MONTHYEARML20217H5221999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Byron Station, Units 1 & 2.With ML20212B9261999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Byron Station,Units 1 & 2.With ML20210R3431999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Byron Station, Units 1 & 2.With ML20209H3711999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Byron Station, Units 1 & 2.With ML20195J8001999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Byron Station,Units 1 & 2.With ML20206R6991999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Byron Station Units 1 & 2.With ML20205P7001999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Byron Station,Units 1 & 2.With ML20204C7671999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Byron Station,Units 1 & 2.With ML20199E6371998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Byron Station,Units 1 & 2.With ML20198D1501998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Byron Nuclear Power Station,Units 1 & 2.With ML20195F8321998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Byron Nuclear Power Station,Units 1 & 2.With ML20154L5501998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Byron Nuclear Power Station,Units 1 & 2.With ML20197C9051998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Byron Nuclear Power Station,Units 1 & 2.With ML20151Z9651998-08-31031 August 1998 Revised MOR for Aug 1998 for Byron Nuclear Power Station. Rept Now Includes Page 9 Which Was Omitted from Previously Issued Rept ML20237B4841998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Byron Nuclear Power Station Units 1 & 2 ML20236R1531998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Byron Nuclear Power Station,Units 1 & 2 ML20248M3071998-05-31031 May 1998 Monthly Operating Repts for May 1998 for Byron Nuclear Station,Units 1 & 2 ML20247J9091998-04-30030 April 1998 Monthly Operating Repts for Apr 1998 for Byron Nuclear Power Station,Units 1 & 2 ML20216D5881998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Byron Nuclear Power Station,Units 1 & 2 ML20248L1531998-02-28028 February 1998 Monthly Operating Repts for Feb 1998 for Byron Nuclear Power Station,Units 1 & 2 ML20202G1881998-01-31031 January 1998 Monthly Operating Repts for Jan 1998 for Byron Nuclear Power Station,Units 1 & 2 ML20198P2461997-12-31031 December 1997 Monthly Operating Repts for Dec 1997 for Byron Nuclear Power Station,Units 1 & 2 ML20197F1201997-11-30030 November 1997 Monthly Operating Repts for Nov 1997 for Byron Nuclear Power Station,Units 1 & 2 ML20199D1491997-10-31031 October 1997 Monthly Operating Repts for Oct 1997 for Byron Nuclear Power Station Units 1 & 2 ML20211P8861997-09-30030 September 1997 Monthly Operating Repts for Sept 1997 for Byron Nuclear Power Station,Units 1 & 2 ML20217A9031997-08-31031 August 1997 Monthly Operating Repts for Aug 1997 for Byron Nuclear Power Station,Units 1 & 2 ML20211P9061997-08-31031 August 1997 Corrected Page 8 of Monthly Operating Rept for Aug 1997 for Byron Nuclear Power Station,Units 1 & 2 ML20210L4061997-07-31031 July 1997 Monthly Operating Repts for Jul 1997 for Byron Nuclear Power Station,Units 1 & 2 ML20149D9441997-06-30030 June 1997 Monthly Operating Repts for June 1997 Byron Nuclear Power Station,Units 1 & 2 ML20210L4111997-05-31031 May 1997 Corrected Page 6 of Monthly Operating Rept for May 1997 for Byron Nuclear Power Station,Unit 1 ML20141C3081997-05-31031 May 1997 Monthly Operating Repts for May 1997 for Byron Nuclear Power Station,Units 1 & 2 ML20141E2491997-04-30030 April 1997 Monthly Operating Repts for Apr 1997 for Byron Nuclear Power Station,Units 1 & 2 ML20141C3491997-04-30030 April 1997 Corrected Pp 4 & 10 of Monthly Operating Rept for Apr 1997 for Byron Nuclear Power Station,Units 