paos 7 or 13 HOU$ TON UGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBA5Co SERWCES ELECTRIC GENERATING STATION UNITS 1 & 2 INCORPORATEO QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C A-I-2 ORGANIZATION AND RESPONSIBILITIES b) Responsible for review for completeness, control, storage, preservation, and safekeeping of Ebasco site generated quality assurance records until turnover to the Client or his designee.

c) Establishment and implementation of a records indexing system to permit proper traceability and retrieval.

d) Establishment of a procedure for access to the records storage area, and removal and retrieval of quality records.

l 3.1.1.2.4 At the site level, intermediate positions for all of the above categories may be required but , R13 functional reporting will remain as depicted in l Figure I-2.6. l 3.1.2 Quality Assurance Engineering - The Quality Assurance Engineering subdivision is headed by the Manager Quality Assurance Engineering. He is responsible for the following activities which are under the direction of supervisors reporting to him and are performed in accordance with Quality Assurance procedures:

a) Administration of training and qualification programs for Quality Assurance audit and inspection personnel.

b) Conducting Quality Assurance education, both internal and external to' Quality Assurance. Quality Assurance Education Specialists from Quality Assurance Engineering are assigned to the construction site. These specialists report administratively and functionally to the Quality Program Site Manager, but receive technical direction from Quality Assurance Engineering at the Ebasco home office.

c) Interdepartmental auditing of all individuals or groups responsible for activities covered by the Quality Program, d) Development and implementation of Corporate Trend Analysis programs.

3222M

61094 HST PM45 O 13 PAGE OF HOUSTON UGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SENCEs ELECTRIC GENERATING STATION UNITS I & 2 INCORPORATED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-I-2 ORGANIZATION AND RESPONSIBILITIES 3.1.2.1 Radiation Safety - Ebasco's Corporate Radiation Safety Officer reports to the Director Quality Assurance through the Manager Quality Assurance Engineering. He is responsible for auditing and enforcing the Ebasco Procedures for radiation safety.

3.1.3 Inservice Inspection / Nondestructive Examination Services -

The Inservice Inspection / Nondestructive Examination Services subdivision is headed by the Manager of Inservice Inspection /

Nondestructive Examination. He is responsible for the following activities which are under the direction of supervisors reporting to him:

a) Establishment and/or int <rpretation of NDE requirements and acceptance criteria '.or fabricated and erected equipment as required.

b) Reviewing and commenting on NDE procedures and radiographic films r abmitted by site construction forces and/or clients.

c) Advising site construction forces as to proper NDE procedures, applications, techniques, equipment, and qualifications.

d) Qualification and certification of Ebasco NDE personnel.

3.1.4 Quality Assurance Consulting - The Quality Assurance Consulting subdivision is headed by the Senior Consulting Quality Assurance Engineer, who is responsible for the following activities:

a) Development of Quality Assurance standards and procedures.

b) Interpretation of quality assurance requirements as specified in national codes, standards, and regulatory documents, and incorporating these requirements in company documents.

3.2 Materials Applications, under the supervision of the Chief Materials Engineer, includes two subdivisions: Materials Engineering and Welding Engineering. A Project Materials Engineer and Project Welding Engineer are assigned to the South Texas Project. These positions may be assigned to the same individual if properly qualified. A Site Welding Superintendent, who reports to the Chief Materials Engineer in New York, is assigned to the construction site and is responsible for the direction, supervision, and administration of a site welding operations 3222M

sios4uston4s pace 9 or 13 HOUSTON UGHTING AND POWER COMPANY SECTION SOUTi TEXAS PROJECT EBASCO SERVICES ELECTRIC GENERATING STATION UNITS 1 & 2 QUAUTY ASSURANCE PROGRAM DESCRIPTION - PART C mcom pon A r co 9A-I-2 ORGANIZATION AND RESPONSIBILITIES staff. Quality-related activities of Materials Applications personnel include the following:

a) Develop material and welding specifications.

b) Develop and qualify welding procedures and fabrication techniques for use by Ebasco site construction forces.

c) Prepare site welding operations implementation procedures for

Ebasco site construction forces.

d) Advise Ebasco Construction management as to the development and application of advanced welding techniques which would enhance quality.

e) Prepare Process Data Checklists which provide comprehensive requirements for welding process and procedure selection, postweld thermal treatment, and inspection at the construction site.

f) Review specifications and drawings provided by the Client or his designee for compliance with applicable codes and regulatory requirements for proper selection of materials, weld procedures, and joint details.

g) Supervise the welder performance testing program at the construction site to assure that all code and regulatory requirements have been met.

h) Provide technical assistance as required to resolve problems at the construction site in the areas of welding, materials, heat treatment, and other related areas.

1) Provide technical assistance concerning material properties under service conditions involving stress, radiation, temperature, corrosive media, etc, to determine capability of specific materials to perform in such environments.

j) Review, monitor, and provide recommendations for upgrading of Ebasco welder training programs and welder assignment practices, k) Prepare and monitor site filler material control procedures.

1) Supervise and direct testing and applied research programs required to resolve site construction materials and welding problems.

3222M r,, .- ,, ,_- , - - _ , _ , . _ . . _ _ , _ _ ._ _ _ _

______m_ _ _ - . __y

- m--- - , , - - - - .

siosausrea4s 10 pace or 13 HOUSTON L!GHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO $ERWCES ELECTRIC GENERATING STATION UNITS 1 & 2 LNCORPORATED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-I-2 ORGANIZATION AND RESPONSIBILITIES 3.3 The Quality Assurance Consulting Engineer reports to the Vice President Corporate Quality Programs. He is responsible for conducting audits of the Ebasco Quality Assurance function to determine and report its compliance with the Ebasco Quality Program requirements.

3.4 The Materials Engineering Laboratory performs field nondestructive examination services. The Materials Engineering Laboratory.is administered by a Manager who reports to the Vice President Corporate Quality Programs. The NDE Laboratory Supervisor reports administrative 1y to the Materials Engineering Laboratory Manager or his designee and is responsible for the technical direction of nondestructive examination activities performed by the Site NDE Laboratory at the construction site. The NDE Laboratory Supervisor reports functionally to the Quality Control Site Supervisor or his designee.

4.0 CONSTRUCTION AND PLANT SERVICES GROUP Primary responsibility for construction and plant services rests with the Group Vice President Construction and Plant Services. The Construction organization has the prime responsibility for the performance of quality construction on the South Texas Project and is described in the following paragraphs.

4.1 The President Ebasco Constructors Inc reports to the Group Vice l President Construction and Plant Services and is responsible for

executive management of all construction activities and services.

I (See Figure I-2.4.)

4.1.1 The Ebasco Construction Manager reports to the President Ebasco Constructors Inc and is responsible for overall supervision and coordination of all construction activities and services.

Additionally, the Ebasco Construction Manager shall approve the Standard Site Procedures. The Ebasco Construction Manager has stop l work authority.

4.1.2 The Manager of Construction Quality reports to the President Ebasco Constructors Inc, and is responsible for development of Construction procedures, keeping abreast of NRC and code lR13 requirements, and periodic reporting to Construction management of current Quality Program status and any required corrective actions.

4.1.3 The Site Manager reports to the Ebasco Construction Manager.

The Site Manager has the responsibility for the direction and i coordination of all on-site activities related to construction. The Site Manager has stop work authority.

3222M

, siosa ustra45 ,,oe 11 or 13 HOUSTON LIGHTING AND POWER COMPANY S E CTION SOUTH TEXAS PROJECT l EBASCO SERVICES ELECTRIC GENERATING STATION UNITS 1 & 2 INCORPORATED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-I-2 i ORGANIZATION AND RESPONSIBILITIES I 4.1.4 The Discipline Managers report to the Site Manager. Each l Discipline Manager is individually responsible for the Ebasco l 1

construction operations and activities within his assigned l l discipline. He will manage all phases of construction within I disciplines assigned, including field engineering and cost control, lR13 to assure that the work accomplished is completed within the budget l l' and in accordance with the contract and all applicable installation l plans, procedures, specifications, drawings, and the Quality l l Assurance Program. The Discipline Managers have stop work authority. l  ;

4.1.5 The Labor Relations Representative reports to the Site Manager.

The Labor Relations Representative is conversant with the general provisions of the Project Stabilization Agreement. The Labor Relations Representative participates in settlement of local labor disputes, assists in preparation for arbitration proceedings related to operations at the site, and advises the Site Manager on lR13 local labor relation matters.

i l 4.1.6 The Senior Resident Engineer reports to the Site Manager and is responsible for administering, coordinating, and supervising all Site Construction Engineering and technical activities, for

interpretation of design documents and specifications, for I
furnishing assistance to Ebasco site personnel as required, and for lR13-t establishing and providing training and development programs for l construction. The Senior Resident Engineer has stop work authority. l 4.1.7 The Construction Services Superintendent reports to the Site l Manager and will be responsible for providing and establishing lR13 ,

adequate and efficient accounting, timekeeping, and computer support I programs as required to support the construction effort. l 4.1.8 The Manager of Safety'/ Security reports to the Site Manager. l The Manager of Safety / Security is responsible for establishing and I enforcing the site security, safety, and industrial hygiene programs lR13 in accordance with established policy and all federal and state l l regulations, as well as any other criteria necessary to ensure the safety of site personnel.

I

. 3222M.

y -

w r, w .-w---. y.ew, w ---r--

sios-msm4.es ,y, 12 ,, 13 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SEWICES ELECTRIC GENERATING STATION UNITS 1 & 2 INCORPOR ATED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-I-2 ORGANIZATION AND RESPONSIBILITIES 4.1.9 The Permanent Plant Maintenance (PPM) Superintendent reports to the Site Manager and is responsible for administering the IR13 .

maintenance program for permanent plant equipment upon receipt from the warehouse until turnover to the Client.

4.1.10 The Start-up Support Superintendent interfaces with the l Client's Start-up Manager and reports to the Site Manager for project I coordination. He is responsible for systems testing, including IR13 ensuring construction progress in support of systems testing, and I conducting construction test efforts. l 4.1.11 The Site Fabrication Shop Coordinator reports directly to the l Mechanical Discipline Manager and is responsible for coordinating l work to be performed in the fabrication shop, ensuring housekeeping lR13 is maintained in the fabrication shop, and establishing laydown l areas around the fabrication shop in support of the construction l effort. l 4.1.12 The Systems Completion Manager reports to the Site Manager I and is responsible for the coordination of systems turnover to the IR13 Client. l 4.1.13 The Manager of Materials reports to the Site Manager and is I responsible for implementing a program for control of material as it l

< is issued from the Controlled Material Storage Area and transported IR13 to and staged in the field. This responsibility includes expediting i of material requirements. l 4.1.14 The Shift Superintendents (2nd or 3rd shift) report to the l Site Manager and are responsible for directing, coordinating, and l providing general supervision of all construction activities lR13 associated with their shift. The Shift Superintendents have stop l work authority. l I

5.0 INTERFACE Interface, as applicable, is so illustrated by Figure I-2.9 at the end of this Section and is explained by appropriate and applicable South Texas Project documents.

1 3222M

sion-msreus pace 13 or 13 HOUSTON LIGHTING AND POWER COMPANY SE CTION SOUTH TEXAS PROJECT EBASCO SERVICES ELECTRIC GENERATING STATION UNITS I & 2 l

QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C INCORPORATEQ QA-I-2 ORGANIZATION AND RESPONSIBILITIES 6.0 ORGANIZATION CHARTS The following figures apply to this Section:

Figure No. Title Revision I-2.1 Operations Organization Showing Quality Program Committee Representation 6-STP I-2.2 Corporate Quality Programs Organization 7-STP I-2.3 Deleted -

1 I-2.4 Organization for Construction 6-STP lR13 I-2.5 Deleted -

I-2.6 Quality Assurance Organization 6-STP I-2.7 Qur.lity Assurance Engineering Quality Assurance Specialists 6-STP I-2.8 Deleted -

I-2.9 Interface Between Houston Lighting &

Power Company, Bechtel Energy Corporation, and Ebasco Services Incorporated 4-STP lR13

)

i 4

I i

f 3222M i

Ebasco Services incorporated OPERATIONS ORGANIZATION SHOWING QUALITY PROGRAM COMMITTEE REPRESENTATION PREstDENT I

I I I I GROUP GROUP GROUP GROUP VICE PRE SIDENT VICE PREstDENT VICE PRES 10ENT ADVANCED VICE PRE $1 DENT CONSTRUCTION INTERNAilONAL ENGINE E RING & OPE R ATIONS TECH,NOLOGY

& PECIAL PLANT SERVICES PROKCTS I I I i 1 1 I l PEsTEI.1 mEsloE,.1 v'cgg$g"' yICE ,REslot,,, m,i,,s;;;r "'*10"'

ER PLANT vg, Pat

, s,y,Nr V. ,,,E,,,,,,,

CORPORATE ENVIROSPHE RE MANAGEMENT NOJE CT o at,yy ADVANCED CostST RUCTOR S

& CONSULTING COMPANY mOCUREMENT SE RVICE $ q TECH 880 LOGY SERVICES IPfC.

ENGINEERING INC.

OP OP OP OP OP OP & & &

COMM COMM COMM COMM COMM COMM COMM COMM COMM REP REP REP REP REP REP REP REP REP MH

?8w

$7 o ,~

W I

Ebasco Services incorporated CORPORATE QUALITY PROGRAMS ORGANIZATION PRESIDENT I

VICE PRESIDENT CORPORATE QUALITY PROGR AMS I

I I I l CHIE F DIRECTOR CHIEF VENDOR MATERIALS OUALITY OUALITY ASSURANCE TER ALS ENGINEER ASSURANCE R E PR ESE NT ATIVE ENGINEERING LABORATORY I I

"' T 'I MANAGER MANAGER VENDOR NDE LABORATORY

=

g,E RI qgER OUALITY ASSUR ANCE QUALITY ASSURANCE - QUALITY ASSURANCE SUPE RVISOR PROJECTS ENGINEERING $UPE R VISORS AND STAFF I I I PROJECT OUALITY ASSURANCE

- WE LDING OUALITY ASSURANCE ENGINEERING VENDOR OUALITY ASSUR ANCE ENGINEERS SUPE R VISOR T. SUPERVISORS & QUALITY ASSURANCE CONSULTING =

ENGINEERS & STAFFS R E PR ESE NT ATIVE S ENGINE E R SPECIALISTS MANAGER #

_ OUALITY ASSUR ANCE -

imDE SERVICES SER ICES I l MANAGER SITE ISimDE QUAllTY ASSURANCE. SUPE R VISOR $

SITE SUPERVISORS &

& STAFFS STAFFS

. ST MA A ER SENIOR CONSULTING OUALITY ASSURANCE -

SITE SUPERVISOR $

AND STAF FS ENGINEER & STAFF

. NOT APPLICABLE TO THE STP OUALITY PROGRAMS ORGANIZATION

  • REPORTS FUNCTIONALLY TO THE QUALITY CONTROL SITE SUPERVISOR FIGURE I-2.2 REV. 7-STP

Ebasco Services incorporaked ORGANIZATION FOR CONSTRUCTION ADAPTED r0R HOUSTON LIGHTING & POWER C0eAPANY SOUTHTEXAS PROJECT ELECTRIC GENERATING STATION UNITS I & 2 GROUP VICE PRESIDENT CONSTRUCitON ab PLANT SE RVICES I

PRE SIDE NT E eASCO CONSTRUCTORS INC DtRf CTOR MANAGE R OF CHaf F OU AL t T V CONST RHC TION ASSUR ANCE MA TE RIALS Ot I AL i1 Y f NGINE ER NtWYORK gggyggg

. e w re eeeeee e,_ mm_

Sif f $33 g e

CONS T RUCTIO86 MANAGfR 8 CLIE NT SIT E ST AR T UP MAN AGE R gaggggg W

I-

- . - . - . - . - e_e _e_e e I I I I i 1 A ,T, .

