ML20196C755

From kanterella
Jump to navigation Jump to search
Monthly Operating Rept for Jan 1988
ML20196C755
Person / Time
Site: Millstone 
Issue date: 01/31/1988
From: Newburgh G, Scace S
NORTHEAST NUCLEAR ENERGY CO., NORTHEAST UTILITIES
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
MP-11499, NUDOCS 8802160222
Download: ML20196C755 (5)


Text

.

AVERAGE DAILY UNIT POWER LEVEL I

DOCKET NO, 50-245 UNIT MILLSTONE 1 OATE 880202 COMPLETED BY G. NEWBURGH TELEPHONE (203) 447-1791 Extension 4400 MONTH JANUARY, 1988 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net)

(MWe-Net) 1 660 17 659 2

660 18 660 3

659 19 660 4

660 20 657 5

660 21 660 6

658 22 660 7

660 23 660 8

659 24 660 9

660 25 660 10 660 26 660 11 660 27 659 12 659 28 660 13 651 29 660

)

i 14 659 30 660 15 659 31 660 16 660 INSTRUCTIONS 1

On this format, list the average daily unit power level in MWe-Net for each day in the reporting month.

Compute to the nearest whole megawatt.

i 8802160222 880131 gDR ADOCK 050 5

[6

'~

OPERATING DATA REPORT

\\

DOCKET NO. 50-245 OATE 880202 COMPLETED BY G. NEWBURGH TELEPHONE (203) 447-1791 Extension 4400 OPERATING STATUS 1.

Unit Name: MILLSTONE 1 l Notes l

2.

Reporting Period: JANitARY,1988 l

l 3.

Licensed Thermal Power (MWt): 2011 l

l 4.

Nameplate Rating (Gross MWe): 662 l

l 5.

Design Electrical Rating (Net MWe): 660 l

l 6.

Maximum Dependable Capacity (Gross MWe):684 l l

7.

Maximum Dependable Capacity (Net MWe): 654 l l

8.

If Changes Occur in Capacity Ratings (Items Number 3 Through 7)

Since Last Report, Give Reasons:

N/A 9.

Power Level To Which Restricted, If Any (Net MWe):

N/A 10.

Reasons For Restrictions, If Any:

N/A This Month Yr.-to-Date Cumulative 11.

Hours In Reporting Period 744 744 150,552 12.

Number Of Hours Reactor Was Critical 744 744 117,070 13.

Reactor Reserve Shutdown Hours 0

0 3,283.3 14.

Hours Generator On-Line 744 744 113,936.5 15.

Unit Reserve Shutdown Hours 0

0 93.7 16.

Gross Thermal Energy Generated (MWH) 1,492,778 1,492,778 211,698,873 17.

Gross Elec. Energy Generated (MWH) 512,600 512,600 71,289,196 18.

Net Electrical Energy Generated (MWH) 490,642 490,642 68,005,362 19.

Unit Service Factor 100 100 75.7 l

20.

Unit Availability Factor 100 100 75.7 21.

Unit Capacity Factor (Using MDC Net) 100.8 100.8 69.1 l

22.

Unit Capacity Factor (Using DER Net) 99.9 99.9 68.4 l

23.

Unit Forced Outage Rate 0

0 11.2 24.

Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each):

N/A l

25.

If Shut Down At End Of Report Period, Estimated Date of Startup:

N/A 26.

Units In Test Status (Prior to Commercial Operation):

Forecast Achieved INITIAL CRITICALITY N/A N/A

)

l INITIAL ELECTRICITY N/A N/A COMMERCIAL OPERATION N/A N/A

DOCKET NO. 50-245 UNIT SHUTDOWNS AND POWER REDUCTIONS UNIT NAME MILLSIONE 1 DATE 880202.

COMPLETED BY G. NEWBURGH REPORT MONTH JANUARY, 1988 TELEPHONE (203) 447-1791 Extension 4400 No.

Date Type Duration Reason 2 Method of Licensee System Component Cause & Corrective l

(Hours)

Shutting Event Code 4 Code 5 Action to 8

Down Reactor Report #

Prevent Recurrence 4

N/A 4

1 2

3 4

F:

Forced Reason:

Method:

Exhibit G - Instructions 5:

Scheduled A-Equipment Failure (Explain) 1-Manual for Preparation of Data B-Maintenance or Test 2-Manual Scram Entry Sheets for Licensee C-Refueling 3-Automatic Scram Event Report (LER) File D-Regulatory Restriction 4-Continued from (NUREG-0161)

E-Operator Training & License Examination previous month F-edministrative 5-Power Reduction 5

G-Operational Error (Explain)

(Duration = 0)

Exhibit 1 -Same Source H-Other (Explain) 6-Other (Explain)

a REFUELING INFORMATION REQUEST i

1.

Name of facility:

Millstone 1 2.

Scheduled date for next refueling shutdown: MARCH, 1989 3.

Schedule date for restart following refueling: MAY, 1989 4

Will refueling or resumption of operation thereafter require a technical specification change or other license amenoment?

Yes, Technical Specification Changes Regarding:

(1) Maximum Average Planar Linear Heat Generating Rate (2) Maximum Critical Power Ratio 5.

Scheduled date(s) for submitting licensing action and supporting information:

Summer 1988 6.

Important licensing considerations associated with refueling, e.g.,

new or different fuel design or supplier, unreviewed design or performance analysis methods, significant changes in fuel design, new operating procedures:

196 GE88 Fuel Assemblies 7.

The number of fuel assemblies (a) in the core and (b) in the spent i

fuel storage pool:

(a)

In Core: (a) 580 (b) 1732 8.

The present licensed spent fuel pool storage capacity and the size of any increase in licensed storage capacity that has been requested or is planned, in number of fuel assemblies:

2184 As,semblies 9.

The projected date of the last refueling that can be discharged to the spent fuel pool assuming the present licensed capacity:

1987, Spent Fuel Pool, Full Core Off Load Capability is Reathed.

Temporary rack approved for installation if required: plans for additional capacity in progress.

j i

General Offices o Selden Street. Berlin. Connecticut a ca.n c'emo., w w n ccas-P.O. BOX 270 x.e a..m aoma co*~

HARTFORD. CONNECTICUT o6141 o270

$ $ $' M,"co,~.

(2o3) 66s sooO L

L J

February 10, 1988 HP-11499 Re:

10CFR50.71(a)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, D. C. 20555

Reference:

Provisional License DPR-21 Docket No. 50-245

Dear Sir:

In accordance with Millstone Unit 1 Technical Specification 6.9.1.6, the following monthly operating data report for Millstone Unit 1 is enclosed.

One additional copy of the report is enclosed.

Very truly yours, NORTHEAST NUCLEAR ENERGY C0'iPANY FOR:

Stephen E. Scace Station Superintendent Millstone Nuclear Power Station f

c-BY:

Carl d[Init Unit 3 Superintendent Millstone Nuclear Power Station SES/GSN:Ifg

Enclosures:

(4) cc:

Regional Administrator, Office of Inspection and Enforcement, Region I Director, Office of Inspection and Enforcement, Washington, D. C. (10)

Director, Office of Resource Management William Raymond, Senior Resident Inspector

%2 N

'(