1 & 2 ML20140D7511997-03-31031 March 1997 Monthly Operating Repts for Mar 1997 for Byron Nuclear Power Station,Units 1 & 2 ML20141C3281997-03-31031 March 1997 Corrected Page 4 of Monthly Operating Rept for Mar 1997 for Byron Nuclear Power Station,Unit 1 ML20141C3131997-02-28028 February 1997 Corrected Pp 4 & 6 of Monthly Operating Rept for Feb 1997 for Byron Nuclear Power Station,Unit 1 ML20136H5811997-02-28028 February 1997 Monthly Operating Repts for Feb 1997 for Byron Nuclear Power Station,Units 1 & 2 ML20134L8651997-01-31031 January 1997 Monthly Operating Repts for Jan 1997 for Byron Nuclear Power Station ML20133M2391996-12-31031 December 1996 Monthly Operating Repts for Dec 1996 for Byron Nuclear Power Station,Units 1 & 2 ML20132C4521996-11-30030 November 1996 Monthly Operating Repts for Nov 1996 for Byron Nuclear Power Station,Units 1 & 2 ML20134N0561996-10-31031 October 1996 Monthly Operating Rept for Oct 1996 for Byron Nuclear Power Station,Units 1 & 2 ML20129A6861996-09-30030 September 1996 Monthly Operating Repts for Sept 1996 for Byron Nuclear Power Station Units 1 & 2 ML20117N5051996-08-31031 August 1996 Monthly Operating Repts for Aug 1996 for Byron Nuclear Power Station,Units 1 & 2 ML20134N0861996-08-31031 August 1996 Revised Monthly Operating Rept for Aug 1996 for Byron Unit 2 ML20134N0631996-07-31031 July 1996 Revised Monthly Operating Rept for Jul 1996 for Byron Unit 1 ML20116M6481996-07-31031 July 1996 Monthly Operating Rept for July 1996 for Bs NPP Units 1 & 2 ML20115E2141996-06-30030 June 1996 Monthly Operating Repts for June 1996 for Byron Nuclear Power Plant Units 1 & 2 ML20117M3851996-05-31031 May 1996 Monthly Operating Repts for May 1996 for Byron Nuclear Power Station ML20117G6261996-04-30030 April 1996 Monthly Operating Repts for Apr 1996 for Byron Nuclear Power Station Units 1 & 2 ML20101R6151996-03-31031 March 1996 Monthly Operating Repts for Mar 1996 for Byron Nuclear Power Station 1999-09-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217H5221999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Byron Station, Units 1 & 2.With ML20217P6351999-09-29029 September 1999 Non-proprietary Rev 6 to HI-982083, Licensing Rept for Spent Fuel Rack Installation at Byron & Braidwood Nuclear Stations ML20217A1691999-09-22022 September 1999 Part 21 Rept Re Engine Sys,Inc Controllers,Manufactured Between Dec 1997 & May 1999,that May Have Questionable Soldering Workmanship.Caused by Inadequate Personnel Training.Sent Rept to All Nuclear Customers ML20212B9261999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Byron Station,Units 1 & 2.With ML20210R3431999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Byron Station, Units 1 & 2.With ML20210E2251999-07-21021 July 1999 B1R09 ISI Summary Rept Spring 1999 Outage, 980309-990424 ML20209G1751999-07-0808 July 1999 SG Eddy Current Insp Rept,Cycle 9 Refueling Outage (B1R09) ML20207H7941999-06-30030 June 1999 Rev 0 to WCAP-15180, Commonwealth Edison Co Byron,Unit 2 Surveillance Program Credibility Evaluation ML20207H8071999-06-30030 June 1999 Rev 0 to WCAP-15178, Byron Unit 2 Heatup & Cooldowm Limit Curves for Normal Operations ML20207H7851999-06-30030 June 1999 Rev 0 to WCAP-15183, Commonwealth Edison Co Byron,Unit 1 Surveillance Program Credibility Evaluation ML20207H7771999-06-30030 June 1999 Rev 0 to WCAP-15177, Evaluation of Pressurized Thermal Shock for Byron,Unit 2 ML20209H3711999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Byron Station, Units 1 & 2.With ML20207H7561999-06-28028 June 1999 Pressure Temp Limits Rept (Ptlr) ML20207H7621999-06-28028 June 1999 Pressure Temp Limits Rept (Ptlr) ML20195J8001999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Byron Station,Units 1 & 2.With ML20207B6481999-05-25025 