" I SIN 90R PROGRAM DtSCIPitNE I^'II*#

SH,p y SYSTEMS STARi tiP SITE Slif MANAGE RS Surf maNTENOf NYg RESI,M COMPtfTlON StfPPOsly WE LDENG MANAGER SE CURIT Y ggg Wf ENT R MAbsAGE R SUPE Risdif 900f MT SUPE RIN TE NDE NT M

< ,AeR TIOss tAeOR M,{,yNT CONSTRUCTsOss MANAGER tsast Surf RvtSIOss

R g

_R= T.S Rf ==- S=::,=,T = = fNT -

MAT R.A<S e STOP WORE AUTHORfiY LA N d I

% T4

EBASCO SERVICES INCORPORATED QUALITY ASSURANCE ORGANIZATION (HRECTOR OUAttiv ASSURANCE I I I I

  • I MANAGER MANAGER MANAGtR St NM MANAGER mytagg OUAL 11Y OUAt tiV OUAt tf Y ASSURANCE ASSUR ANCE ASSURANCE sum AUTV l'ROJE C TS (NGINE (RING SE R VICE S A80CE Stif StRVICES g I I I l l I

MANAGf MENT & MANAGEMtNTIb A SUPE R VISING SUPE R VISIPfG MANAGERS OUAllTV MANAGER E NGINE E RS E NGINE E RS 550 PfDf INTERNAf 90NAL PRmiRAM MANAGEMENTS MANAGEtefNin OUALITY OUAlt!Y OUAl tiV SITE MAN AGE R TE O AUTV AREA aggggaucg SUPE R VISORS SUPE RVISORS ASSURANCE ASSUfqANCE ASSUR ANCf E NGINE E RS PROJE C f S INGINE f RING I

I l l mutamat numugG MONCT OUAllT V OUAttiV Self AS$4STA887

" vtwnon ayatuavMm e OUAu f V A$$UR ANCf CONIROL CONSM W ASSURANCE ountstv mesounctS A SIT E Sit t RfCORDS "

  1. a "G SUPI RVISOR E NGINEIRS esa'gec'"t w'e e t SUPT RVt OR UPt R VISOq 8" SUPf RVISORS E NL8NE E RS ortaa enses na e cuality mgCO#DS esassactestet e T#s esO amat Ytt$

RaOtaffDee Saf a f 7 OU AlliY ASSURANCE E NGINE E RS l -

OUALITY OUAllTV OUALITV UII NA"IY "IOEA Y ASSURANCE ASSUR ANCE CONTROL ECOROS ASSUR ANCE / M RYeCE WSTRUCitW Rf p M NTL INGINE t RS/ f NGINE TRS/ E NGINE E RS/

I II A"I Y E E IIA"'NAIO I SPE CI Alls TS SPIC 4AltSTS M CI AL IST S E WINEERS/ $PE CI AllST S SP(C$AltSTS & STANDARDS SPI CI Alf$iS SPICIAttsf5 ADMfNIST R A TION W "1 e ssov arpt etAets to rs t eve QMC ouaut, assuna=cs omaamerarsom JS m tT!

I t/) H

  • H I m .t3

EBASCO SERVICES INCORPORATED OUALITY ASSURANCE ENGINEERING QUALITY ASSURANCE SPECIALISTS EMAG C VOR 4O UAt . A-t f T.

I

_ I _I_ __I

.=A .

. A. A . ._,4, U <= > = a T

. A UA,.t t.T T, u -i s .o .A. . . ,r,,J, I L _ . .__ I ___1._____ _l .

w w

,,,e,s,e,n,,n a., serm,De,,S,,I,ne,sc,,l,evt

,A A

""'."i."4,".=

' "#' I

=

8

""'"'c"o.8."."*"C' '"""'",r,

==

,o ,

AS

. Assam medeaf gu,e aven DM mvists GBAN,AGS 880 4 3 2s,E WWsSOR R,,EumassCE 0 RyggGIS SU 9 RwtSoft

_ _ , _ _ y

__I_ _I___ __I__ 1 1 __ I _ _I_ i __1. __ _ _ L_ _ l ObsAt 6f T (RJat tf T ASSURAastg c,e naFION=

I gg gg, se M 8 R

===a = =ava .. A.00 me.485 n c.800.in At.o.m o sfe.r A.,g g aaa .A.f AmCOR.O.B.. GU=l.f.v.A&.slWRAfe[5 A,,,,

ogg g g e s aassoastops t u nasseeaf m A88D CE RI es? 5819 Aospessaggaaggse NAE " E 8 ' I .tCamagts . trC :.v

= , at A6syll

.U,.

Of AUDef ameG I

I . . . _ _ _ _ - . _ _ _I _I

  • ====

== ,,, A A r .

vi or=

gg S vet UAl enes ,AUDe g pg,aseDam,D,B gg ygg gg RE Outet est e TS w eouaAtsen.g A<=aa'a a '= ou, t.&as

== c=w u m.

t,,

y____ , ,

.__I __.l___. I

_ l __ .l___ I_ _ l __. .__I _ __I _ . _ I___ _ I __ ._ _1_ _

=ac c'"" ,,.'l",',,, an ,""

"= ==uaa . Ac"" .

",*a * 's 0 la

==

MH . seOs APPLDCABLE TO THE STP dO OUALITY ASSURA88CE ORGApollAfeOst C

00

@M I

Cf3 H H l N .N N

.I INTERFACE BETWEEN HOUSTON LIGHTING & POWER COMPANY, BECHTEL ENERGY CORPORATION, AND EBASCO SERVICES INCORPORATED

'- " "s ' = ' , ' , ' ' -- -- -------

MX,,,

1 HOUSION LIGHilNG as POWE R CO J emes eenn es e < iemeeeeneme. . mmemesnumumeemenene ... ..ne......... .. meneummeenoeme eumeennuseenenmemessennemueuem.

fit LHII L f NE HGV COfiP ronPon A II ()g gpr,pg nA e see eaes a sesNee f it I D g PMOJf C I DA ==== =----== ptinWfm M A "8 "I " MANAfitR 9nnJE C1 I ser, ease e missG RICHIE L ENf RGV COf4P mene.< . .mmeneeenen euees ee meeneeem ess ee ee s s e s ee eee ee eeeens ee eeemee < mesoommenmesmenouemeeeeeenoemuseenne eememmme eeemmenee i R A5CO Si RVICI" INC DeHf C f f)R PRg getH N T

- Ot ta g i t y - 884500 A $56 DR A NC f C08d19 ReK f OR% INC .

l

( omsgIpe13C INief I e Mi A t 0I w Pete M;44 Asie MANAGER l

Sif f MANAt lft - == amm --a- ame == =

$49f MANAGE H 73 M t1 m

-1 .O;

ts

& [9 8 #NilRIAtl l @ ** - - = = = = = f e e4BMitects A f H We DtV trl DNf %f NNPR Mf $409 N f

,'a M^Naus at s ae '*'s a Q .

is e ee=u A . A .MeNeu n A s ve Oneig e Ise seg

$109-21($TP)4 3 PAGE 1 OF HOUSTON LIGHTING AND POWER COMPANY

$ECTION SOUTH TEXAS PROJECT EBASCO SEWCES ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C INCORPORATED QA-I-3 PERSONNEL INDOCTRINATION AND TRAINING

__ PROGRAM IN OUALITY ASSURANCE 1.0 SCOPE This Section describes the program for indoctrination and training of Ebasco personnel engaged in activities affecting quality with respect to the requirements of this b nual and its supporting principal implementing procedures. Ebasco personnel shall be indoctrinated and trained, as necessary, to assure that proficiency is achieved and maintained in those parts of the Quality Assurance Program as it applies to the individual's responsibility.

2.0 GENERAL The Indoctrination and Training Program is a combined effort of the Ebasco organizations implementing any portion of this Manual and its principal implementing procedures, and the Quality Assurance organization. The Construction, Materials Applications, and Quality Assurance organizations are responsible to schedule, indoctrinate, and train their personnel, and to record this indoctrination and training, unless otherwise denoted by project commitments.

3.0 PROGRAM REQUIREMENTS 3.1 Preplanned written lessons shall contain the substance of the indoctrination and training program. These lessons shall address one or more quality-related topics, to achieve one or more stated educational objectives. The training will be conducted by trained supervisors or their designees within the Construction and Materials Applications organizations, and by a Quality Assurance Education Specialist or designee when the need arises. A Quality Assurance Education Specialist will be responsible for training the selected instructors within the other Ebasco organizations in methods of conducting required quality assurance training.

[ 3222M

-- _ _ _ _ -. _ n_._ _ _ _ ___ _- _.___. __ _

siosaustenas pace 2 0, 3 HOUSTON LIGHTING A!;0 POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SENCES ELECTRIC GENERATING STATION UNITS 1 & 2

- QUAUTY ASSURANCE PROGRAM DESCRIPTION - PAfiT C QA-I-3 INCOR POR A TE D PERbONNEL INDOCTRINAT ON AND TRAINING PROGRAM IN QUALITY ASSURANCE 3.2 For Construction, Quality Assurance, and Materials Applications, preplanned training lessons are maintained by each organization respectively. The preplanned training lessons relate to activities the personnel shall be performing. For Construction and Materials Applications, a responsible person within the respective organization shall determine the training requirements for each individual based on that individual's assigned responsibilities and past experience. Within the Quality Assurance organization, a Quality Assurance Education Specialist shall be responsible for determination of an individual's training requirements based upon that individual's assigned responsibilities and past experience, as applicr're. Preplanned training lessons are updated, when required, and reflect a-- changes in the program. Copies of these preplanned training lessant ,shall be kept on file by the respective organization. Quality-affected. training will reflect project requirements.

4.0 RECORDS ' \

Individual training files for personnel in the Construction, Quality Assurance, and Materials Applications organizations receiving indoctrination and training in accordance with this program's requirements shall be maintained by each affected organization. These records will indicate, as applicable, the subject matter, the training received, attendance date, time duration, instructor, and special qualifications or restrictions, if any.

5.0 SCHEDULING ,

Scheduling training of applicable organization personnel will be coordinated with a Quality Assurance Education Specialist where necessary. As new personnel are added to the South Texas Project within an organization, appropriate indoctrination and training sessions will be scheduled based in the requirements of this Manual.

6.0 PROGRAM UPDATING This indoctrination and training program is subject to continuous development to broaden and improve its effectiveness. A Quality Assurance Education j

Specialist will hold periodic discussions with those groups involved with the training program to coordinate recommendations for updating. A Quality l Assurance Education Specialist is responsible for updating the program for the

, Quality Assurance organization.

3222M

siosausrea.es pace 3 or 3 HOUSTON LIGHTING AND POWER COMPANY

$ECTION SOUTH TEXAS PROJECT E 5O E ES ELECTRIC GENERATING STATION UNITS 1 & 2 QUAUTY ASSURANCE PROGRAM DESCRIPTION - PART C QA-I-3 PERSONNEL INDOCTRINATION AND TRAINING PROGRAM IN QUALITY ASSURANCE 7.0 ADMINISTRATION 7.1 The Quality Assurance Engineering Quality Resources and Training Management Group shall have overall responsibility for administrating the quality assurance training program. It shall provfde technical expertise for developing necessary programs and review existing programs for currency.

7.2 Management of each Ebasco organization is responsible to assure that the appropriate personnel attend the training program (s) for which they are scheduled.

8.0 TRAINING, QUALIFICATION, AND CERTIFICATION OF QUALITY CONTROL PERSONNEL Training, qualification, and certification of Site Quality Control inspection personnel shall be in accordance with written procedures. The Quality Control Site Supervisor or his designee shall coordinate with a Quality Assurance Education Specialist regarding the training, qualification, and certification of Quality Control personnel. Qualification records for all Quality Control personnel assigned to the South Texas Project site shall be maintained by a Quality Assurance Education Specialist at the site. These records will be reviewed initially by the Manager Quality Assurance Engineering, or his designee, for compliance with the qualification requirements, and thereafter on an annual basis by auditors from the Site Quality Assurance organization.

Any deficiencies detected shall be reported in writing by the Quality Assurance Site Supervisor, or his designee, to the Quality Control Site Supervisor for resolution. Pending resolution of the deficiency, the individual shall be restrained from performing any Quality Control activities.

9.0 AUDITS Audits of indoctrination and training activities shall be performed to assure compliance with this Program. Such audits shall be performed in accordance with the requirements of Section QA-III-9 of this Manual.

l 3222M

siosaitsre>44s paos 1 or 4 HOUSTON UGHTING AND POWER COMPAN) $ECTION SOUTH TEXAS PROJECT EBASCO SERVICES ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C A-I-6 INCORPORATED QUALITY ASSURANCE RECORDS 1.0 SCOPE This Section covers the requirements and guidelines for the collection, filing, storage, disposition, and maintenance of lifetime and nonpermanent quality assurance records associated with the construction and maintenance of nuclear power plants.

2.0 RESPONSIBILITY It shall be the responsibility of Ebasco to maintain quality assurance (QA) records in accordance with the requirements of this Section until such time as those records are turned over to the Client or his designee for permanent storage. The HL&P SIP - RMS Site Records Center is the principal and final records repository. All QA records shall be accessible to the Client or his designee until such time as they are turned over to the Client or his designee.

