Attachment IV to ET 97-0071 Page 2 of 2 TABLE 3.3-1 (Continued)
ACTION STATEMENTS (Continued)
ACTION 5 - a.
With the number of OPERABLE channels one less than the Minimum Channels OPERABLE requirement, restore the inoperab,1,e4hannel to OPERABLE status within 48 ho f thees i perable channel is not rostored to OPERABLE within 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br />, then, within thg 49th ourApen the Rea reakerpnd suspend all operations h
g positive reactivity change "" '% r
.,~
b.
With no channels OPERABLE, open the Reactor Trip Breakers, suspend all operations involving positive reactivity changes and venfy compliance with the SHUTDOWN MARGIN requirements of Specification 3.1.1.1 within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> and every 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> thereafter.
ACTION 6 - With the number of OPERABLE channels one less than the Total Number of Channels, STARTUP and/or POWER OPERATION may proceed provided the following conditions are satisfied:
- a. The inoperable channel is placed in the tripped condition within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />; and
- b. The Minimum Channels OPERABLE requirement is met; hov.ever, the inuperable channel may be bypassed for up to 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> for surveillance testing of other channels per Specification 4.3.1.1.
ACTION 7 - With the number of OPERABLE Channels one less than tise Minimum Channe!s OPERABLE requirement, restore the inoperable channel to OPERABLE status within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> or be in at least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />; however, one channel may be bypassed for up to 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> for surveillance testin TWim 4.3.1.';, prov'ided the other channel i PERABLEspesaWe l
ACTION 8 - With less than the Minimum Number of Channels OPERABLE, within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> determine by observation of the associated permissive annunciator window (s) that the interlock is in its required state for the existing plant condition, or apply Specification 3.0.3.
AC TION 9 - With the number of OPERABLE Reactor Trip Breakers one less than the Minimum Channels OPERABLE requirement, be in at least HOT STANDBY within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />; however, one breaker may be bypassed for up to 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> for surveillance testing per Specification 4.3.1.1, provided the other breaker is OPERABLE.
ACTION 10 - With the number of OPERABLE channels one less than the Minimum Channels OPERABLE requirement, restore the inoperable channel to OPERABLE status within 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> or open the Reactor trip breakers within the next hour.
ACTION 11 - With the number of OPERABLE channels less than the Total Number of Channels, operation may continue provided the inoperable channels are placed in the tripped condition within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />.
WOLF CREEK - UNIT 1 3/4 3-6 Amendment No. f.3,36, 43,82,69 9708040190 970729 PDR ADOCK 05000482 P