May 1999 SER Accepting Revised SGTR Analysis for Byron & Braidwood Stations.Revised Analysis Was Submitted to Support SG Replacement at Unit 1 of Each Station ML20195B2591999-05-19019 May 1999 Rev 66a to CE-1-A,consisting of Proposed Changes to QAP for Dnps,Qcs,Znps,Lcs,Byron & Braidwood Stations ML20206R6991999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Byron Station Units 1 & 2.With ML20195C7961999-04-28028 April 1999 Rev 2 to NFM9800233, Byron Station Unit 2 COLR for Cycle 8A (BY2C8A) M980023, Rev 2 to NFM9800233, Byron Station Unit 2 COLR for Cycle 8A (BY2C8A)1999-04-28028 April 1999 Rev 2 to NFM9800233, Byron Station Unit 2 COLR for Cycle 8A (BY2C8A) ML20205P7001999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Byron Station,Units 1 & 2.With ML20205B5091999-03-26026 March 1999 SER Accepting Relief Requests 12R-24,Rev 0 & 12R-34,Rev 0, Related to Second 10-year Interval Inservice Insp for Byron Station,Units 1 & 2 ML20205C5101999-03-21021 March 1999 Revised Safety Evaluation Supporting Improved TS Amends Issued by NRC on 981222 to FOLs NPF-37,NPF-66,NPF-72 & NPF-77.Revised Pages Include Editorial Corrections ML20204G3831999-03-19019 March 1999 Safety Evaluation Accepting Second 10-yr Interval ISI Request for Relief 12R-11 M990004, Rev 0 to NFM9900043, Byron Unit 1,Cycle 10 COLR in ITS Format W(Z) Function1999-03-17017 March 1999 Rev 0 to NFM9900043, Byron Unit 1,Cycle 10 COLR in ITS Format W(Z) Function ML20206A8831999-03-17017 March 1999 Rev 0 to NFM9900043, Byron Unit 1,Cycle 10 COLR in ITS Format W(Z) Function ML20207M9231999-03-12012 March 1999 Amended Part 21 Rept Re Cooper-Bessemer Ksv EDG Power Piston Failure.Total of 198 or More Pistons Have Been Measured at Seven Different Sites.All Potentially Defective Pistons Have Been Removed from Svc Based on Encl Results ML20204H9941999-03-0303 March 1999 Non-proprietary Rev 4 to HI-982083, Licensing Rept for Spent Fuel Rack Installation at Byron & Braidwood Nuclear Stations ML20204C7671999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Byron Station,Units 1 & 2.With ML20199G8271998-12-31031 December 1998 Rev 1 Comm Ed Byron Nuclear Power Station,Unit 1 Cycle 9 Startup Rept ML20205M7061998-12-31031 December 1998 Unicom Corp 1998 Summary Annual Rept. with ML20202F6181998-12-31031 December 1998 Cycle 8 COLR in ITS Format & W(Z) Function ML20206B4001998-12-31031 December 1998 Annual & 30-Day Rept of ECCS Evaluation Model Changes & Errors for Byron & Braidwood Stations ML20199E6371998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Byron Station,Units 1 & 2.With ML20202F6021998-12-31031 December 1998 Cycle 9 COLR in ITS Format & W(Z) Function ML20196K6731998-12-31031 December 1998 10CFR50.59 Summary Rept for 1998 ML20207H7731998-11-30030 November 1998 Rev 0 to WCAP-15125, Evaluation of Pressurized Thermal Shock for Byron,Unit 1 ML20207H8011998-11-30030 November 1998 Rev 0 to WCAP-15124, Byron Unit 1 Heatup & Cooldown Limit Curves for Normal Operation ML20198D1501998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Byron Nuclear Power Station,Units 1 & 2.With ML20196A4191998-11-19019 November 1998 Safety Evaluation Accepting QA TR CE-1-A,Rev 66 Re Changes in Independent & Onsite Review Organization by Creating NSRB ML20195F8321998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Byron Nuclear Power Station,Units 1 & 2.With 05000454/LER-1998-018, Corrected LER 98-018-00:on 980912,inoperable Unit 1 DG Was Noted.Caused by Low Lube Oil Pressure Condition.Immediately Entered Into Lcoar for AC Sources TS 3.8.1.1,Action a1998-10-0909 October 1998 Corrected LER 98-018-00:on 980912,inoperable Unit 1 DG Was Noted.Caused by Low Lube Oil Pressure Condition.Immediately Entered Into Lcoar for AC Sources TS 3.8.1.1,Action a