3.0 QUALITY ASSURANCE RECORDS SYSTEM Each organization within Ebasco (including but not limited to the Construction and Quality Assurance organizations) that participates in the generation, collection, filing, storage, disposition, or maintenance of quality assurance records shall establish a writtca quality assurance record system applicable to the function (s) performed by that organization. These written procedures shall provide that each completed quality assurance record shall be transmitted by the organization generating the records to the Ebasco Site Quality Records group for final review and transmittal to the Client or his designee. This system shall be implemented and enforced in accordance with the requirements of the following paragraphs that apply to the function (s) of that org'anization.

4.0 GENERATION OF QUALITY ASSURANCE RECORDS 4.1 The QA, records to be generated shall be specified in the applicable desigi specifications, constructiot 3. maintenance, test, or inspection praccdures, and other documents as necessary.

4.2 hil QA records shall be dated and signed or otherwise authenticated.

4.3 Gi records shall be indexed. The indexing system shall include as a

- 'r.ininum:

4.3.1 - QA r cords retention times (retention period begins on date

.of satisfactory operation of items).

3222M

cosausrea4s pace 2 Or 4 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBA5Co SENES ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C INCORPORATED QA-1-6 QUALITY ASSURANCE RECORDS 4.3.2 Location of storage area.

4.3.3 Location of QA records within storage area.

4.4 All QA records shall be distributed and handled in accordance with written instructions.

4.5 There shall be sufficient information in the QA records to permit identification between the records and the item (s) or activity to which it applies. Identification of QA records may be by purchase order number, system, or any means that permits accurate traceability.

4.6 All QA records shall be classified as " lifetime" or " nonpermanent."

4.7 When QA records are corrected or supplemented they shall be reviewed or approved by the organization that originated the records. All corrections and supplements shall bear dates and authorized signatures or initials traceable to the authorized individual.

4.8 Inspection and test records shall contain the following, as applicable:

a) The type of observation.

b) Evidence of completing and verifying an inspection or test operation, c) The date end results of the inspection or test.

d) Information related to nonconformances.

e) Inspector or data recorder identification.

f) Evidence of the acceptability of the results.

5.0 RECEIPT OF QUALITY ASSURANCE RECORDS 5.1 A system shall be established for receipt of QA records at the Site which shall include:

5.1.1 A checklist designating the required QA records.

3222M

61094 HST P)445 PAGE 3 or 4 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SENCE5 ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C INCORPORATED QA-I-6 QUALITY ASSURANCE RECORDS 5.1.2 A record of QA records received.

5.1.3 Written procedures for receipt and inspection of incoming Site QA records.

These quality assurance records shall be maintained by Site Quality Records and audited by Site Quality Assurance to assure that they are maintained properly until turned over to the Client or his designee.

5.2 The system described in Paragraph 5.1 of this Section shall permit an accurate assessment of the status of the QA records during the receiving process.

6.0 TEMPORARY STORAGE, PRESERVATION, AND SAFEKEEPING 6.1 QA records shall be stored in accordance with a written procedure which shall require or include the following:

6.1.1 Description of storage facility, if other than a dual facility.

6.1.2 Description of filing system to be used.

6.1.3 Method for verifying that QA records received are in agreement with transmittal documents and pre-established records checklist and that the QA records are legible.

6.1.4 Rules governing access to files.

6.1.4.1 A list shall be generated designating those personnel who shall have access to the files.

6.1.5 Method fer maintaining control of QA records removed from storage. Such method shall provide for signing out of QA records removed from storage or other appropriate means of maintaining control of the records removed.

6.1.6 Method of filing supplemental information and supurseding obsolete QA records. Supplemental information shall be filed with the original documents whenever practical.

6.2 A custodian (or custodians) shall be desigaated to implement the requirements of Paragraph 6.1 of this Section.

3222M

sionatisre>44s R,og 4 or 4 HOUSTON UGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBA5CO SENCES ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C INCORPORATED QA-I-6 QUALITY ASSURANCE RECORDS 6.3 QA records may be stored within a temporary storage facility if they are protected from damage and loss. This shall include:

6.3.1 Storage within fire-resistant cabinets with a four-hour Underwriters' rating or a satisfactory alternative.

6.3.2 Protection from condensation.

6.3.3 Disallowance of loose documents. Records shall be attached to binders, placed in folders, or similarly maintained.

6.3.4 Specially processed QA records such as radiographs, microfilm, etc, shall be stored and protected in accordance with the manufacturer's recommendations.

6.4 A satisfactory alternative to the requirements of Paragraph 6.3 of this Section is maintenance of duplicate QA records stored in a separate remote location.

6.5 Audits shall be performed to assure the effectiveness of the storage system, and shall include:

6.5.1 Verification that QA records which have been processed into the records facility are available in their proper location and in good condition, including those records that have been logged-out and removed away from the storage system.

6.5.2 Audit results shall be documented and its resulted discrepancies shall be verified to assure their correction.

6.6 The storage systems shall provide for accurate retrieval of QA records without undue delay.

7.0 DISPOSITION OF QA RECORDS Upon transfer of QA records, the Client or his designee shall acknowledge in writing the receipt of the particular QA records.

8.0 AUDITS Audits shall be performed in accordance with Section QA-III-9 of this Manual to assure conformance to the requirements of this Section.

3222M

cos msrew PAos 1 or 4 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SENCEs ELECTRIC GENERATING STATION UNITS 1 & 2 WCOR POR A TED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-l INSTRUCTIONS, PROCEDURES, AND DRAWINGS 1.0 SCOPE Activities affecting quality performed at the construction site shall be described in written instructions, procedures, or drawings that have been developed in accordance with the requirements of this Section. Departmental procedures which describe the manner in which activities affecting quality are to be accomplished are part of the Ebasco Quality Program.

2.0 RESPONSIBILITIES 2.1 Where the Ebasco Nuclear Quality Assurance Manual designates an individual or organization with the responsibility of performing quality-related functions at the construction site, such functions shall be performed in accordance with written instructions, procedures, or drawings that have been developed by the organization performing the function. These instructions, procedures, and drawings shall establish the manner of performing the activity in accordance with the requirements of the Ebasco Nuclear Quality Assurance Program Manual and of the organization performing the activity.

2.2 When documented evidence is required for the satisfactory performance of particular activities, checklists, forms, and/or other appropriate means shall be utilized to provide this evidence. Such documents shall be signed and dated by the party performing the activity.

2.3 Ebasco procedures, instructions, or drawings describing activities affecting quality which are qualitative or quantitative in nature (ie, inspections or tests) shall contain or reference criteria for determining that such activities have been satisfactorily accomplished.

2.4 Standard Quality Assurance Procedures, and Standard Site Procedures when applicable, shall be reviewed and approved by the Quality Program Site Manager prior to implementation.

3.0 DEVELOPMENT OF INSTRUCTIONS, PROCEDURES, AND DRAWINGS 3.1 Instructions, procedures, or drawings for activities affecting quality at the construction site shall be developed by the Construction and Site Quality Assurance organizations for their respective quality-related functions. The Ebasco Nuclear Quality Assurance Program Manual shall be used as a guideline for their development. In addition, all Site Quality Control Procedures shall include or reference at least the following:

3223M

sto9 2HSTPM45 2 4 PAGE or HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SEmCES ELECTRIC GENERATING STATION UNITS 1 & 2 INCORPORATED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-l INSTRUCTIONS, PROCEDURES, AND DRAWINGS a) Identification of characteristics to be inspected, b) Identification of the individuals or groups responsible for performing the inspection operation, c) Acceptance and rejection criteria.

d) A description of the method of inspection.

e) Verification of completion and certification of inspection.

f) A record of the results of the inspection operation.

3.2 The Ebasco Engineering Development and Standards Department shall develop company instructions and procedures of categories, such as Nuclear (N), pertaining to quality-related functions.

3.3 Individual departments / disciplines shall be responsible for the development of their own intradepartmental/ discipline instructions, procedures, or drawings that establish the methods for performing quality-related functions. The Ebasco Engineering Development and Standards Department will provide, upon request, guidance and assistance in developing the documents.

3.4 If so requested by a department, Quality Assurance Engineering shall act in an advisory capacity during the preparation of internal Ebasco procedures.

3.5 All procedures, instructions, and drawings for activities affecting quality shall be identified, dated, and shall provide authorized signature (s) of approval.

3.6 To assure that all Ebasco Quality Control and Construction procedures and instructions comply with this Manual, site-specific requirements, and applicable codes and regulatory requirements, they shall be submitted for review and acceptance to Ebasco Site Quality Assurance prior to implementation. When required by the Contract, quality assurance, quality control, special process, and construction procedures and instructions shall also be submitted to the Client or his designee for acceptance prior to implementation.

i 3223M

sio 2,<srp;445 ,4ac 3 Or 4 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SEWCES ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C INCOR, ORATE 7 QA-III-l INSTRUCTIONS, PROCEDURES, AND DRAWINGS 3.7 The Standard Quality Assurance Procedures are procedures which are developed by the Client, Bechtel, and Ebasco and are common to each organization. Standard Quality Assurance Procedures shall be approved by the Quality Program Site Manager prior to implementation.

3.8 The Standard Site Procedures are developed by Bechtel, Ebasco, and the Client, as applicable, for project activities. The Standard Site Procedures shall be approved by the Ebasco Construction Manager and, where required, by the Quality Program Site Manager prior to implementation.

4.0 DISTRIBUTION AND CONTROL 4.1 Each Ebasco department shall be responsible for maintaining and enforcing a written system for the distribution and control of that organization's instructions, procedures, and drawings (other than design; ie, rigging drawings) for activities affecting quality. This system shall provide for at least the following:

4.1.1 Copies of these documents and revisions thereto shall be distributed to all appropriate department personnel in a timely manner.

4.1.2 Outdated and/or superseded documents shall either be destroyed or shall be clearly marked as " Superseded" or " Void" to avoid inadvertent use.

4.1.3 A file of the latest revision of these documents shall be maintained. Such a file shall be readily available to all affected personnel.

4.1.4 A log of the documents shall be maintained. The log shall indicate as a minimum:

a) Title of document.

b) Document identification number.

c) Latest revision number and date of document presently in use.

d) Distribution of document (Manual Holder No.).

3223M

sios-austra4s paos 4 or 4 HOUSTON LIGHTING AND POWER COMPANY S ECTION SOUTH TEXAS PROJECT EBASCO SEplCES ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C INCORPORATED kA-III-1 INSTRUCTIONS, PROCEDURES, AND DRAWINGS 4.2 A historical file of all revisions and changes to instructions, procedures, and drawings shall be maintained by the applicable organization responsible for such documents or as may be described in the applicable organization's procedures.

4.3 All approved Ebasco site generated field sketches, construction procedures, quality control procedures, and special process procedures shall be transmitted to the Client or his designee for distribution and control in accordance with Section QA-III-2 of this Manual.

5.0 CHANGES TO DOCUMENTS Changes to Ebasco documents, the Standard Quality Assurance Procedures, and the Standard Site Procedures shall be reviewed and approved by the same organization responsible for the original document when those changes affect the original reviewer, unless delegated in writing by the originating organization to another responsible organization. The reviewing organization shall have access to pertinent background information upon which to base their approval and shall have adequate understanding of the requirements and intent of the original document.

6.0 AUDITS Audits shall be performed in accordance with Section QA-III-9 of this Manual to assure conformance to the requirements of this Section.

3223M

_y_.p_ .- ,- -- -

sios-ausrpa4s pace 1 or 4 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SERWCEs ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C A-III-2 INCORPORATED DOCUMENT CONTROL 1.0 SCOPE This Section of the Manual establishes the requirements for the control of all project documents used by Ebasco which have an effect on quality-related activities. These requiremente apply to those documents such as specifications and drawings, as well as site instructions and site procedures, which control or direct activities affecting quality.

2.0 RESPONSIBILITIES 2.1 The correspon!ing Department Heads or their designees shall be responsible for furnishing the Client or his designee with the latest of all Ebasco site generated field sketches, construction procedures, quality control procedures, and special process procedures.

2.2 The Client or his designee shall be responsible for the distribution and control of all construction site design documents, drawings, specifications, construction procedures, quality control procedures, special process procedures, and Standard Site Procedures.

2.3 Ebasco shall assure satisfactory implementation of the Client or his designee's distribution and control of Ebasco-generated documents as per the requirements of Paragraph 6.0 of this Section of the Manual.

2.4 The Quality Assurance Site Supervisor or his designee shall be responsible for the distribution and control of site generated Quality Assurance Instructions and the distribution of Standard Quality Assurance Procedures.

3.0 _IS_SUANCE OF CONTROLLED DOCUMENTS 3.1 Establishment of Document Control Stations 3.1.1 Docunent control stations shall be established and maintained by the Client or his designee.

3.1.2 Requests by Ebasco for the establishment of new or deletion of existing document control stations for the distribution of controlled documents shall be submitted by the corresponding Department Head or Discipline Manager to the Client or his designee. lR13 3.1.3 Requests by Ebasco for additions or deletions of documents issued to an established document control station shall be submitted to the Client or his designee.

3222M

siosausrex4s pace 2 4 or HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ESA CO SENCEs ELECTRIC GENERATING STATION UNITS 1 & 2 INCORPORATED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-2 DOCUMENT CONTROL 3.2 Design Documents, Drawings, and Specifications 3.2.1 The Client or his designee shall furnish, distribute, and control all design documents, drawings, and specifications to the established document control stations in accordance with the Client's or his designee's written procedures.

3.2.2 Ebasco personnel shall use during their work activities the latest design documents, drawings, and specifications as provided by the Client or his designee at the appropriate document control stations, except that field change requests in an " Interim Approval" stage shall be controlled by the Senior Resident Engineer in accordance with approved site procedures.

3.3 Ebasco Intradepartmental/ Discipline Instructions and Procedures 3.3.1 Intradepartmental/ Discipline instructions and procedures shall be issued and controlled in accordance with Section QA-III-l of this Manual.

3.3.2 Quality Assurance Instructions and Standard Quality Assurance Procedures describing responsibilities of Site Quality Assurance shall be distributed and controlled at the construction site in

" book" form by the Quality Assurance Site Supervisor. A master file shall be maintained of all procedures and revisions. A master list shall be maintained indicating each person or organization to whom a book of procedures has been issued. New or revised procedures will be issued to each holder of a procedure

" book." A receipt system shall be used which requires written acknowledgement of distributed procedures. Receipt acknowledgements shall be maintained for the latest revision.

3.4 Ebasco Site-Generated Procedures and Instructions Ebasco site generated construction, special process, and quality control procedures and instructions shall be transmitted to the Client or his designee for distribution to the established document control stations.