ML20207H7671998-10-0505 October 1998 Rv Weld Chemistry & Initial Rt Ndt ML20154L5501998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Byron Nuclear Power Station,Units 1 & 2.With ML20197C9051998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Byron Nuclear Power Station,Units 1 & 2.With ML20151Z9651998-08-31031 August 1998 Revised MOR for Aug 1998 for Byron Nuclear Power Station. Rept Now Includes Page 9 Which Was Omitted from Previously Issued Rept ML20238F6551998-08-28028 August 1998 SE Authorizing Licensee Request for Relief NR-20,Rev 1 & NR-25,Rev 0 Re Relief from Examination Requirement of Applicable ASME BPV Code,Section XI for First ISI Interval Exams ML20237E2331998-08-21021 August 1998 Revised Pages of Section 20 of Rev 66 to CE-1-A, QA Topical Rept ML20237B3361998-08-14014 August 1998 B2R07 ISI Summary Rept,Spring 1998 Outage, 961005-980518 ML20237B4841998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Byron Nuclear Power Station Units 1 & 2 1999-09-30
[Table view] |
Text
^
a BYRON NUCLEAR POWER STATION UNIT 1 AND UNIT 2 MCETHLY PERFORMANCE REPORT COMMONWEALTH EDISON COMPANY NRC DOCKET NO. 050-454 NRC DOCKET NO. 050-455 LICENSE NO. NPF-37 LICENSE NO. NPF-66 (0625M/0062M-2)
G807080084 880430 POR .
{b I ADOCK 05000454 I. (
R PDC
0 d
I. Monthly Report for Byron Unit 1 for the month of Aoril 1988 A. Summary of Operating Experience for Unit 1 The unit Degan this reporting period in Mode 1 at 98% power. On 4/2/88, a load decrease, for a two week outage, to repair a tube leak in the ID Steam Generator, was started. The turbine was tripped at 0852 on 4/3/88.
Mode 5 (Cold Shutdown) was entered at 0501 on 4/4/88. The outage was completed and the unit synchronized to the grid at 1528 on 4/15/88. By 1300 on 4/18/88 the unit was returned to 98% power. At 2120 on 4/18/88 a reactor trip occurred due to Hi flux rate. The reactor remained in Mode 3 (Hot Standby) until 1149 on 4/21/88 when the reactor was taken critical.
The unit was synchronized to the grid at 1435 the same day. Power was increased to 49% on 4/22/88. The unit operated at power levels of up to 98% for the rett of the reporting period.
G l
l l
i (0625M/0062M-3)
'. .O f
B. OPERATING DATA REPORT 050-454 DOCKET NO.:
UNIT: Byron One DATE: 05/10/88 COMPILED BY: D. J. Spitser TELEPHONE: (815)234-5441 x2023 OPERATING STATUS
- 1. Reporting Period: April 1988. Gross Hours: 720
- 2. Currently Authorized Power Level (MWt): 3411 Design Electrical Rating: 1175 (MWe-gross)
Design Electrical Rating: 1120 (MWe-net)
Max Dependable Capacity (MWe-net): NOT DETERMINED
- 3. Power Level to Which Restricted (If Any): 1097 (Mwe-net)
- 4. Reasons for Restriction (If Any): Steam Generator Split flow (23MW)
THIS MONTH YR TO DATE CUMULATIVE *
- 5. Report Period Hrs. 720 2904 22993
- 6. Rx Critical Hours 369.7 2553.7 17865.7
- 7. Rm Reserve Shutdown Hours 0 0 37.8
- 8. Hours Generator on Line 360.1 25+4.1 17505.1
- 9. Unit Ressrve Shutdown Hours 0 0 0
- 10. Gross Thermal Energy (HWH) 934505 7826762 51422612
- 11. Gross Elec. Energy (MWH) 310196 2592971 17218748
- 12. Net Elec. Energy (MWH) 283917 2443496 16182933 i
- 13. Reactor Service Factor 51.3 87.9 77.7
- 14. Reactor Availability Factor 51.3 87.9 77.9 j' 15. Unit Service Factor 50.0 87.6 76.1
( 16. Unit Availability Factor 50.0 87.6 76.1
- 17. Unit Capacity Factor (MDC not) N/A N/A N/A
- 18. Unit Capacity Factor (DER not) 35.2 75.1 62.8
- 19. Unit Forced Outage Hrs. 65.7 65.7 977.8
- 20. Unit Forced Outage Rate 15.4 2.5 5.3
- 21. Shutdowns Scheduled Over Next 6 Months: 09/03/88
- 22. If Shutdown at End of Report Period, Estimated Date of Startup:
- 23. Units in Test Status (Prior to Commercial Operation): None
- Note - The cumulative numbers do not reflect power generated prior to commercial i service.
l (0625M/0062M-4)
~
o ,
g\
e C. AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.: 050-454 UNIT: Byron One DATE: 05/10/88 COMPILED BY D. J. Spitzer TELEPHONE: (815)234-5441 x2023 MONTH: April, 1988 l
DAY AVERAGE DAILY POWER LEVEL (HWe-Net)
- 1. 1058 MW 16. 329 MW
- 2. 1039 MW 17. 528 MW
- 3. 112 MW 18. 873 MW
- 4. -18 MW 19. -28 MW
- 5. -14 MW __ 20. -27 MW-
- 6. -13 MW 21. 58 MW
- 7. -12 MW 2 2 . _. __ 702 MW
- 8. -13 MW 23. 308 MW
's
- 9. -19 MW 24. 560 MW
- 10. -20 MW 25. 1067 MW
- 11. -16 MW 26, 1078 MW
- 12. -17 MW , 27. 1077 MW __
- 13. -21 NH 28. 1076 MW
- 14. -26 MW 29. 1078 MW
- 15. 55 MW 30. 1075 MW INSTRUCTIONS On this form list the average daily unit power level in MWe-Net for each day in the reporting month. Compute to the nearest whole megawatt. These figures will be used to plot a graph for each reporting month. Note that when maximum dependable capacity is used for the net electrical rating of the unit there may be occasions when the daily average power level exceeds the 100% line (or the restricted power level line.) In such cases the average daily unit power output sheet should be footnoted to explain the apparent anomaly.
(0625M/0062M-5) l 1
4
' a RIport Period April, 1988 UNIT SHUTDOWNS / REDUCTIONS
(UNIT 1) **************************
t No. Date Tyne Hours Reason Method LER Number _ System Component Cause & Corrective Action to Prevent Recurrence
- 4. 04/03/88 S 294.6 A 1 SG Outage for Snubber Inspection and ID Steam Generator Leak Repair.
- 5. 04/18/88 F 65.7 A 3 6-88-002-00 --
Ex Trip On Power Range Flux Rate HIgh.
- 6. 04/23/88 - ---
B 5 --
Re-Adjust Power Range N.I. "High Flux Ex Trip" Setpoints.
ococcoo********
O Summary
TYPE Reason Method System & Comnonent F-Forcsd A-Equip Failure F-Admin 1-Manudl Exhibit F & H S-Sched B-Maint or Test G-Oper Error 2-Manual Scram Instructions for C-Refueling H-Other 3-Auto Scram Preparation of D-Regulatory Restriction 4-Continued Data Entry Sheet E-Operator Training 5-Reduced Load Licensee Event Report
& License Examination 9-OtLar (LER) File (NUREG-0161)
==
^ ._ ,_.
a.
E.
UNIOUE REPORTING REOUIREMENTS (UNIT 1) for the month of April 1988
- 1. Safety /Rellef valve operations for Unit One.