3.5 Field Change Requests 3.5.1 A Field Change Request shall be submitte; to the Senior Resident Engineer from applicable site personnel whenever conditions arise which may warrant consideration by the Client or his designee of a change in the specified design.

3222M

sion auste>44s pace 3 or 4 HOUSTON LIGHTING AND POWER COMPANY S E CTION SOUTH TEXAS PROJECT EBAS O SE ES ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-2 DOCUMENT CONTROL 3.5.2 The Senior Resident Engineer shall submit the proposed Field Change Request to the Client or his designee for evaluation, disposition, distribution, and control by the Client or his designee in accordance with the Client's or his designee's written procedures.

3.5.2.1 In order to expedite field change requests associated with in process activities against design drawings, an " Interim Approval" shall be obtained by the Senior Resident Engineer from the Client or his designee in accordance with approved site procedures.

3.6 Field Change Notice 3.6.1 A " Field Change Notice" shall be generated by the Senior Resident Engineer as is allowed by the design specification and shall be approved, issued, and controlled by the Senior Resident Engineer in accordance with approved site procedures.

3.6.2 A Field Change Notice (FCN) is to provide construction with a method of documenting conditions (not tolerances) that are within criteria allowed by the applicable specifications. An FCN shall not i be used in lieu of a Nonconformance Report (NCR) or a Field Change Request (FCR).

3.7 Field Sketches 3.7.1 Field sketches shall be prepared, reviewed, and approved by the Senior Resident Engineer or his designee in accordance with approved site procedures. Only the following two types of field i sketches shall be permitted to be utilized by field personnel as a basis for the fabrication, installation, and inspection of safety-related items:

a) Field sketches which have been approved by the Client or his designee, b) Field sketches which the Senior Resident Engineer has

, determined to be within standard detailing parameters established by specifications prepared by the Client or his designee.

3.7.2 Field sketches shall be transmitted by the Senior Resident Engineer to the Client or his designee for approval and/or distribution to the established document control stations by the Client or his designee.

3222M

6109 21($TP)4-85 k PAGE OF k HOUSTON LIGHTING AND POWER COMPANY

$ECTION SOUTH TEXAS PROJECT EBASCO SENCES ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C A-III-2 INCOR POR ATED

DOCUMENT CONTROL i 4.0 CHANGES TO DOCUMENTS i

Changes to Ebasco documents shall be distributed in the same manner as the  !

original document. Revised documents shall be controlled in accordance with '

the requirements of this Section and/or written procedures in order to avoid

inadvertent use of outdated documents.

4 5.0 QUALITY ASSURANCE RECORDS Quality Assurance records shall be maintained by Site Quality Records which shall be audited by Site Quality Assurance to assure that they are maintained properly.

5.1 The system for control and retrieval of Quality Assurance records at the site shall be in accordance with Section QA-I-6 of this Manual.

j 6.0 AUDITS I

Ebasco Site Quality Assurance shall audit the Client's or his designee's

, control and distribution of Ebasco generated construction, special process, and quality control procedures and instructions in accordance with the requirements of Section QA-III-9 of this Manual.

i i

f 1

i i

i a

3222M 1

,. , - - . - . _ _ _ _ _ _ _ . _ _ _ _ _ _ _. _. . . . , . . . _ . _ , _ . - _ - _ _ . . _ _ - ~ , . - - _ . . _ - _ _ . _ _ _ . - _ _ _ .

e sos-a usrei4.es pace 1 5 or HOUSTON LIGHTING AND POWER COMPANY

$ECTION SOUTH TEXAS PROJECT EBASCO SERVICES ELECTRIC GENERATING STATION UNITS 1 & 2 INCORPORATED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-6 NONCONFORMANCES 1.0 SCOPE This Section establishes the requirements for the identification, control, and disposition of items or services found to be in nonconformance with the applicable requirements at the construction site. All activities described in this Section shall be performed in accordance with written instructions and/or procedures.

2.0 CONSTRUCTION SITE NONCONFORMANCES 2.1 Nonconformances at the construction site may be detected by Ebasco Site Quality Control, Site Quality Assurance, or Construction. The person identifying a nonconforming condition shall document the condition by initiating a South Texas Project Site Nonconformance Report.

2.2 All nonconformances detected shall be reported to the Quality Assurance Site Supervisor and/or the Quality Control Site Supervisor or their designees. A preliminary assessment of the severity of the nonconformance shall be made in accordance with Company Procedure N-23 or approved site procedures. The final responsibility for evaluation of all nonconformances for possible reportability rests with the Client or his designee.

2.3 Quality Control procedures shall require that all nonconforming items shall be clearly marked or tagged as conconforming and shall be segregated when possible.

2.4 The Nonconformance Report shall then be reviewed and processed in accordance with Paragraph 4.0 of this Section of the Manual.

2.5 After processing of the Nonconformance Report, the Quality Assurance Site Supervisor or his designee shall distribute copies of the reviewed and evaluated report in accordance with internal Site Quality Assurance Instructions.

2.6 The Quality Assurance Site Supervisor and the Quality Control Site Supervisor or their designees from the Site Quality Assurance organization shall verify by audits, reinspections, or other appropriate means that the necessary corrective actions are taken.

3223M

s ios-msr es-es pace 2 or 5 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SERME5 ELECTRIC GENERATING STATION UNITS 1 & 2 lNCORPORATED QUAUTY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-6 NONCONFORMANCES 3.0 REINSPECTION 3.1 For nonconformances detected at the construction site, the Quality Control Site Supervisor or his designee shall assure that reinspection is performed on all items and services reported as nonconforming.

Reinspection shall be performed in accordance with the requitements of the governing code (s) and in accordance with requirements at least as stringent as those by which the nonconformance was detected. He shall document the satisfactory correction or resolution of all nonconformances on the dispositioned Nonconformance Report. This documentation shall provide sufficient detailed information for as-built records.

3.1.1 Nonconformances not corrected in accordance with the requirements of the approved disposition to the Nonconformance Report shall not be accepted by Site Quality Control. Items or services shall not be accepted by Site Quality Control until such time as the appropriate corrective action has been accomplished.

4.0 REVIEW OF NONCONFORMANCE REPORTS 4.1 Upon receipt or initiation of a Nonconformance Report, the Quality Assurance Site Supervisor or his designee from the Site Quality Assurance organization shall perform the following functions in accordance with QA procedures and/or instructions:

4.1.1 Log-in the report and record a unique identifying number on the report.

4.1.2 Route the report to the Client or his designee who shall disposition and approve the report.

4.1.3 Receive the report from the Client or his designee following approval of the dispositioned report.

4.1.4 Upon receipt of the approved Nonconformance Report from the Client or his designee, the Quality Assurance Site Supervisor or his designee shall log-in the results of the review and distribute copies of the report for implementation of the approved disposition as necessary in accordance with approved procedures.

3223M l

siosausTra4s paar 3 o, 5 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SERVICES ELECTRIC GENERATING STATION UNITS 1 & 2 INCORPORATED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-6 NONCONFORMANCES 4.2 Dispositions for all nonconformances to the design specifications or other documents originally requiring review and approval of the Client or his designee, must have the review and approval of the Client or his designee prior to implementation unless otherwise permitted by approved procedures.

4.3 The Quality Assurance Site Supervisor or his designee shall perform a final review for closure of Nonconformance Reports generated in accordance with the requirements of this Section.

4.4 The Quality Assurance Site Supervisor or his designee shall maintain on file, copies of all open Nonconformance Reports generated in accordance with the requirements of this Section.

5.0 DEFICIENCY NOTICES 5.1 Deficiencies in the quality of items and services which either violate the restrictions of Paragraphs 5.2 and 5.3 of this Section of the Manual or are detected during final inspection at the construction site, and which can (approved be Client by the corrected bydesignee or his reworking)or duringby the standard normal repair procedures course of construction, shall be documented on a Deficiency Notice. Copies of all Deficiency Notices shall be transmitted to the Quality Control Site Supervisor or his designee who will initiate Nonconformance Reports based on information given in the Deficiency Notices when he determines that this action is necessary. In this case, the Deficiency Notice becomes a part of the Nonconformance Report and only the Nonconformance Report is required to be resolved.

5.2 Items discovered to be out-of-tolerance or not to specification at in process inspection checkpoints of an inspection process shall be documented on a Deficiency Notice, provided all conditions listed below are met:

a) The condition is corrected prior to final inspection / acceptance of the work.

b) The work does not proceed beyond the checkpoint until the correction is made.

c) The out-of-tolerance condition does not reflect on work previously accepted.

d) No violation of code is evident.

4 l 3223M i

siosauste>44s pros 4 ,, 5 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SERVICES G A NG TATION UNm 1 & 2 fNCORPORATED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-6 NONCONFORMANCES Deficiencies meeting the above requirements which can easily be reworked immediately by Construction, may be documented on the inspection report, with no other documentation required.

Examples include, but are not limited to:

a) Loose bolts.

b) Undersized welds.

c) Coating thickness too low.

d) Surface profile too low.

Damage which would affect the integrity of an item shall be classified as a nonconformance and processed accordingly.

5.3 An unacceptable ASME Code weld found during the normal welding / inspection process shall be processed and reported on a

" Process Data Checklist" form in accordance wir.h approved Site Quality Control procedures. Any unacceptable weld found after the normal welding / inspection process is completed shall be documented as nonconforming in accordance with this Section of the Manual.

5.4 The processing of Deficiency Notices shall be detailed in approved Site Quality Control procedures.

6.0 TREND ANALYSIS OF NONCONFORMANCE REPORTS AND DEFICIENCY NOTICES 6.1 Ebasco's Corporate Trending Copies of Nonconformance Reports from the sources mentioned above shall be submitted to the Quality Assurance Engineering Supervisor of Auditing. The Quality Assurance Engineering Superviser of Auditing subsequently receives the Nonconformance Report and makes an analysis of the available data with respect to quality trends.

The trend analysis and distribution of subsequent reports shall be made in accordance with the requirements of Quality Assurance Procedure QA-D.3.

3223M k ^

siosastei4-es ,,o, 5 o, 5 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SERWCEs ELECTRIC GENERATING STATION UNITS 1 & 2 tNCORPORATED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-6 NONCONFORMANCES 1

6.2 Client's Trending Copies of Nonconformance Reports (NCR's) and Deficiency Notices (DN's) from the sources mentioned above shall be transmitted to the

, Client's Quality Systems / Administration (QS/A). The Client's QS/A is responsible for the South Texas Pro ject Trend Program activity in accordance with their procedure (s). '

7.0 RECORDS Nonconformance Reports shall be maintained in accordance with Section QA-I-6 of this Manual and/or approved Site Quality Assurance Instructions.

8.0 AUDITS Ebasco Site Quality Assurance shall be responsible for the performance of audits in accordance with Section QA-III-9 of this Manual to the extent necessary to assure compliance to the requirements of this Section.

4 4

3223M

610941($T P)445 PAGE OF HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SEREE5 ELECTRIC GENERATING STATION UNITS I & 2 INCORPORATED QUAllTY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-7 CORRECTIVE ACTION 1.0 SCOPE This Section establishes the requirements for the identification, analysis, and implementation of corrective action for safety-related items and services. The Section applies to activities performed at the construction site.

2.0 GENERAL 2.1 Corrective action shall be required for identified and documented nonconformance(s) associated with safety-related items and services.

2.2 The need for corrective action may be identified from the following sources:

a) Inspection activities performed by Site Quality Control.

b) Site Quality Records document reviews.

c) Quality Assurance audits performed by the Quality Assurance organization in accordance with Section QA-III-9 of this Manual.

d) Audits of Ebasco performed by the Client or his designee or regulatory bodies.

c) Nonconformances detected at the construction site as described in Section QA-III-6 of this Manual, f) Audits of the Quality Assurance and Materials Applications organizations performed by the Management Audit Committee.

g) Surveillances performed by Site Quality Assurance.

2.3 Determinati i and review of corrective action items shall be made as early as possible in order to preclude the possible repetition of deficiencies.

2.4 During the review of all corrective action items, consideration shall be given to the training of personnel if it is determined that this was a cause of the deficiency.

2.5 Dissemination of corrective action information to responsible individuals shall be performed in a minimum length of time.

3223M

siosausre>44s Pao, 2 4 or HOUSTON LIGHTING AND POWER COMPANY SECTION S0UDi TEXAS PROJECT EBASCO SENES ELECTRIC GENERATING STATION UNITS 1 & 2 INCORPORATED QUALITY ASSURANCE PROGRAM 0ESCRIPTION - PART C QA-III-7 CORRECTIVE ACTION 2.6 At the discretion of the Quality Assurance Site Supervisor or his designee from the Site Quality Assurance organization, for corrective action items identified per Paragraph 2.2 of this Section, a corrective action document may be issued. This document shall be used when deficiencies detected are not isolated cases and when they are of sufficient magnitude to warrant a documented supervisory review in accordance with approved Quality Assurance procedures or instructions.

This document goes beyond the standard audit action response required by audit reports.

2.7 For programmatic deficiencies detected by Site Quality Assurance, the maximum length of time for corrective action response shall be 20 working days from the receipt of notice of deficiency. The maximum implementation time shall be 20 working days from the acceptance of corrective action response, unless otherwise approved by the Director Quality Assurance or his designee from the Quality Assurance organization. Nonconformance reports shall be initiated and processed in accordance with Section QA-III-6 of this Manual.

2.8 It shall be the responsibility of the Quality Assurance Site Supervisor or his designee from the Site Quality Assurance organization to assure that all required corrective action is implemented in a timely manner.

2.9 A preliminary assessment of the severity of deficiencies and nonconformances detected shall be made in accordance with Company Procedure N-23 or approved site proc (dures. The final recpunaibility for evaluation of all deficiencies and nonconformances for possible reportability rests with the Client or his designee. Reporting of deficiencies and nonconformances in accordance with 10 CFR 50.55e and its subsequent evaluation will be the responsibility of the Client or his designee.

3.0 DETERMINATION AND IMPLEMENTATION METHODS 3.1 Nonconformance Reports Generated at the Construction Site 3.1.1 Site Quality Control shall perform direct inspection of activities at the construction site as required by Section QA-III-11 of this Manual.

3223M

6109-21tSTPl445 PAGE OF HOUSTON LIGHTING AND POWER COMPANY SECTION SOUDi TEXAS PROJECT EBASCO SERVICES ELECTRIC GENERATING STATION UNITS 1 & 2 INOORPORATED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-7 CORRECTIVE ACTION 3.1.2 Nonconformances noted during these inspection activities shall be documented on a Nonconformance Report in accordance with Section QA-III-6 of this Manual. Site Quality Control shall verify that the corrective action which has been stipulated on the completed form is implemented. Site Quality Control shall maintain a log of all required corrective action and shall review this periodically to assure the resolution of deficiencies and implementation of required corrective action.