VALVES NO & TYPE PLANT DESCRIPTION DATE ACTUATED ACTUATION CONDITION OF EVENT None
- 2. Licensee generated changes to ODCM. (Y/N)
No
- 3. Indications of failed fuel. (Y/N)
Yes. I131 = 2.6 E-3 pcuries/ gram a
l l-l l
l l
(0625M/0062M-7)
- r. LICENSEE EVENT REPORTS (UNIT 1)
The following is a tabular sumenary of all Licensee Evant Reperts for Byron Nuclear Power Station, Unit One, submitted during the reporting period, April 1 through April 30, 1988. This information is provided pursuant to the reportable occurrence reporting requirements as set ferth in 10CFR 50.73.
Occurrence Licensee Event Report Numher Date Title of Occurrence None l
l (0625M/0062M-8) i
II. Monthly Report for Byron Unit 2 for the month of April 1988 A. Summary of Operatina Experience for Unit 2 The unit began this reporting period in Mode 1 at 94% power. The unit operated at power levels of up to 94% until 4/8/88 when power was reduced to investigate the erratic operation ol a feedwater pump governor valve. Power remained at approximately 54% until 4/10/88 '
when the unit was returned to 94% power. The unit operated at power levels of up to 94% for the rest of the reporting period.
(0625M/0062M-9) l t
I i
B. OPERATING DATA REPORT DOCKET NO.: 050-455 UNIT: Byron Two DATE: 05/10/88 COMPILED BY: D. J. Spitzer TELEPHONE: (815)234-5441 x2023 OPERATING STATUS
- 1. Reporting Period April 1988. Gross Hours: 720
- 2. Currently Authorized Power Level (MWt): 3411 Design Electrical Rating: 1175 (MWe-gross)
Design Electrical Rating: 1120 (MWe-net)
Max Dependable Capacity (MWe-net): NOT DETERMINED
- 3. Power Level to Which Restricted (If Any): 1055 (MWe-net)
- 4. Reasons for Restriction (If Any): Steam Generator Split Flow. (65 MW)
THIS MONTH YR TO DATE CUMULATIV'.*
- 5. Repott Period Hrs. 720 2904 6097
- 6. Rx Critical Hours 720 2889.6 5210.8
- 7. Rx Reserve Shutdown Hours 0 0 0
- 8. Hours Generator on Line 720 2691.2 4971.6
- 9. Unit Reserve Shutdown Hours 0 0 0
- 10. Gross Thermal Energy (MWH) 2215387 7660533 14132697
- 11. Gross Elec. Energy (MWH) 765010 2561438 4665749
- 12. Het Elec. Energy (MWH) 723376 2410588 4381489
- 13. Reactor Service Factor 100 99.5 85.6
- 14. Reactor Availability Factor 100 99.5 85.6
- 15. Unit Service Factor 100 92.7 81.5
- 16. Unit Availability Factor 100 92.7 81.5
- 17. Unit Capacity Factor (MDC not) N/A N/A N/A
- 18. Unit Capacity Factor (DER not) 89.7 74.1 64.2
- 19. Unit Forced Outage Hrs. 0 25.2 312.2
- 20. Unit Forced Outage Rate 0 1.0 6.0
- 21. Shutdowns Scheduled Over Next 6 Months:
- 22. If Shutdown at End of Report Period, Estimated Date of Startup:
- 23. Units in Test Status (Prior to Commercial Operation): None
- Note - The cumulative numbers do not reflect power generated prior to commercial service.
(0625M/0062M-10)
C. AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.: 050-455 UNIT: Byron Two DATE: 05/10/88 COMPILED BY: D. J. Spitzer TELEPHONE: (815)234-5441 x2023 MONTH: April, 1988 DAY AVERAGE DAILY POWER LEVEL (MWe-Net)
- 1. 1055 MW 16. 985 MW
- 2. 1050 MW 17, 1009 MW
- 3. 1013 MW 18. 1031 MW
- 4. 1045 MW 19. 1023 MW
- 5. 1046 MW 20. 1026 MW
- 6. 1061 MW 21. 1031 MW
- 7. 1061 MW 22. 995 AW
- 8. 944 MW 23. 1042 MW
- 9. 649 MW 24. ___ 1043 MW
- 10. 642 MN 25, 1023 MW
- 11. 1044 MW 26. 1042 MW
- 12. 1048_Kf 27, 1052 MW
- 13. 1034 MW 28. 1060 MW
- 14. 1032.NM 29. 987 MW __
- 15. 1021 MW 30. 1019 MW INSTRUCTICHS l
On this form list the average daily unit power level in MWe-Net for each day l in the reporting month. Compute to the nearest whole megawatt. These figures will be used to plot a graph for each reporting month. Note that when maximum i dependable capacity is used for the net electrical rating of the unit there may be occasions when the daily average power level exceeds the 100% line (or the restricted power level line.) In such casas the average daily unit power l output sheet should be footnoted to explain the apparent anomaly.