3.2 Site Quality Assurance Audits Site Quality Assurance shall perform audits of activities performed at the construction site as required by Section QA-III-9 of this Manual. Site Quality Assurance shall also perform follow-up action as described in Section QA-III-9 to assure that corrective action, if required, has been accomplished. If disagreement about the type or effectiveness of corrective action exists, the problem shall be reviewed by appropriate levels of management until satisfactory resolution is obtained.

3.3 Client or His Designee, or Regulatory Agency Audits Audits of construction site activities may be performed by the Client or his designee and/or appropriate regulatory agencies. If corrective action is required as a result of one of these audits, the Quality Assurance Site Supervisor or his designee from the Quality Assurance organization shall be responsible for obtaining a response from the cognizant individual (s) for submittal to the auditing body.

4.0 FINAL VERIFICATION OF CORRECTIVE ACTION IMPLEMENTATION In addition to his other duties, overall responsibility for verification of the implementation of required corrective action rests with the Quality Assurance Sit

  • Supervisor or his designee from the Quality Assurance organization. He shall be responsible for performing this verification for all items indicated in Paragraph 3.0 of this Section, and shall assure that the corrective action is implemented and in a timely manner. In the event that there is a disagreement between those individuals who detect a deficiency and those responsible for the function found to be deficient, the Quality Assurance Site Supervisor shall contact appropriate higher levels of management as necessary until resolution is obtained.

3223M

s ios.2 u sm4-as 4 4 Pace or HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SERVICES ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C INCORPORATED QA-III-7 CORRECTIVE ACTION 5.0 DETERMINATION AND AISYSIS OF QUALITY TRENDS 5.1 Ebasco's Corporate Trending In order to prevent the recurrence of quality problems, Ebasco has developed a method for the determination and analysis of quality trends. Copies of audit reports and Nonconformance Reports (or other appropriate documentation) mentioned above shall be submitted to the Quality Assurance Engineering Supervisor of Auditing. The Quality Assurance Engineering Supervisor of Auditing subsequently receives all reports and makes an analysis of the available data with respect to quality trends. The trend analysis and distribution of subsequent reports shall be made in accordance with Quality Assurance Procedure QA-D.3.

5.2 Client's Trending Copies of Nonconformance Reports (NCR's), Standard Deficiency Reports (SDR's), and Management Corrective Action Requests (MCAR's) shall be transmitted by the Site Quality Assurance organization to the Client's Quality Systems / Administration (QS/A). The Client's QS/A is responsible for the South Texas Project Trend Program activity in accordance with their procedure (s).

3223M

i siosattsTP)445 PAGE l CF HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SERVICES ELECTRIC GENERATING STATION UNITS 1 & 2 INCORPORATED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-8 CONTROL OF SPECIAL PROCESSES 1.0 SCOPE This Section of the Quality Assurance Manual establishes the requirements for the control of special processes at the construction site. Included herein are provisions for the establishment of critical process parameters, qualification of the processes, and training and qualification of personnel who perform the functions covered by this Section.

2.0 RESPONSIBILITIES 2.1 The Quality Assurance organization shall be responsible for the following:

2.1.1 Developing and implementing Site Quality Control procedures and for qualifying personnel to perform inspection of special processes.

2.1.2 Providing technical assistance for procedure review and development as required.

2.1.3 Qualifying personnel performing nondestructive examination.

2.1.4 Performance of audits in accordance with Section QA-III-9 of this Manual to assure conformance to the requirements of this Section.

2.2 The Materials Applications organization shall be responsible for the following:

a) Development and qualification of welding procedures.

b) Providing technical assistance for procedure review and development as required by Site Quality Assurance and Site Quality Control.

c) Qualification of welders and welding operators.

d) Development of heat treating procedures.

2.3 The Construction organization shall be responsible for the following:

2.3.1 Implementing welding and heat treating procedures.

3223M

siosaitsrea4s Pace 2 o, 3 HOUSTON LIGHTING AND Pr 1 COMPANY SECTION SOUTH TEXAS PRL .CT EBASCO SENES ELECTRIC GENERATING STATION UNITS 1 & 2 INCORPORATED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-8 CONTROL OF SPECIAL PROCESSES 2.3.2 Developing and implementing procedures for other activities classified as special processes (eg, cadwelding, chemical cleaning, flushing) and for qualifying personnel to perform those functions.

2.4 The Ebasco Site NDE Laboratory, an extension of the Materials Engineering Laboratory, is responsible for developing and implementing nondestructive examination procedures.

3.0 METHODS FOR CONTROL OF SPECIAL PROCESSES 3.1 Site Special Process Procedures 3.1.1 Nondestructive examination procedures used at the construction site shall be developed by the Site NDE Laboratory and shall be reviewed and accepted by the Quality Assurance Site Supervisor or his designee, to assure compliance to the requirements of all applicable codes and standards, as a minimum. Conformance to these procedures and qualification requirements shall be verified through audits and surveillances performed by Site Quality Assurance.

3.1.2 All welding procedures used at the construction site shall be prepared by the New York Materials Applications organization. The weld procedures test material shall be prepared either at the home office or the construction site according to instructions for qualification provided by the New York Materials Applications organization.

3.1.3 Construction procedures for site implementation of welding and heat treating requirements shall be developed by the Site Welding Superintendent or his designee.

3.1.4 All welders installing safety-related components shall be qualified according to appropriate codes and standards. Welder qualification shall be performed by the Site Welding Superintendent or his designee. Verification of conformance to procedure and operator qualification requirements shall be performed in accordance with site procedures by Site Welding Superintendent (or his designee) surveillance, Site Quality Control inspection, and/or Site Quality Assurance audit and surveillance functions.

3223M

6109-2 t(ST P)445 pagg 3 o, 3 HOUSTON UGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SENCES ELECTRIC GENERATING STATION UNITS 1 & 2 INCORPORATED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-8 CONTROL OF SPECIAL PROCESSES

3.1.5 All Construction procedures for site implementation of r requirements for welding, heat treating, and other special processes shall be reviewed and accepted by the Quality Assurance Site Supervisor or his designee. All comments resulting from such reviews shall be resolved prior to procedure implementation.

4.0 RECORDS Records pertaining to this Section shall be maintained in accordance with Section QA-I-6 of this Manual.

i-i l

4 i

i 3223M

6109 21($TP)4-85 1 b PAGE OF HOUSTON UGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT ESASCO SENCE5 ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C 1

INCORPORATED QA-III-9 QUALITY ASSURANCE AUDITS I

i 1.0 SCOPE 1

Quality-related activities at the construction site and Ebasco home office are independently audited by the Quality Assurance organization. This Section establishes the requirements and guidelines for the preparation, performance, reporting, and follow-up of quality assurance audits as performed by Site Quality Assurance, home office Quality Assurance Engineering, and the Ebasco Management Audit Committee.

, 2.0 RESPONSIBILITIES 2.1 The Ebasco Quality Assurance Site Supervisor or his designee from 1

the Site Quality Assurance organization shall assign qualified Site Quality Assurance personnel to perform audits of construction site activities.

2.2 The Quality Assurance Engineering Supervisor of Auditing shall 4

assign qualified Quality Assurance personnel to perform home office audits of Ebasco site activities.

4 2.3 A committee chaired by the Quality Assurance Consulting Engineer shall conduct audits of the Ebasco Materials Applications and Quality Assurance organizations at the home office.

3.0 GENERAL REQUIREMENTS FOR AUDITS PERFORMED BY THE QUALITY ASSURANCE ORGANIZATION

3.1 Audit Personnel 4

' 3.1.1 Audit personnel shall be independent of direct responsibility for performance of the activity being audited.

3.1.2 Audit personnel shall be qualified to perform quality assurance audits based on experience and training as described in

! Quality Assurance Procedure QA-G.3.

3.2 Training and Orientation

, 3.2.1 Audit personnel shall have experience and training or orientation to assure their competence for performing audits. The competence of personnel to perform audits shall be developed by one or more of the following methods:

i

a) Providing personnel with working knowledge of appropriate I regulatory documents, practices, codes, and standards.

J r

i 3223M

,, -.---,- - , - - . , . . - - , - - . - - - - , - - - - - - - - , . . , - . - - - . . . - ..-~----,r,. --- - - , - - , -e n~-r- r-- - - -

siosausrew4s paos 2 8 or HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SENCES ELECTRIC GENERATING STATION UNITS 1 & 2 INCORPORATrD QUAUTY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-9 QUALITY ASSURANCE AUDITS b) Training or orientation in general and specialized methods of planning and performing audits.

c) On-the-job training under direct supervision of a Lead Auditor.

3.2.2 The requirements for training and orientation of auditors shall be in accordance with Quality Assurance procedures.

3.3 Proficiency of Lead Auditors 3.3.1 Lead Auditors performing audits shall maintain their proficiency through one or more of the following methods:

a) Regular, active participation in the audit process, b) Review and study of codes, standards, and procedures related to Quality Assurance Programs and program auditing.

c) Participation in orientation or training programs.

3.3.2 The Director Quality Assurance or his designee shall evaluate Lead Auditors in accordance with Quality Assurance Procedure QA-G.3 to assure that the Lead Auditors are maintaining their proficiency.

3.4 Scheduling of Audits 3.4.1 Audits shall be initiated as early in the life of the project or activity as practicable in order to assure timely implementation of the applicable Quality Assurance Program requirements, and to assure effective quality assurance during construction activities.

3.4.2 Audits shall be regularly scheduled on the basis of the status and safety importance of the activities to assure conformance to the Ebasco Nuclear Quality Assurance Program. Applicable elements of the Quality Assurance Program shall be audited by the home office Quality Assurance Engineering and the Ebasco Management Audit Committee at least annually or once within the life of the activity, whichever is shorter.

3.4.3 Audits performed by Ebasco Site Quality Assurance at the construction site shall be scheduled in accordance with the Standard Quality Assurance Procedures requirements.

3223M

siosansrea4s p4ac 3 'or 8 1 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SERWCES ELECTRIC GENERATING STATION UNITS 1 & 2 INCORPORATED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-lll-9 QUALITY ASSURANCE AUDITS 3.4.4 Supplemental audits shall be conducted when:

a) Significant changes in the Quality Assurance Program are made.

b) There is evidence of significant noncompliance to the Quality Assurance Program.

c) An assessment of the effectiveness of the Quality Assurance Program is requested.

d) It is necessary to verify implementation of corrective action.

e) It is considered necessary by the Quality Program Site Manager.

3.5 Planning of Audits '

Preparation for audits shall include the development of a' written audit plan of standard format which shall include or identify the following:

a) Audit scope.

b) Requirements and applicable documents.

c) Activities to be audited.

d) Organization to be audited.

e) Tentative audit schedule.

f) Approved written procedures and/or checklists which assure that the organization will be audited to the extent necessary. These procedures and/or checkliste shall provide for verifying corrective action of deficiencies identified in previous audits.

Audit procedures and/or checklists may be developed as part of a general audit program and need not be unique for each audit.

3223M

s tosa t tsT P>44s pace 4 or 0 H0JSTON LIGHTING AND POWER COMPANY S E CTION SOUTH TEXAS PROJECT EBASCO SERWCE5 ELECTRIC GENERATING STATION UNITS 1 & 2 (NCORPORATED QUAUTY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-9 QUALITY ASSURANCE AUDITS 3.6 The Audit Team 3.6.1 The audit shall be performed by one or more individuals. A qualified Lead Auditor shall be established as the team leader for audits when teams are comprised of two or more auditors. When audits are performed by only one individual, that individual shall be a qualified Lead Auditor and considered to be the team leader.

The team leader shall be responsible for:

a) Orientation of the team.

b) Assuring communication between the team and the organization being audited.

c) Coordinating the preparation and issuance of audit reports.

d) Establishing the pace of the audit.

3.6.2 The team leader shall assure that the team is prepared prior to performing the audit. Information such as appropriate procedures, manuals and prior audit reports shall be made available to the team members. Each auditor shall be provided with any appropriate audit plans, procedures, or checklists necessary to performing the audit.

3.7 Audit Notification The organization to be audited shall be notified of a scheduled audit and the scope of the audit. Such notification shall be given a reasonable time before the audit is to be performed.

3.8 Audit Performance 3.8.1 Checklists and/or written procedures prepared during audit planning shall be used to conduct the audit.

3.8.2 An informal pre-audit conference shall be arranged at the audit site in order to confirm audit scope and discuss the audit plan.

3223M

r

/!

1, a sios-tits rpus pace 5 or 8 HOU$ TON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SENCES ELECTRIC OF.NERATING STATION UNITS 1 & 2 lNCORPORATED QUALITY AS!URANCE PROGRAM DESCRIPTION - PART C QA-III-9 QUALITY ASSURANCE AUDITS 3.8.3 A post-audit conference shall be conducted to:

g.- -

a) Inform those audited of the audit results.

7 b) Assure understanding of audit results.

. 3.9 Reporting of Audit Results 3.9.1 An audit report shall be compiled and shall be signed by the audit team leader. The audit report shall provides a) Description of,the audit scope.

b) Identification of the auditors.

c) Persons contacted.

, d) A summary of the audit results, including an evaluation statement regarding the effectiveness of the Quality Assurance Program elements which were audited.

e) Detailed description of Quality Assurance Program deficiencies and causes thereof where possible.

f) Recommendations for correcting program deficiencies or improving the Quality Assurance Program, if possible.

3.9.2 The s.udit report shall be issued in a timely manner as defined in,the applicable Quality Assurance procedure, but shall not exceed 30 days from the post-audit conference.

3.10 Audit Follow-up 3.10.1 A response to the audit report shall be prepared by the responsible individual and submitted within the required time period as established in the audit report, but shall not exceed 30 days. The response shall state the corrective action taken or to be taken, and the date of completion. The audit team leader, or another qualified Lead Auditor or the management of the auditing group shall review the re7ponse for acceptance. As necessary, subsequent responses may be required to verify completion of corrective action.

3223M

siosaustea4s pace 6 or 8 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EsA CO $E CES ELECTRIC GENERATING STATION UNITS I & 2 QUAUTY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-9 QUALITY ASSURANCE AUDITS 3.10.2 Follow-up action shall be performed by a qualified Lead Auditor to:

a) Assure that the written reply to the audit report is received.

b) Assure that corrective action is identified and scheduled for each program deficiency.

c) Confirm that deficiencies are resolved and corrective action, when necessary, is accomplished.

3.10.3 Follow-up action may be accomplished through written communication, re-audit, or other appropriate means.

3.10.4 Follow-up action taken shall be documented.

3.11 Trend Analysis of Audit Reports The Quality Assurance Engineering Supervisor of Auditing shall make an analysis of the available data (such as the audit reports mentioned above) with respect to quality trends, and report the result of the analysis. Distribution of the trend analysis reports shall be made in accordance with the requiremer.ts of Quality Assurance Procedure QA-D.3.

4.0 SPECIFIC AUDIT REQUIREMENTS 4.1 Management Audits 4.1.1 A committee chaired by the Quality Assurance Consulting Engineer is responsible for conducting audits of Ebasco Materials Applications and Quality Assurance functions to determine compliance with the Ebasco Quality Assurance Program requirements.

This committee is made up of personnel not in the Quality Assurance organization and who are qualified in accordance with criteria denoted in Ebasco Nuclear Procedure N-24. These audits will also include evaluating quality assurance policy effectiveness and assuring that appropriate implementing procedures are available and are being complied with.

3223M

sios-austem pace 7 or 8 HOUSTON UGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBA$CO SERVICES ELECTRIC GENERATING STATION UNITS 1 & 2 INCORPORATED QUAUTY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-9 QUALITY ASSURANCE AUDITS 4.1.2 This auditing shall be accomplished on an annual basis in accordance with the requirements of Ebasco Nuclear Procedure N-24.

The management audit committee shall be comprised of at least two qualified representatives from either Ebasco Constructors Inc or Engineering, and the QA Consulting Engineer. Each committee representative shall be appointed by the respective group Vice President; however, no committee member can be directly engaged in any policy-making or administrative phase of the Ebasco Quality Assurance Program, but shall be knowledgeable in the general area of quality assurance. The committee shall be directly responsible to the Vice President Corporate Quality Programs.

4.1.3 The committee shall prepare an audit report for each audit performed. This report shall be submitted directly to the Vice President Corporate Quality Programs, with copies to other appropriate parties.

4.1.4 The Vice President Corporate Quality Programs shall be responsible for informing the concerned Ebasco management of the results of the audits performed by the committee. He shall also be responsible for initiating the implementation of any changes or corrective action deemed necessary to improve the effectiveness of the Ebasco Nuclear Quality Assurance Program.

4.2 Audits by the Quality Assurance Organization 4.2.1 Site Quality Assurance shall audit the various quality-related activities performed by Ebasco organizations on the construction site in accordance with the requirements of this Section, the applicable Site Quality Assurance Instructions, and the Standard Quality Assurance Procedures.

4.2.2 Training and qualification records for Site Quality Control personnel shall be audited in accordance with Section QA-I-3, Paragraph 8.0, of this Manual.

4.2.3 Quality Assurance auditors shall have the authority to reject items, services, or work for nonconformance to the specification, drawing, or quality control requirements.

4.2,4 Home office Quality Assurance Engineering will conduct periodic audits and evaluations of the construction site annually in accordance with this Manual and Quality Assurance Procedure QA-D.5.2.

3223M

. . _ - . _ . - -- . -- . _ - . ~ _ . - - . _

sios aiistr>44s pace 8 or 8

.1 HOU$ TON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT

  • EBASCO SERVICE 5 ELECTRIC GENERATING STATION UNITS 1 & 2 INCORPORATED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-9 QUALITY ASSURANCE AUDITS 5.0 AUDIT RECORDS 5.1 Records generated during audit preparation, performance, or l follow-up shall be retained for all audits in accordance with the applicable requirements of Section QA-I-6 of this Manual and/or approved Quality Assurance procedures. Such records shall include:

a) Audit plans and checklists, t

I b) Audit reports.

4 c) Written replies to audit reports. j d) Status of required corrective action.

e) Other documents which support audit findings and corrective i action as appropriate.

1 5.2 Records of training and experience of auditors shall be maintained for all personnel who are performing audits or who have previously performed audits. These shall be retained for the same period of time as required for the audit reports with which the auditors are associated.

Maintenance and retention shall be in accordance with Quality Assurance Procedure QA-G.3.

I i

i 3223M

,. ~ - _ _ _

e sosausTP>44s ,,,, 1 o, 3 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBA5CO SERVICES ELECTRIC GENERATING $TATION UNITS 1 & 2 lHCORPORATED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-10 IDENTIFICATION AND CONTROL OF ITEMS 1.0 SCOPE '

1.1 This Section establishes the requirements for the identification and control of safety-related items at the construction site.

1.2 The activities described herein shall be performed in accordance with written instructions, procedures, and/or drawings that have been developed and accepted in accordance with the requirements of Section QA-III-1 of this Manual.

2.0 RESPONSIBILITIES 2.1 Site Quality Control shall be responsible to perform the following functions in accordance with written procedures:

a) Assure that items received from the Client or his designee at the construction site are properly identified and are accompanied by appropriate documentation traceable to the items.

1 b) Assure that all items shall be physically identified in accordance with Paragraph 3.0 of this Section of the Manual, and appropriate written procedures.

c) Assure that identification of items shall be transferred to inspection and test records and as-built documents in a manner sufficient to provide the required traceability.

d) Assure that itema are handled and stored in accordance with the requirements of Section QA-III-14 of this Manual so as to maintain identification.

2.2 The Quality Assurance Site Supervisor or his designee from the Site Quality Assurance organization shall be responsible for the performance of reviews and audits in accordance with Section QA-III-9 of this Manual to assure compliance to the requirements of this Section.

3.0 GENERAL 3.1 Documented Quality Control procedures require that items shall be physically identified by the following means, as applicable:

a) Stenciled or etched markings b) Strip markings i

3223M

siosaitsre>44s pace 2 or 3 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT E ASCO 5E CES ELECTRIC GENERATING STATION UNITS 1 & 2 QUAUTY ASSURANCE PROGRAM DESCRIPTION - PART C

, , QA-III-10 IDENTIFICATION AND CONTROL OF ITEMS c) Imprinted tape d) Tagging e) Stamping f) Color-coding g) Records traceable to the items h) Procedural control i) Other appropriate means in accordance with approvcd Site Quality Control procedures 3.2 When it is impractical to physically identify individual small items, these may be identified as to heat numbers, batch, lot, or

]

specification by applying markings to bags, bins, tanks, or other.

suitable containers.

3.3 Identification of items shall provide the required degree of traceability to pertinent documents.

1 3.4 All markings shall be clear, unambiguous, and indelible and shall not affect the function of the item when applied.

1 3.5 When an item is subdivided, markings shall be transferred to each part of the item.

3.6 Markings shall not be obliterated or hidden by surface treatment or coatings unless other means of identification is substituted.

3.7 All safety related items and materials shall be controlled by one or more of the following:

a) Uniquely identifiable and traceable.

b) Physically marked items are not traceable but readily retrievable.

c) Physically identified as to type and users tested.

d) Identifiable as to type, by some physical characteristic or other administrative control.

3223M

siosa nsre>44s Pace 3 or 3 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBA5Co 5ER CES ELECTRIO GENERATING STAP9N UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C p QA-III-10 IDENTIFICATION AND CONTROL OF ITEMS 4.0 RECORDS Records pertaining to this Section shall be maintained in accordance with Section QA-I-6 of this Manual.

3223M

_ _ _ _ _ - _ _ _ _ _ . _ - _ - . _ a

sios-msm4.es ,m 1 y 3 HOUSTON UGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT

""*5 0 5E CES ELECTRIC GENERATING STATION UNITS 1 & 2

, ,, QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-ll INSPECTION 1.0 SCOPE This Section establishes the requirements for the inspection of safety-related items and services at the construction site as necessary to assure compliance with documented instructions, procedures, specifications, drawings, codes, and regulatory requirements.

2.0 RESPONSIBILITIES 2.1 Site Quality Control shall be responsible for the following:

a) Development of written procedures for the inspection of safety-related items and services which list the required inspection activities when existing inspection documents such as standard specifications and drawings do not provide an adequate basis for inspection.

b) Submittal of inspection procedures to Ebasco Site Quality Assurance for review and acceptance in accordance with Section QA-III-l of this Manual.

c) Preparation of reports for all inspections made.

d) Approval processing of inspection procedures and revisions thereto.

2.2 Site Quality Control shall be responsible for performing inspection activities in accordance with appropriate inspection documents.

2.3 Qualification of inspection personnel shall be in accordance with applicable Quality Assurance procedures and Paragraph 4.0 of this Section of the Manual.

2.4 The Quality Assurance Site Supervisor or his designee from the Site Quality Assurance organization shall be responsible for the performance of reviews and audits in accordance with Section Qi-III-9 of this Manual to the extent necessary to assure compliance with Lhe requirements of this Section.

3.0 GENERAL 3.1 Inspection documents shall be prepared based upon the quality requirements contained in specifications, quality control documents and procedures, and applicable codes and standards.

3223M

~

siosausrp>44s paoc 2 or 3 HOUSTON LIGHTING AND POWER COMPANY

$ECTION SOUTH TEXAS PROJECT EBAS O E CES ELECTRIC GENERATING STATION UNITS 1 & 2 QUAUTY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-ll l INSPECTION 3.2 If mandatory inspection hold points are required, the specific hold points shall be indicated on the inspection documents.

3.3 Inspection documents shall specify or reference as a minimum the activities to be performed, acceptance criteria, by whom activities are performed, and the sequence in which the activities are to be performed.

3.4 Where mandatory inspection hold points are indicated on inspection documents or procedures, work may continue beyond a hold point only with the written approval of the Quality Control Site Supervisor or his qualified designee.

3.5 Inspection reports shall indicate the acceptability status of the items or services inspected with respect to meeting the applicable quality requirements.

3.6 When inspections are to be performed by use of a sampling program (ie, to determine the acceptability of a group of like-items based upon the results of an inspection of a representative number of items from the group), the sample size shall be identified on the inspection documents.

Justification for this sampling shall be based upon recognized standard construction practices and successful past experience, as well as the complexity and function of the activity, item, or service to be inspected.

4.0 TRAINING AND QUALIFICATION OF INSPECTION PERSONNEL 4.1 Inspection personnel shall have experience and training to assure their competence for performing inspection. The competence of personnel to perform inspections shall be developed by one or more of the following methods:

a) Providing personnel with working knowledge of appropriate regulatory documents, practices, codes, and standards.

b) Training or orientation in general and specialized methods of planning and performing inspections.

c) On-the-job training under direct supervision of an experienced, qualified inspector.

I

! 3223M l

L

6109-21($T P)4 45 PAGE OF HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SENCES ELECTRIC GENERATING STATION UNITS 1 & 2 INCORPORATED QUAUTY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-11 INSPECTION 4.2 The requirements for training and qualification of inspectors shall be in accordance with applicable Quality Assurance procedures, and qualification of inspectors shall be based upon consideration of the following:

a) Records of education and experience, b) Test results, where applicable.

c) Results of capability determination.

4.3 Site Quality Control shall be responsible for scheduling and cr.ordinating training for quality control personnel in advance of implementation of the applicable inspection documents. This training shall be conducted in sufficient detail and with sufficient frequency to assure that the personnel responsible for the inspection fully understand the requirements contained in the applicable inspection documents.

4.4 Inspectors performing inspections shall maintain their proficiency through one or more of the following methods:

a) Regular, active participation in the inspection process. '

b) Reilew and study of codes, standards, and procedures related to Quality Assurance Programs and program inspection.

4.5 The Director Quality Assurance or his designee shall periodically evaluate inspectors in accordance with applicable Quality Assurance procedures to assure that the inspectors are maintaining their proficiency.

5.0 RECORDS 5.1 All inspection documents shall be maintained in accordance with Sectian QA-I-6 of this Manual.

5.2 Records of training, experience, and certification of inspectors shall be maintained for all personnel who are performing inspection or who have previously performed inspections. These records shall be retained for the same period of time as required for the inspection reports with which the inspectors are associated.

3223M

siosa us r p>445 pace 1 ,, 2 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBA$CO SERWCE5 ELECTRIC GENERATING STATION UNITS 1 & 2 INCORPORATED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-12 TEST CONTROL 1.0 SCOPE 1.1 This Section describes the system employed at the construction site which assures that tests required to demonstrate that items will perform satisfactorily in service are identified and documented. The requirements of this Section apply to all phases of the testing program at the construction site, including, but not limited to: functional testing, proof testing, acceptance testing, and operational testing.

1.2 These tests shall be performed in accordance with written test procedures which include or reference the requirements and acceptance limits contained in applicable design documents.

2.0 RESPONSIBILITIES 2.1 Site Quality Control procedures shall provide for the following:

a) Assuring that all prerequisites for the given test have been met.

b) Use of trained personnel to witness tests.

c) Identification of test equipment and the item to be tested.

d) Checking the condition of test equipment and the item to be tested.

e) Use of devices calibrated in accordance with Section QA-III-13 of this Manual for the performance of tests.

f) Verification that tests are performed under proper environmental conditions; eg, cleanliness.

g) Documentation of test results, h) Acceptance criteria for test requirements.

2.2 Site Quality Assurance shall review and comment on the written procedures for tests covered by this Section. All comments shall be resolved prior to implementation of the procedures. These test procedures shall be reviewed in accordance with Site Quality Assurance procedures and/or instructions for the inclusion of:

a) Provisions for assuring that all test prerequisites have been met.

3223M

Gl09-2t($TP)4 85 PAGE OF HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJEC1 EBASCO SERVICES ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C mconPonarco QA-III-12 TEST CONTROL b) Identification of items to be tested.

c) Identification of calibrated devices or equipment to be used during testing.

d) Provisions for checking condition of test equipment and item to be tested, e) Proper environmental conditions under which test is to be performed.

f) Test methods.

g) Operations to be performed.

h) Inclusion of, or reference to, acceptance criteria.

1) Data to be recorded.

j) Requirements for qualified and/or certified personnel.

2.3 Test reports shall be reviewed and signed-off by Ebasco Quality Control in accordance with written procedure requirements to assure that test requirements have been satisfied.

2.4 The Quality Assurance Site Supervisor or his designee from the Site Quality Assurance organization shall be responsible for the performance of reviews and audits in accordance with Section QA-III-9 of this Manual to the extent necessary to assure compliance to the requirements of this Section.

3.0 RECORDS All records pertaining to this Section shall be maintained in accordance with Section QA-I-6 of this Manual.

i l

l 3223M l

L

s ios.zirst p>44s paar 1 or 2 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SEWICES ELECTRIC GENERATING STATION UNITS 1 & 2 INCORPORATED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-13 CONTROL OF MEASURING AND TESTING EQUIPMENT 1.0 SCOPE 1.1 This Section describes the interface activities between the Client and Ebasco for the purpose of providing Measuring and Test Equipment (M&TE) and calibration services. This Section also describes the requirements of Ebasco's M&TE control for the equipment used at the construction site when performing tests and inspections of safety-related items.