(0625M/0062M-11) l t
l l
~
Rcport Period April, 1988 UNIT SHUTDOWNS / REDUCTIONS
(UNIT 2) **************************
No. Date Iggn Hours Reason Method rEn Nn=her System Cn=ponent . Cause & Corrective Action to Prevent Recurrence
- 7. 04/08/88 A 5 FW 2C FW Pp 2C Feedwater Pump Low Pressure Governor Valve ocooceame****ee o Snamary
TYPE Reason Methnd System & Comnonent F-Forced A-Equip Failure F-Admin 1-Manual Exhibit F & H S-Sched B-Maint or Test G-Oper Error 2-Manual Scram Instructions for C-Refueling H-O the r 3-Auto Scram Preparation of D-Regulatory Restriction 4-Continued Data Entry Sheet E-Operator Training 5-Reduced Load Licensee Event Report i
& License Examination 9-Other (LER) File (NUREG-0161)
(0525M/0062M-12)
f .
E.
UNIOUE REPORTING REQUIREMENTS (UNIT 2) for the month of Aoril 1988
- 1. Safety / Relief valve operations for Unit Two.
VAINES NO & TYPE PLANT DESCRIPTION DAIE ACTUATED ACTUATION CONDITICM OF EVENT None
- 2. Licensee generated changes to ODCH. (Y/N)
No
- 3. Indications of failed fuel. (Y/N)
Yes. I131 = 6.4 E-3 pcuries/ gram (0625M/0062M-13)
- p r m v
/
.{ .
j -
' i
! F.
- . LICENSEE EVENT REPORTS (UNIT 2) -
l '
The following is a tabular summary of all Licensee Event Reports for Byroni Nuclear Power Station, Unit Two, submitted during the reporting period, Apell 1 through April 30, 1988. This information is provided pursuant to the; reportable occurrence reporting requirements as set forth in 10CIR 50.73. '
(
t Occurrence
- Licensee Event Report Number Date Title of Occurrence i 88-002-00 03/29/88 Component cooling water surge .[
tank level instrumentation \
discrepancies due to a design error.
88-003-00 03/29/88 Technical Specification action statement not satisfied during unintended 2B diesel generator i inoperability due to incorrect drawing.
.! 1 i
ti i
e
' t i
1
- (0625M/0061M-14) 4 t.
l 1
i v
ti
- p. -
6
. .- L .
.. C:mmtnwealth Edison Byron Nuclear Station 4450 North German Church Road Byron, Illinois 61010 0%
~9 g.s # ,p -
May 10, 1988 '
3 0* y C,e f LTR: BYRON 88-0457 File 2.7.200 Director, Office of Management Information and Program Control United Stater. Nuclear Regulatory Cormiission Washington, D.C. 20555 ATIN: E Docuatent Control Desk V Gentlemen Enclosed for your information is the Monthly Performance Report covering Byron Nuclear Power Station for the period April 1 through April 30, 1988.
Very truly yours, R. Plenlewicz Station Manager Byron Nuclear Power Station RP/DJS/bb 9\ s v
cc: A.B. Davis, NRC, Region III NRC Resident Inspector Byron
- Gary Wright, Ill. Dept. of Nuclear Safety
\
N T.J. Malman/K.L. Graesser L.D. Dutterfield ^\ T Nuclear Fuel Services, PWR Plant Support t[s L. Anastasia, Station Nuclear Engineering k, \
3 INPO Records Center
h l
! (0625M/0062M-1)