1.2 Ebasco's activities described herein shall be performed in accordance with written instructions, procedures, and/or drawings that have been developed and accepted in accordance with the requirements of Section QA-III-l of this Manual.

2.0 RESPONSIBILITIES 2.1 The Client shall be responsible for the issuance and subsequent calibration of all measuring and testing devices.

2.2 The Ebasco Quality Control Site Supervisor or his designee shall be responsible to assure compliance with site implementing procedures for the control of user M&TE apparatus used by the Site Quality Control.

2.3 The Ebasco Site Manager or his designee shall be responsible to assure compliance with site implementing procedures for the control of user M&TE apparatus used by Ebasco Construction.

2.4 The users shall assure that the measuring and testing devices used are marked with the proper identification number and identified to their calibration due date, and are of the proper range, type, and accuracy to verify conformance to established requirements.

3.0 GENERAL 3.1 Measuring and Test Equipment issued from the Client to Ebasco shall be controlled in accordance with approved site procedures.

3.2 Methods shall be employed to assure proper handling, storage, and care of the M&TE in order to maintain its required accuracy.

3223M

[

$ 109-2 t(ST P)445 paog 2 2 or HOU$ TON LIGHTING AND POWER COMPANY SECTION SOUTH TEXA5 PROJECT EBASCO SERWCES ELECTRIC GENERATING STATION UNITS 1 & 2 QUAllTY ASSURANCE PROGRAM DESCRIPTION - PART C INCORPORATED QA-III-13 CONTROL OF MEASURING AND TESTING EQUIPMENT 3.3 Any M&TE found to be out-of-calibration shall be returned to the Client. When M&TE is found to be out-of-calibration, damaded, lost, or stolen, an evaluation shall be made to ascertain the validity of previous inspection or test results and the acceptability of suspect items, the original required inspections and/or tests shall be repeated using properly calibrated equipment. Suspect items on which a questionable device was used shall be listed on the Nonconformance Report (NCR) or Deficiency Notice (DN), as applicable.

3.4 Inspection and test reports shall include identification of M&TE used to perform the inspections and/or tests.

3.5 The Quality Assurance Site Supervisor or his designee from the Site Quality Assurance organization shall be responsible for the performance of reviews and audits in accordance with Section QA-III-9 of this Manual to the extent necessary to assure compliance with the requirements of the Client's measuring and test equipment calibration program and the requirements of this Section.

4.0 RECORDS Records pertaining to this Section shall be maintained in accordance with Section QA-I-6 of this Manual.

3223M

siosa usrea 4s paos 1 or 5 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SEWCES ELECTRIC GENERATING STATION UNITS 1 & 2 INCORPORATED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-14 CONTROL OF RECEIVING, HANDLING, AND STORAGE 1.0 SCOPE 1.1 This Section describes the methods employed during receiving, handling, storage, and installation to assure that all safety-related items received by Ebasco at the construction site will be usable when needed. These requirements apply to both items received by Ebasco from the Client or his designee and Ebasco site-fabricated subassemblies which require temporary storage before assembly or installation. They also apply to both on-site and off-site facilities which are used for the storage of items under control of the construction forces.

1.2 The activities described herein shall be performed in accordance with written instructions, procedures, and/or drawings that have been developed and accepted in accordance with the requirements of Section QA-III-1 of this Manual.

1.3 The storage of safety-related items maintained in facilities under the direct control of the Client or his designee is excluded from the scope of this Manual.

2.0 RESPONSIBILITIES 2.1 The Ebasco Construction organization shall be responsible for the following-a) Performance of receiving, handling, storage, maintenance, and cleaning activities in accordance with specifications provided by the Client or his designee and/or code requirements.

b) Development of methods for special handling (off-loading) in accordance with manufacturer's recommendations and/or specifications provided by the Client or his designee.

c) Establishing storage areas to meet levels as briefly described below:

1) Level A - Indoor, controlled environment.
2) Level B - Indoor, heated and ventilation controlled.
3) Level C - Indoor or equivalent, ventilation controlled.
4) Level D - Outdoor.

3223M

$ 10941($T Pi445 PAGE OF HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SENCES ELECTRIC GENERATING STATION UNITS 1 & 2 INCORPORATED QUAUTY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-14 CONTROL OF RECEIVING, HANDLING, AND STORAGE d) Development of general storage plans which list types of items and their intended storage locations and levels. Such plans shall be prepared prior to receipt of items from the Client or his designee.

2.2 Ebasco Site Quality Control shall be responsible for the following:

a) Qualification of personnel performing inspection functions applicable to receiving, handling, and storage.

b) Assigning qualified quality control personnel for performance of inspection and/or surveillance of receiving, handling, storage, maintenance, and cleaning activities.

c) Performing and documenting inspection and/or surveillance activities in accordance with approved checklists to verify that receiving, handling, storage, maintenance, and cleaning activities, as described in Paragraph 2.1 of this Section, are performed in accordance with project requirements.

d) Establishing and implementing methods for rejection of nonconforming items which provide adequate means of identifying the item as nonconforming and physically segregating the item where practical. When segregation is not practical, a status type indicator shall be used. Application and removal of status type indicators shall be by quality control personnel only.

2.3 Ebasco Site Quality Assurance shall be responsible for the performance of audits in accordance with Section QA-III-9 of this Manual to the extent necessary to assure compliance to the requirements of this Section.

2.4 The Client or his designee is responsible for procurement and initial receiving inspection of all safety-related items. However, if requested in writing by the Client or his designee to perform initial receiving inspection of safety-related items upon their arrival at the job site, Ebasco will conduct a complete program that covers the full parameters of this Section. Otherwise, Ebasco shall conduct a receiving inspection program as is applicable and in accordance with approved site procedures.

3223M

_o

sios.2usTP>44s ,,ac 3 o, 5 HOUSTON LIGHTING ArdD POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SERVICES ELECTRIC GENERATING STATION UNITS 1 & 2 (NCORPORATED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-14 CONTROL OF RECEIVING, HANDLING, AND STORAGE 3.0 RECEIVING INSPECTION 3.1 Safety-related items utilized for fabrication, erection, installation, or modification shall be subjected to receiving inspection to assure conformance to the requirements of the applicable drawings, specifications, and other documents as required. Where source inspection is not performed, receiving inspection at site for acceptability will be performed.

3.2 Inspection Requirements Receiving inspection procedures shall be prepared by the Qualf.ty Control Site Supervisor or his designee in accordance with the requirements of this Manual. These procedures shall provide instructions and checklists for performing receiving inspection and shall include at least the following activities:

a) Documentation review to assure that the documentation package has been received and that a signed " Release for Shipment" form accompanies the items received, when applicable.

b) Visual examination, c) Marking and tagging for traceability.

d) Testing when specified.

e) Preparation for storage.

4.0 HANDLING i

4.1 Handling practices applied to safety-related items shall assure minimum possibility for damage or loss of environmental protection.

4.2 Inspection Requirements Site Quality Control procedures shall provide for at least the following:

a) Review of handling requirements for safety-related items, b) Performance of appropriate inspections to assure that handling operations have not jeopardized item integrity.

3223M

4109-21($7P)445 pagg 4 5 o,

HOUSTON LIGHTING AND POWER COMPANY SE CTION SOUTH TEXAS PROJECT EBASCO SENCE5 ELECTRIC GENERATING STATION UNITS I & 2 INCORPORATED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-14 CONTROL OF RECEIVING, HANDLING, AND STORAGE 5.0 STORAGE AND IN-PIACE PROTECTION 5.1 All safety-related items shall be stored in locations and storage levels as outlined below except for those items released from storage and placed in their permanent or staged locations which shall be cared for, maintained, and inspected in accordance with design specifications and the applicable approved procedures. In place protection in permanent location is permitted for large items such as equipment, provided that the permanent location is ready for the item installation. If the permanent location or the area in which the item is staged does not afford the required level of protection, additional protection shall be provided to prevent degradation of the item. For in place protection purposes, a permanent location shall be considered to be within the room and/or immediate vicinity in which the item is to be permanently installed.

5.2 Inspection _ Requirements Site Quality Control procedures shall provide for at least the following:

a) Monitoring of the storage levels listed below:

1) Level A - Indoor, controlled environment.
2) Level B - Indoor, heated and ventilation controlled.
3) Level C - Indoor or equivalent, ventilation controlled.
4) Level D - Outdoor.

-b) Monitoring maintenance of storage areas to control such items as the following:

1) Physical condition of storage area.
2) Access to storage area.
3) Fire protection.

i l 4) Prohibited materials.

i l

l l

l

! 3223M L

$ 10941($T P)445 PAGE OF HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SENCES ELECTRIC GENERATING STATION UNITS 1 & 2 lNCORPORATED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-14 CONTROL OF RECEIVING, HANDLING, AND STORAGE c) Inspection of stored items and items protected in place to assure their integrity.

d) Verification of general storage plans which list types of items and their intended storage locations and levels.

e) Monitoring of storage areas to maintain proper segregation of materials. Items shall retain an appropriate identification for retrievability and inventory control, as applicable to the nature and use of the material.

f) Monitoring of provisions for preservation of items, as required by special conditions.

g) Verification that the withdrawal of any component, assembly, system, or materials from the Client's or his designee's warehouse or storage areas shall be by the Requisition for Stored Items completed by the responsible supervisor or his designated representative. The request shall identify the material and applicable references to a drawing or specification.

5.3 The Client or his designee shall be responsible for the establishment of storage levels, maintenance, and any other applicable handling and storage requirements. The Ebasco Construction organization is responsible for developing and implementing procedures addressing these requirements.

6.0 RECORDS Records pertaining to this Section shall be maintained in accordance with Section QA-I-6 of this Manual.

3223M

c o,q u 3r p,4 4,

,,og 1 o, 2 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SERWCES ELECTRIC GENERATING STATION UNITS 1 & 2 (NCORPORATED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C QA-III-15 INSPECTION, TEST, AND OPERATING STATUS 1.0 SCOPE 1.1 This Section establishes requirements for identifying and documenting the status of inspections and tests performed on safety-related items at the construction site and the status of the readiness of these items for turnover to the Client or his designee.

The Client or his designee is responsible for preoperational testing.

1.2 The activities described herein shall be performed in accordance with written instructions, procedures, and/or drawings that have been developed and accepted in accordance with the requirements of Section QA-III-1 of this Manual. Procedures and instructions shall include identification and authority of the individuals or groups responsible for application and removal of status indicators.

2.0 RESPONSIBILITIES 2.1 Site Quality Control shall be responsible for the following:

2.1.1 Develop and implement a system for maintaining the status of safety-related items through the use of status indicators such as physical location and tags, markings, work travelers, stamps, or inspection records. This system shall provide for the identification and maintenance of the status of inspections and tests performed on these items throughout fabrication, installation, and erection. This system shall provide methods which assure that only items that have passed the required inspections and tests are used or installed. Where physical tagging is either impractical or insufficient, procedural control or other appropriate means for maintaining item status shall be employed.

2.1.2 Control and maintain a log of the issuance and removal of status indicators such as tags. ,

2.1.3 Develop and implement plans for the witnessing and documenting the results of inspections and tests.

2.1.4 Provide methods for assuring that all requin'd inspections and tests are performed (checklists, travelers, etc).

2.2 Construction shall be responsible for the following:

2.2.1 Develop and implement a system for marking and tagging to indicate those safety-related items which are in test, so as to prevent inadvertent operation.

3223M

sios-msrea.es pace 2 or 2 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO ER ES ELECTRIC CENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C

, p QA-III-15 INSPECTION, TEST, AND OPERATING STATUS 2.2.2 Develop and implement a system for maintaining the status of all systems turned over to the Client or his designee for-preoperational testing.

3.0 GENERAL 3.1 Quality Control procedures shall require that inspection and test status be maintained by the use of status indicators such as tags, markings, travelers, stamps, inspection records, work sequence plans, or other appropriate means.

3.2 The progress of fabrication, installation, erection, inspection, and test shall be entered on appropriate documents. Provisions shall be made for updating these documents to reflect current conditions.

3.3 Nonconforming safety-related items shall be clearly identified and marked and shall be processed in accordance with Section QA-III-6 of this Manual.

3.4 Records of tests and inspection results shall be prepared and maintained in an orderly and systematic manner.

3.5 The Quality Assurance Site Supervisor or his designee from the Site Quality Assurance organization shall be responsible for the performance of reviews and audits in accordance with Section QA-III-9 of this Manual to the extent necessary to assure compliance to the requirements of this Section.

4.0 RECORDS Records pertaining to this Section shall be maintained in accordance with Section QA-I-6 of this Manual.

3223M

_ - _ _ _ _ _ _ _ . _ _ _ ~

6109-21(STPl445 PAGE 1 OF 3 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SERWCEs ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C Appendix I INCOR POR ATED TERMS AND DEFINITIONS This Appendix contains certain terms and their definitions used in this Manual that are important to the uniform understanding of the Manual and its application. Where a term is used to convey a different intent than that related herein, clarification must be provided at the point of application:

ACTIVIIIES AFFECTING QUALITY (Quality-related activities) - Activities affecting the quality of safety-related items, including designing, purchasing, fabricating, handling, shipping, storing, cleaning, erecting, installing, inspecting, and testing.

AUDIT - A planned and documented activity performed in accordance with written procedures or checklists to verify, by examination and evaluation of objective evidence, that applicable elements of a quality assurance program have been developed, documented, and effectively implemented in accordance with applicable regulatory documents, guidelines, or requirements. An audit does not include surveillance or inspection for the purpose of process control or product acceptance.

AUDITS (INTERNAL) - Audits perform 3d by Ebasco personnel on those Ebasco organizations that are governed by the Ebasco Quality Assurance Program.

CLIENT OR HIS DESIGNEE " Client" is defined as Houston Lighting and Power Company and "his designee" as Bechtel Energy Corporation.

CONSTRUCTION OPERATION - Activities related to construction of a nuclear power station.

EBASCO HOME OFFICE - Office where project support and related functions are performed at Ebasco, New York.

INSPECTION - A phase of quality control which by means of examination, observation, or measurement determines the conformance of items or services to predetermined quality requirements.

INSTRUCTIONS - Written descriptions of activities to be performed, including job specificaticas, work instructions, shop construction drawings, job tickets, planning sheets, operating or procedure manuals, test procedures, or other written forms, to assure that the activity is adequately described.

ITEM - Any level of unit assembly, including structure, system, subsystem, component, part, or material.

3223M

4109-21(S T P)4-05 2 3 p,og or HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SENCES ELECTRIC GENERATING STATION UNITS 1 & 2 iscomponarso QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C Appendix I TERMS AND DEFINITIONS NONCONFORMANCE - A deficiency in characteristic, documentation, or procedure which renders the quality of an item or service unacceptable. Items discovered to be out-of-tolerance of specification at routine checkpoints of an inspection process shall not be considered as a nonconformance, provided:

a) The conditions are corrected prior to acceptance of the work.

b) The work does not proceed beyond the checkpoint until the correction is made.

c) The condition does not affect work previously accepted.

d) No violation of procedure or Code is evident.

QUALITY ASSURANCE (QA) RECORDS - are those records which furnish documentary evidence of the quality of items and of activities affecting quality. A document is considered a quality assurance record when the document has been completed. QA records may be either the original or a reproduced copy.

QA RECORDS (LIFETIME) - are those records which meet one or more of the following criteria:

a) Those which would be a significant value in demonstrating capability for proper functioning of safety-related items.

b) Those which would be of significant value in maintaining, reworking, repairing, replacing, or modifying the item.

4 i c) Those which would be of significant value in determining the cause 1 of an accident or malfunction of an item.

d) Those which provide required baseline data for in-service inspection.

QA RECORDS (NONPERMANENT) - are those records which meet all of the following criteria:

a) Those of no significant value in demonstrating capability for safe operation.

b) Those of no significant value in maintaining, reworking, repairing, replacing, or modifying the item.

3223M

I sios.wsr p>4.es pace 3 or 3 HOUSTON UGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT cBASCO SERWCES ELECTRIC GENERATING STATION UNITS 1 & 2 INCORpCR ATED QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C Appendix I TERMS AND DEFINITIONS c) Those of no significant value in determining the cause of malfunction of an item.

d) Those which do not provide baseline data for in-service inspection.

QUALITY TREN_D - A consistent reporting of conformance or nonconformance with applicable criteria attributed to a specific organizational unit.

SAFETY-RELATED ITEM - Any item designated by the Client or his designee, in accordance with the guidelines established by the Licensing Department of the Client or his designee, to be Safety Class 1, 2, 3, Seismic Category I, or electrical Class IE and any other items as designated by the Licensing Department and indicated as safety-related in the PSAR or FSAR.

SERVICE - Performance of nuclear safety-related activities such as fabrication, inspection, nondestructive examination, installation, and test.

SPECIAL PROCESS - A special process is a fabrication, testing, or inspection operation whose correct performance is governed by parameters established during qualification testing for the operation, eg, welding and nondestructive testing.

! 3223M l.

siosaitsTr>44s paos 1 6 or HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SERVICES ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C Appendix II EBASCO EXCEPTIONS TO US NUCLEAR REGULATORY GUIDES AND ANSI STANDARDS INDICATED IN SECTION QA-I-l EXCEPTIONS TO ANSI N45.2.5-1974:

1. ANSI N45.2.5-1974, Section 4.8, states " Pumped concrete must be sampled from the pump line discharge." In lieu of this statement, in process strength samples of pumped concrete are taken at the delivery point.

Correlation tests of air content, slump, and temperature are performed to verify these plastic properties of the concrete at the placement point in accordance with the following frequency requirements:

A. A minimum of two correlation tests are performed for each pumped placement exceeding 200 cu. yds.

B. Otherwise, a minimum of two correlation tests per week are performed when any individual pumped placement during a week requires delivery '

of more than one truckload of concrete.

C. During a week when a pumped placement exceeding 200 cu. yds. is made, the correlation tests performed on that placement will satisfy the weekly requirement for performing two correlation tests as specified in Item B above.

If the correlation test result shows a concrete property not meeting the specification limits and/or tolerances at the point of placement, the frequency of correlation testing shall be increased to 100 cubic yards.

If two consecutive correlation tests exceed the specified limit for slump, air content, or temperature, the Constructor shall document the condition, notify Bechtel Site Engineering within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> of completion of the placement and shall return to control of the concrete by in-orocess testing at the point of placement per ANSI N45.2.5-1974.

" Correlation Testing," " Delivery Point," and " Placement Point" are as

defined in ANSI N45.2.5-1978, Section 1.4.
2. Samples and frequency for cadweld testing is in accordance with ACI-359-ASME Section III, Division 2, issued for trial use and comment in 1973, including Addenda 1 through 6 (see Sections 3.8.1.6.3 and 3.8.3.6.3 of the South Texas Project Final Safety Analysis Report).

i j 3223M

stosattsTPM45 PAos 2 or 6 HOUSTON LIGHTINC AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SENCES ELECTRIC GENERATING STATION UNITS 1 & 2

" ^ QUAUTY ASSURANCE PROGRAM DESCRIPil0N - PART C Appendix II EBASCO EXCEPTIONS TO US NUCLEAR REGULATORY GUIDES AND ANSI STANDARDS INDICATED IN SECTION QA-I-l EXCEPTIONS TO ANSJ N_45.2.1-1973:

3. Section 2.1, Planning. The required planning is frequently performed on a generic basis for application to many installa : ions on one or more projects. This rer tits in standard procedures or plans for installation and inspection and f esting which meet the requirements of the standard.

Individual plans fcc each item or system are not normally prepared unless the work operations are unique. However, standard procedures or plans will be reviewed for applicability in each case. Installation plans or procedures are also limited in scope to those actions or activities which are essential to maintain or achieve required quality. This is consistent with Section 2, Paragraphs 2 and 3, of ANSI N45.2-1971 which provides for examinst.on, i measurement, or testing to assure quality or indirect control by monitoring of processing methods. However, final cleaning or flushing activities will be performed in accordance with procedures specific to the system.

4. Section 4, Pre-Installation Cleanness. This section states, " Items should not be delivered to the point of installation site sooner than necessary unless the installation location is considered a better storage area." As an alternate to this requirement items may be delivered to the installation site sooner then absolutely necessary when determined to be advantageous for other considerations, for example, reduced handling or easier access, thereby reducing susceptibility to handling damage. In all such cases, equipment stored in place will be protected in accordance with Section 5 of ANSI N45.2.1-1973.

S. Section 3.1.2, Cleanness Classifications - Class B. Ebasco interprets the lighting level of 100 footcandles to be guidance. It is Ebasco's normal practice that the lighting level for determining " metal clean" of accessible surfaces of piping and components is determined by the inspector. Typically he uses a standard two-cell flashlight supplemented by other lighting as he deems necessary.

EXCEPTIONS TO ANSI N45.2.2-1972:

6. Section 2.7, Classification of Items. The four-level classification system may not be used explicitly. However, the specific requirements for each classification as specified in the standard will be applied to the items suggested in each classification and for similar items.

Classification differing from Section 2.7 will be considered acceptable provided no degradation is assured; for example, electric motors designed for outside service nay be stored in Level C area rather than a Level B.

3223M

...,4,is1 ,, 43

,,,, 3 or 6 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SEnlCES ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C Appendix II

" " " ^ '

EBASCO EXCEPTIONS TO US NUCLEAR REGUIATORY GUIDES AND ANSI STANDARDS INDICATED IN SECTION QA-I-1

7. Section 6.2, Storage Areas. Paragraph 6.2.1 requires control and limited access to storage areas. In lieu of and to amplify this paragraph, the following will be applied:

" Access to storage arean for Levels A, B, and C will be controlled by the individual (s) responsible for storage. While the above areas will be posted to limit access, other positive controls (other than that for the overall site area) or guards may not be provided. Level D areas will be posted with the storage level designation only."

8. Section 5.5, Correction of Nonconformances. This section provides for

" rework" and "use-as-is" dispositions for nonconforming items. As an alternate, the " repair" disposition (as defined in ANSI N45.2.10-1973) will also be used.

9. Section 6.2.4, Storage of Food and Associated Items. Controlled areas, within storage areas, will be established for the storage of food, drink, and salt tablets. These areas will be controlled through normal supervision and inspection.
10. In Section 8, the control of documentation and records shall be in accordance with Section QA-I-6 of the Ebasco Nuclear Quality Assurance Program Manual for the South Texas Project.
11. Appendix A3.4.2, Inert Gas Blankets. There may be cases involving large or complex shapes for which an inert or dry air purge flow is provided rather than a static gas blanket in order to provide adequate protection due to difficulty of providing a leakproof barrier. In these cases a positive pressure purge flow may be utilized as an alternative to the leakproof barrier.

EXCEPTIONS TO ANSI N45.2.3-1973:

12. Section 2.1, Planning. The required planning is frequently performed on a generic basis for application to many installations on one or more projects. This results in standard procedures or plans for installation and inspection and testing which meet the requirements of the standard.

Individual plans for each item or system are not normally prepared unless the work operations are unique. However, standard procedures or plans will be reviewed for applicability in each case. Installation plans or procedures are also limited in scope to those actions or activities which are essential to maintain or achieve required quality.

3223M

siosausrpaas pact 4 or 6 HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SERVICES E' ECTRIC GENERATING STATION UNITS 1 & 2

" QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C Appendix II EBASCO EXCEPTIONS TO US NUCLEAR REGULATORY GUIDES AND ANSI STANDARDS INDICATED IN SECTION QA-I-l

13. Alternative equivalent zone designations and requirements may be utilized to cover those situations not included in the subject standard; for example, situations in which shoe covers and/or coveralls are required but material accountability is not. In addition, zones might be combined into the next more restrictive category in order to reduce total number of zones.

EXCEPTIONS TO ANSI N45.2.4-1972:

14. Section 1.2, Applicability. The standard is applied to the items and systems identified in Paragraph 1.1.1 and to additional systems depending on the nature and scope of the work to be performed and the importance of the item or service involved.
15. Section 2.1, Planning. The required planning is frequently performed on a generic basis for application to many installations on one or more projects. This results in standard procedures or plans for installation and inspections and testing which meet the requirements of the standard.

Individual plans for each item or system are not normally prepared unless the work operations are unique. However, standard procedures or plans will be reviewed for applicability in each case. Installation plans or procedures are also limited in scope to those actions or activities which are essential to maintain or achieve required quality.

EXCEPTIONS TO ANSI N45.2.8-1975:

16. Section 1.1, Scope. The term "important items" will be interpreted to apply to those activities or quality attributes of an item or service that could affect a nuclear safety-related characteristic. For example, if a barrier is required for leakage control, but serves no structural function, the leaktight characteristic would be considered "important,"

but appearance, dimensional requirements, and structural features would not necessarily be considered important; or if a pump casing is required for coolant boundary integrity, but the pump does not have to operate to provide for nuclear safety, those attributes which affect its operation would not be considered important from the standpoint of nuclear safety.

Section 2.1, Planning. The required planning is frequently performed on a generic basis for application to many installations on one or more projects. This results in standard procedures or plans for installation and inspection and testing which meet the requirements of the standard.

Individual plans for each item or system are not normally prepared unless the work operations are unique. However, standard procedures or plans 3223M

s tosa t tsTP)445 PAGE 5 6 3r HOUSTON LIGHTING AND POWER COMPAhr SECTION SOUTH TEXAS PROJECT EEASCO SERVICES ELECTRIC GENERATING STATION UNITS 1 & 2 QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C Appendix II EBASCO EXCEPTIONS TO US NUCLEAR REGULATORY GUIDES AND ANSI STANDARDS INDICATED IN SECTION QA-I-l will be reviewed for applicability in each case. Installation plans or procedures are also limited in scope to those actions or activities which are essential to maintain or achieve required quality.

17. Section 3.3, Processes and Procedures. The terms " installation site,"

" installation area," and " site" used in this standard shall be interpreted as follows:

a) " Installation site" or " site" will be interpreted the same as

" construction site." When applied to documents, these may be at the central office or work area document control station.

b) Installation area - Immediate proximity of location where work is to be performed.

18. Section 3.5(e), Site Conditions. This requirement will be applied only if subsequent correction of adjacent nonconformances could damage the item being installed.

Section 4.6, Care of Items. HL&P retains the authority and is the

" Responsible Organization" for temporary usage of equipment or facilities unless specific (ie, on a case-by-case basis) or general authority is granted in writing to the Construction Manager's organization.

EXCEPTIONS TO ANSI N45.2.9-1974:

19. Section 1.4, Definitions. Quality Assurance Records - A document is considered complete when it has finished full processing and has been issued for use in design, procurement, construction, or manufacturing.
20. Section 1.4, Definitions. Authenticated Records - Those records which are clearly identified as a statement by the individual or organization holding responsibility. Handwritten signatures are not required if the document or printout is clearly identified as a statement by the reporting individual or organization.
21. For Appendix A, an installation shall be considered to be in an "as constructed" condition if it is installed within the tolerances established by Project Engineering indicated in the design output documents.

3223M

_J

siosausre>44s paos 6 6 or HOUSTON LIGHTING AND POWER COMPANY SECTION SOUTH TEXAS PROJECT EBASCO SERWCES ELECTRIC GENERATING STATION UNITS 1 & 2

" " " QUALITY ASSURANCE PROGRAM DESCRIPTION - PART C Appendix II EBASCO EXCEPTIONS TO US NUCLEAR REGULATORY GUIDES AND ANSI STANDARDS INDICATED IN SECTION QA-I-l EXCEPTIONS TO ANSI N45.2.12-1977:

22. ANSI N45.2.12-1977, Section 4.5.1, states, "The audited organization shall provide a follow-up report stating the corrective action taken and the date corrective action was completed." This implies that the audited organization must provide the auditing organization with written notification detailing what corrective action was taken and when the corrective action was completed.

In actual practice, the audited organization will provide the auditing organization with documented corrective action including the date when the corrective action will be ccepleted. The auditing organization will evaluate the corrective action response to determine if corrective action -

verification is necessary. If verification is necessary, the corrective

^

action verification will be performed after the scheduled completion date and the result of the verification will be documented.

23. ANSI N45.2.12-1977, Section 1.3 states, "In no way shall the performance of audits by an organization diminish the responsiblity of the audited organziation or contractor for audit of his designated portion of the [

quality assurance program or the quality of his product or services."

For the South Texas Project all quality-related activities implemented for the South Texas Project are audited annually at a minimum, or at least once within the life of the activity, whichever is j shorter. These audits are performed by either Houston Lighting & Power j Company (HL&P), Bechtel Energy Corporation (BEC), or Ebasco Serviceo Incorporated (ESI) Quality Assurance personnel.

EXCEPTIONS TO ANSI N45.2.6-1973:

24. As an alternate, compliance with ANSI N45.2.6-1978 and R.G. 1,58 (Rev 1, 9/80) in its entirety is acceptable.

3223M i -

j